1334 W 65TH ST 90044

Certificate Information: 1334 W 65TH ST 90044

Application / Permit
21014-10000-03859
Plan Check / Job No.
B21LA14210
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
Ground floor addition to (E) detached 1-car garage and conversion of entire building into an ADU per ordinance 186,481.
Permit Issued
Issued on 11/7/2022
Issuing Office
Current Status
CofO Issued on 7/8/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 8/6/2021 APPLICANT
Assigned to Plan Check Engineer 8/8/2021 JOE VO
Corrections Issued 8/10/2021 HELEN NGUYEN
Applicant returned to address corrections 7/2/2022 JOE VO
Plan Check Approved 10/8/2022 JOE VO
Issued 11/7/2022 APPLICANT
CofO in Progress 6/29/2023 ENRIQUE MIRELES
CofO in Progress 6/29/2023 ENRIQUE MIRELES
Permit Finaled 7/8/2023 DEROLD HAUFF
CofO Issued 7/8/2023 DEROLD HAUFF
Permit Finaled 7/8/2023 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 1/20/2022 CINDY QI
Eng Process Fee Ord 176,300 Cleared 2/4/2022 CINDY QI
Sewer availability Cleared 2/4/2022 CINDY QI
Roof/Waste drainage to street Cleared 4/28/2022 CINDY QI
Construction within easement Cleared 8/4/2022 RIDWAN HARDY

Contact Information

Contractor Owner-Builder       ,

Inspector Information

BARRY HACHE, (213) 202-9851 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 12/22/2022 Approved ENRIQUE MIRELES
Underground Mechanical 12/22/2022 Approved ENRIQUE MIRELES
Footing/Foundation/Slab 12/28/2022 Approved ENRIQUE MIRELES
BUILDING-Rough-Frame 2/17/2023 Not Ready for Inspection ENRIQUE MIRELES
Floor/Roof Diaphrgm/Shear Wall 2/17/2023 Approved ENRIQUE MIRELES
Gas Test 2/17/2023 Approved ENRIQUE MIRELES
Green Building Rough 2/17/2023 Approved ENRIQUE MIRELES
Shower Pan 2/17/2023 Approved ENRIQUE MIRELES
Wood Frame 2/17/2023 Approved ENRIQUE MIRELES
ELECTRICAL-Rough 2/23/2023 Approved ENRIQUE MIRELES
Floor/Roof Diaphrgm/Shear Wall 2/23/2023 Approved ENRIQUE MIRELES
HVAC-Rough 2/23/2023 Approved ENRIQUE MIRELES
PLUMBING-Rough 2/23/2023 Approved ENRIQUE MIRELES
Interior/Exterior Lathing 3/1/2023 Corrections Issued ENRIQUE MIRELES
Insulation 3/6/2023 Approved ENRIQUE MIRELES
Interior/Exterior Lathing 3/6/2023 Approved ENRIQUE MIRELES
Drywall Nailing 3/13/2023 Approved ENRIQUE MIRELES
Interior/Exterior Lathing 3/15/2023 Approved ENRIQUE MIRELES
Gas Test 3/23/2023 Not Ready for Inspection ENRIQUE MIRELES
Underground Mechanical 3/23/2023 Not Ready for Inspection ENRIQUE MIRELES
Underground Mechanical 3/29/2023 Approved ENRIQUE MIRELES
BUILDING-Rough-Frame 5/15/2023 Approved ENRIQUE MIRELES
Final 5/15/2023 Corrections Issued ENRIQUE MIRELES
Green Building Final 5/15/2023 Approved ENRIQUE MIRELES
SGSOV-Seismic Gas S/O Valve 5/15/2023 SGSOV Approved ENRIQUE MIRELES
Smoke Detectors 5/15/2023 Approved ENRIQUE MIRELES
Final 5/23/2023 Corrections Issued ENRIQUE MIRELES
Final 6/1/2023 Corrections Issued ENRIQUE MIRELES