4451 W FINLEY AVE 90027
Certificate Information: 4451 W FINLEY AVE 90027
- Application / Permit
- 21014-10000-03823
- Plan Check / Job No.
- B21LA14074
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- (N) 2-STORY ADDITION TO (E) 1-STORY SINGLE FAMILY DWELLING
- Permit Issued
- Issued on 10/13/2021
- Issuing Office
- Current Status
- CofO Issued on 7/10/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/28/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 8/19/2021 | DANIEL YIP |
| Corrections Issued | 8/24/2021 | DANIEL YIP |
| Quality Review Completed | 8/26/2021 | JASON HEALEY |
| Plan Check Approved | 10/8/2021 | DANIEL YIP |
| Issued | 10/13/2021 | APPLICANT |
| Building Plans Picked Up | 10/14/2021 | APPLICANT |
| CofO in Progress | 4/17/2023 | PATRICK LIEBREGT |
| CofO Issued | 7/10/2023 | DANIEL SANCHEZ |
| Permit Finaled | 7/10/2023 | DANIEL SANCHEZ |
Permit Application Clearance Information
| Roof/Waste drainage to street | Cleared | 9/23/2021 | CELINA MORENO |
| Sewer availability | Cleared | 9/23/2021 | CELINA MORENO |
| Eng Process Fee Ord 176,300 | Cleared | 9/28/2021 | CELINA MORENO |
| GPI Written Notices | Cleared | 9/29/2021 | ALLEN MANALANSAN |
| Grading Pre-Inspection | Cleared | 9/29/2021 | ALLEN MANALANSAN |
Contact Information
| Contractor | J B New Construction Inc; Lic. No.: 923970-B | 13923 S CRENSHAW BLVD HAWTHORNE, CA 90250 |
| Engineer | Garcia,, Francisco Diaz; Lic. No.: C88029 | 2919 BURBANK BLVD STE D BURBANK, CA 91505 |
Inspector Information
| JOEL ORDAZ, (213) 252-3049 | Office Hours: 7:00-8:00 AM MON-FRI |
| PTOLEMY HILL, (213) 252-3049 | Office Hours: 7:00-8:00 AM MON-FRI |
| JONATHAN FRANCHINI, (213) 252-3049 | Office Hours: 7:00-8:00 AM MON-FRI |
| ARAM AVAKIAN, (213) 252-3049 | Office Hours: 7:00-8:00 AM MON-FRI |
| EDMOND DECKERT, (213) 252-3049 | Office Hours: 7:00-8:00 AM MON-FRI |
| TIMOTHY KEY, (213) 252-3049 | Office Hours: 7:00-8:00 AM MON-FRI |
| ROBERT CHAVEZ, (213) 252-3049 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Floor/Roof Diaphrgm/Shear Wall | 10/19/2021 | Partial Approval | JOHN TCHANG |
| Pre-Inspection | 10/19/2021 | Approved | JOHN TCHANG |
| Excavation/Setback/Form/Re-Bar | 11/24/2021 | Corrections Issued | GORDON ZUBER |
| Excavation/Setback/Form/Re-Bar | 12/1/2021 | Approved | JOHN TCHANG |
| BUILDING-Rough-Frame | 3/25/2022 | Corrections Issued | ZEYDI STEWART |
| Green Building Rough | 3/25/2022 | Corrections Issued | ZEYDI STEWART |
| Green Building Rough | 5/6/2022 | Not Ready for Inspection | ZEYDI STEWART |
| BUILDING-Rough-Frame | 5/11/2022 | Not Ready for Inspection | PIERRE VEGA |
| BUILDING-Rough-Frame | 6/6/2022 | Corrections Issued | ZEYDI STEWART |
| Green Building Rough | 6/6/2022 | Approved | ZEYDI STEWART |
| HVAC-Rough | 6/6/2022 | Corrections Issued | ZEYDI STEWART |
| PLUMBING-Rough | 6/9/2022 | Not Ready for Inspection | ZEYDI STEWART |
| HVAC-Rough | 6/13/2022 | Partial Approval | ZEYDI STEWART |
| Insulation | 6/16/2022 | Not Ready for Inspection | ZEYDI STEWART |
| HVAC-Rough | 7/11/2022 | Corrections Issued | ZEYDI STEWART |
| PLUMBING-Rough | 7/11/2022 | Corrections Issued | ZEYDI STEWART |
| Special/Order Compliance | 7/11/2022 | Approved | ROBERT MINASSIANS |
| Drywall Nailing | 7/15/2022 | Approved | ZEYDI STEWART |
| Special/Order Compliance | 8/3/2022 | Not Ready for Inspection | PIERRE VEGA |
| ELECTRICAL-Rough | 8/4/2022 | Approved | ZEYDI STEWART |
| HVAC-Rough | 8/4/2022 | Partial Approval | ZEYDI STEWART |
| PLUMBING-Rough | 8/4/2022 | Approved | ZEYDI STEWART |
| Pre-Inspection | 8/4/2022 | Approved | ZEYDI STEWART |
| Special/Order Compliance | 8/4/2022 | Partial Inspection | PIERRE VEGA |
| BUILDING-Rough-Frame | 8/23/2022 | Not Ready for Inspection | ZEYDI STEWART |
| Special/Order Compliance | 8/23/2022 | Partial Inspection | PIERRE VEGA |
| BUILDING-Rough-Frame | 8/29/2022 | Not Ready for Inspection | COREY HUPP |
| BUILDING-Rough-Frame | 9/15/2022 | Approved | ANDEY CHAPARRO |
| Final | 12/29/2022 | Corrections Issued | PATRICK LIEBREGT |
| Footing/Foundation/Slab | 12/29/2022 | Approved | PATRICK LIEBREGT |
| Green Building Final | 12/29/2022 | Approved | PATRICK LIEBREGT |
| SGSOV-Seismic Gas S/O Valve | 12/29/2022 | SGSOV Approved | PATRICK LIEBREGT |
| Smoke Detectors | 12/29/2022 | Approved | PATRICK LIEBREGT |
| Final | 4/10/2023 | Conditional Approval | PATRICK LIEBREGT |