1015 3/4 E 28TH ST 90011

Certificate Information: 1015 3/4 E 28TH ST 90011

Application / Permit
21014-10000-03810
Plan Check / Job No.
B21LA14042
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
PROPOSED 1-STORY A.D.U. PER STATE LAW.
Permit Issued
Issued on 2/25/2022
Issuing Office
Metro
Current Status
CofO Issued on 2/8/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 8/19/2021 APPLICANT
Assigned to Plan Check Engineer 8/23/2021 LAWRENCE QUIRANTE
Corrections Issued 8/23/2021 LAWRENCE QUIRANTE
Plan Check Approved 12/9/2021 ZAW HAN
Building Plans Picked Up 12/10/2021 APPLICANT
Issued 2/25/2022 APPLICANT
CofO in Progress 11/14/2023 ENRIQUE MIRELES
CofO in Progress 11/14/2023 ENRIQUE MIRELES
No Progress 11/21/2023 DEROLD HAUFF
CofO in Progress 2/8/2024 DEROLD HAUFF
Permit Finaled 2/8/2024 DEROLD HAUFF
CofO Issued 2/8/2024 DEROLD HAUFF
Permit Finaled 2/8/2024 DEROLD HAUFF

Permit Application Clearance Information

City Hist. Cultural Monument Cleared 10/28/2021 LAMBERT GIESSINGER
Roof/Waste drainage to street Cleared 10/30/2021 STEVE MELGAR
Address approval Cleared 11/15/2021 STEVE MELGAR
Eng Process Fee Ord 176,300 Cleared 11/17/2021 STEVE MELGAR
Sewer availability Cleared 11/17/2021 STEVE MELGAR

Contact Information

Contractor Figueroa Construction Inc; Lic. No.: 950160-B 2660 CIMARRON STREET      LOS ANGELES, CA 90018

Inspector Information

ALEJANDRO DE ARTOLA, (213) 202-3128 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 3/1/2022 Partial Approval JOAQUIN GREENOUGH
Footing/Foundation/Slab 3/9/2022 Corrections Issued HORACE FULTZ
Footing/Foundation/Slab 3/14/2022 Approved JOAQUIN GREENOUGH
BUILDING-Rough-Frame 4/5/2022 Corrections Issued JOAQUIN GREENOUGH
Green Building Rough 4/5/2022 Corrections Issued JOAQUIN GREENOUGH
Verify Sprinkler Sign Off 4/5/2022 Not Ready for Inspection JOAQUIN GREENOUGH
BUILDING-Rough-Frame 4/15/2022 Not Ready for Inspection HORACE FULTZ
Green Building Rough 4/15/2022 Not Ready for Inspection HORACE FULTZ
PLUMBING-Rough 4/15/2022 Not Ready for Inspection HORACE FULTZ
Verify Sprinkler Sign Off 4/15/2022 Approved HORACE FULTZ
Floor/Roof Diaphrgm/Shear Wall 4/19/2022 Partial Approval JOAQUIN GREENOUGH
Wood Frame 4/19/2022 Partial Approval JOAQUIN GREENOUGH
ELECTRICAL-Rough 5/25/2022 Approved HORACE FULTZ
PLUMBING-Rough 5/25/2022 Approved HORACE FULTZ
BUILDING-Rough-Frame 6/1/2022 Approved JOAQUIN GREENOUGH
Green Building Rough 6/1/2022 Approved JOAQUIN GREENOUGH
Insulation 6/1/2022 Not Ready for Inspection JOAQUIN GREENOUGH
Floor/Roof Diaphrgm/Shear Wall 7/5/2022 Partial Approval HORACE FULTZ
ELECTRICAL-Rough 7/6/2022 Partial Inspection ANTHONY EGSON
Drywall Nailing 7/14/2022 Approved JOAQUIN GREENOUGH
Interior/Exterior Lathing 8/1/2022 Approved JOAQUIN GREENOUGH
Shower Pan 8/1/2022 Approved JOAQUIN GREENOUGH
ELECTRICAL-Final 10/12/2023 Corrections Issued ALEJANDRO DE ARTOLA
Green Building Final 10/12/2023 Corrections Issued ALEJANDRO DE ARTOLA
PLUMBING-Final 10/12/2023 Corrections Issued ALEJANDRO DE ARTOLA
SGSOV-Seismic Gas S/O Valve 10/12/2023 SGSOV Not Ready ALEJANDRO DE ARTOLA
Smoke Detectors 10/12/2023 Corrections Issued ALEJANDRO DE ARTOLA
Final 11/1/2023 Corrections Issued ALEJANDRO DE ARTOLA
ELECTRICAL-Final 11/13/2023 Approved ENRIQUE MIRELES
Final 11/13/2023 OK to Issue CofO ENRIQUE MIRELES
Green Building Final 11/13/2023 Approved ENRIQUE MIRELES
PLUMBING-Final 11/13/2023 Approved ENRIQUE MIRELES
SGSOV-Seismic Gas S/O Valve 11/13/2023 SGSOV Approved ENRIQUE MIRELES
Service/Power Release 11/13/2023 Approved ENRIQUE MIRELES
Smoke Detectors 11/13/2023 Approved ENRIQUE MIRELES