12047 W ANETA ST 90230
Certificate Information: 12047 W ANETA ST 90230
- Application / Permit
- 21014-10000-03808
- Plan Check / Job No.
- B21LA14036
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- (N) 1ST AND 2ND STORY ADDITION TO (E) 1-STORY SINGLE FAMILY DWELLING W/ 2-CAR GARAGE
- Permit Issued
- Issued on 1/14/2022
- Issuing Office
- Metro
- Current Status
- CofO Issued on 1/24/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 8/10/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 8/26/2021 | DANIEL YIP |
| Corrections Issued | 8/31/2021 | DANIEL YIP |
| Quality Review Completed | 9/3/2021 | JASON HEALEY |
| Applicant returned to address corrections | 11/5/2021 | DANIEL YIP |
| Plan Check Approved | 12/8/2021 | DANIEL YIP |
| Issued | 1/14/2022 | APPLICANT |
| Building Plans Picked Up | 1/19/2022 | APPLICANT |
| CofO in Progress | 1/19/2023 | HERBERT GIRON |
| No Progress | 1/21/2023 | RICHARD STEINBACH |
| CofO in Progress | 1/24/2023 | RICHARD STEINBACH |
| Permit Finaled | 1/24/2023 | DANIEL ORRANTE |
| CofO Issued | 1/24/2023 | DANIEL ORRANTE |
| Permit Finaled | 1/24/2023 | DANIEL ORRANTE |
Permit Application Clearance Information
| Roof/Waste drainage to street | Cleared | 9/15/2021 | HISASHI KOBAYAKAWA |
| Sewer availability | Cleared | 9/15/2021 | HISASHI KOBAYAKAWA |
| Eng Process Fee Ord 176,300 | Cleared | 9/20/2021 | HISASHI KOBAYAKAWA |
| Specific Plan | Cleared | 11/3/2021 | PEDRO AYALA |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| MORRIS JACKSON, (310) 914-3885 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 4/6/2022 | Approved | MICHAEL PELHAM |
| Footing/Foundation/Slab | 4/12/2022 | Conditional Approval | DAVID FEILER |
| METHANE-Barrier | 4/12/2022 | Approved | DAVID FEILER |
| METHANE-Subgrade | 4/12/2022 | Approved | DAVID FEILER |
| Floor/Roof Diaphrgm/Shear Wall | 4/21/2022 | Partial Approval | JESUS RODRIGUEZ |
| PLUMBING-Rough | 4/21/2022 | Approved | JESUS RODRIGUEZ |
| Floor/Roof Diaphrgm/Shear Wall | 5/9/2022 | Conditional Approval | JESUS RODRIGUEZ |
| Insulation | 5/9/2022 | Partial Approval | JESUS RODRIGUEZ |
| ELECTRICAL-Rough | 8/3/2022 | Corrections Issued | HERBERT GIRON |
| HVAC-Rough | 8/3/2022 | Corrections Issued | HERBERT GIRON |
| PLUMBING-Rough | 8/3/2022 | Approved | HERBERT GIRON |
| ELECTRICAL-Rough | 8/8/2022 | Approved | HERBERT GIRON |
| Floor/Roof Diaphrgm/Shear Wall | 8/8/2022 | Conditional Approval | HERBERT GIRON |
| HVAC-Rough | 8/8/2022 | Approved | HERBERT GIRON |
| Floor/Roof Diaphrgm/Shear Wall | 8/15/2022 | Approved | HERBERT GIRON |
| Floor/Roof Diaphrgm/Shear Wall | 8/18/2022 | Approved | HERBERT GIRON |
| BUILDING-Rough-Frame | 8/25/2022 | Not Ready for Inspection | HERBERT GIRON |
| Green Building Rough | 8/25/2022 | Not Ready for Inspection | HERBERT GIRON |
| Interior/Exterior Lathing | 8/25/2022 | Not Ready for Inspection | HERBERT GIRON |
| MERV13>=Rough | 8/25/2022 | Approved | HERBERT GIRON |
| METHANE-Rough | 8/25/2022 | Approved | HERBERT GIRON |
| BUILDING-Rough-Frame | 9/6/2022 | Partial Approval | HERBERT GIRON |
| Green Building Rough | 9/6/2022 | Approved | HERBERT GIRON |
| Interior/Exterior Lathing | 9/6/2022 | Partial Approval | HERBERT GIRON |
| Insulation | 9/9/2022 | Approved | HERBERT GIRON |
| Drywall Nailing | 9/16/2022 | Approved | HERBERT GIRON |
| Shower Pan | 9/16/2022 | Approved | HERBERT GIRON |
| Interior/Exterior Lathing | 9/23/2022 | Approved | HERBERT GIRON |
| Gas Test | 12/16/2022 | Corrections Issued | HERBERT GIRON |
| Underground Mechanical | 12/16/2022 | Approved | HERBERT GIRON |
| Gas Test | 12/20/2022 | Approved | HERBERT GIRON |
| ELECTRICAL-Final | 1/13/2023 | Corrections Issued | HERBERT GIRON |
| HVAC-Rough | 1/13/2023 | Corrections Issued | HERBERT GIRON |
| PLUMBING-Final | 1/13/2023 | Corrections Issued | HERBERT GIRON |
| Smoke Detectors | 1/13/2023 | Approved | HERBERT GIRON |
| ELECTRICAL-Final | 1/18/2023 | Approved | HERBERT GIRON |
| Final | 1/18/2023 | OK to Issue CofO | HERBERT GIRON |
| Footing/Foundation/Slab | 1/18/2023 | Approved | HERBERT GIRON |
| Green Building Final | 1/18/2023 | Approved | HERBERT GIRON |
| HVAC-Final | 1/18/2023 | Approved | HERBERT GIRON |
| MERV13>=Final | 1/18/2023 | Approved | HERBERT GIRON |
| PLUMBING-Final | 1/18/2023 | Approved | HERBERT GIRON |
| SGSOV-Seismic Gas S/O Valve | 1/18/2023 | SGSOV Approved | HERBERT GIRON |
| Service/Power Release | 1/18/2023 | Approved | HERBERT GIRON |