5154 S BRYNHURST AVE 90043
Certificate Information: 5154 S BRYNHURST AVE 90043
- Application / Permit
- 21014-10000-03798
- Plan Check / Job No.
- B21LA14028
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- DETATCGED GARAGE CONVERSION ADU AND ADDITION PER ORDINANCE AND LAMC 12.22 A 33(c) &(d).ALL WORK PER WFPP
- Permit Issued
- Issued on 9/15/2022
- Issuing Office
- Metro
- Current Status
- CofO Issued on 6/4/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 9/1/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 9/2/2021 | RAHEL BEYENE |
| Corrections Issued | 9/2/2021 | RAHEL BEYENE |
| Applicant returned to address corrections | 3/12/2022 | ZAW HAN |
| Plan Check Approved | 3/15/2022 | ZAW HAN |
| Building Plans Picked Up | 3/17/2022 | APPLICANT |
| Issued | 9/15/2022 | APPLICANT |
| CofO in Progress | 6/4/2024 | ANTHONY EGSON |
| Permit Finaled | 6/4/2024 | DEROLD HAUFF |
| CofO Issued | 6/4/2024 | DEROLD HAUFF |
| Permit Finaled | 6/4/2024 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 11/10/2021 | ABEL CASILLAS |
| Roof/Waste drainage to street | Cleared | 11/10/2021 | ABEL CASILLAS |
| Eng Process Fee Ord 176,300 | Cleared | 11/15/2021 | ABEL CASILLAS |
| Sewer availability | Cleared | 11/15/2021 | ABEL CASILLAS |
| Construction near power lines | Cleared | 3/4/2022 | RIDWAN HARDY |
Contact Information
| Contractor | De La Rosa Construction; Lic. No.: 855010-B | 3627 E FIRST STREET LOS ANGELES, CA 90063 |
Inspector Information
| LUIS CASTRO, (213) 202-3436 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 10/12/2022 | Partial Inspection | ANTHONY EGSON |
| Underground Mechanical | 1/13/2023 | Partial Inspection | ANTHONY EGSON |
| Underground Mechanical | 1/23/2023 | Partial Approval | ANTHONY EGSON |
| Footing/Foundation/Slab | 1/31/2023 | Corrections Issued | ANTHONY EGSON |
| Underground Mechanical | 1/31/2023 | Approved | ANTHONY EGSON |
| Footing/Foundation/Slab | 2/2/2023 | Approved | ANTHONY EGSON |
| ELECTRICAL-Rough | 3/6/2023 | Corrections Issued | ANTHONY EGSON |
| HVAC-Rough | 3/6/2023 | Not Ready for Inspection | ANTHONY EGSON |
| PLUMBING-Rough | 3/6/2023 | Corrections Issued | ANTHONY EGSON |
| Wood Frame | 3/6/2023 | Corrections Issued | ANTHONY EGSON |
| ELECTRICAL-Rough | 3/10/2023 | Corrections Issued | ANTHONY EGSON |
| HVAC-Rough | 3/10/2023 | Corrections Issued | ANTHONY EGSON |
| PLUMBING-Rough | 3/10/2023 | Partial Approval | ANTHONY EGSON |
| Wood Frame | 3/10/2023 | Not Ready for Inspection | ANTHONY EGSON |
| ELECTRICAL-Rough | 3/16/2023 | Not Ready for Inspection | ANTHONY EGSON |
| Floor/Roof Diaphrgm/Shear Wall | 3/16/2023 | Partial Approval | ANTHONY EGSON |
| HVAC-Rough | 3/16/2023 | Not Ready for Inspection | ANTHONY EGSON |
| PLUMBING-Rough | 3/16/2023 | Not Ready for Inspection | ANTHONY EGSON |
| ELECTRICAL-Rough | 3/24/2023 | Approved | ANTHONY EGSON |
| HVAC-Rough | 3/24/2023 | Approved | ANTHONY EGSON |
| PLUMBING-Rough | 3/24/2023 | Approved | ANTHONY EGSON |
| Wood Frame | 3/24/2023 | Approved | ANTHONY EGSON |
| Interior/Exterior Lathing | 4/3/2023 | Approved | ANTHONY EGSON |
| Insulation | 4/10/2023 | Approved | MICHAEL LEWIS |
| Drywall Nailing | 4/24/2023 | Approved | BRENDAN MORELLI |
| Green Building Rough | 4/24/2023 | Approved | BRENDAN MORELLI |
| Shower Pan | 4/24/2023 | Approved | BRENDAN MORELLI |
| Interior/Exterior Lathing | 5/4/2023 | Approved | ANTHONY EGSON |
| BUILDING-Rough-Frame | 10/16/2023 | Approved | ANTHONY EGSON |
| ELECTRICAL-Final | 10/16/2023 | Not Ready for Inspection | ANTHONY EGSON |
| Final | 10/16/2023 | Corrections Issued | ANTHONY EGSON |
| Green Building Final | 10/16/2023 | Not Ready for Inspection | ANTHONY EGSON |
| HVAC-Final | 10/16/2023 | Not Ready for Inspection | ANTHONY EGSON |
| PLUMBING-Final | 10/16/2023 | Not Ready for Inspection | ANTHONY EGSON |
| SGSOV-Seismic Gas S/O Valve | 10/16/2023 | SGSOV Not Ready | ANTHONY EGSON |
| Smoke Detectors | 10/16/2023 | Approved | ANTHONY EGSON |
| ELECTRICAL-Final | 2/23/2024 | Not Ready for Inspection | ANTHONY EGSON |
| Final | 2/23/2024 | Corrections Issued | ANTHONY EGSON |
| Green Building Final | 2/23/2024 | Not Ready for Inspection | ANTHONY EGSON |
| HVAC-Final | 2/23/2024 | Not Ready for Inspection | ANTHONY EGSON |
| PLUMBING-Final | 2/23/2024 | Not Ready for Inspection | ANTHONY EGSON |
| SGSOV-Seismic Gas S/O Valve | 2/23/2024 | SGSOV Approved | ANTHONY EGSON |
| ELECTRICAL-Final | 4/24/2024 | Approved | ANTHONY EGSON |
| PLUMBING-Final | 4/24/2024 | Corrections Issued | ANTHONY EGSON |
| ELECTRICAL-Final | 4/26/2024 | Approved | ANTHONY EGSON |
| Final | 4/26/2024 | Not Ready for Inspection | ANTHONY EGSON |
| Green Building Final | 4/26/2024 | Approved | ANTHONY EGSON |
| PLUMBING-Final | 4/26/2024 | Approved | ANTHONY EGSON |
| Final | 5/10/2024 | Partial Approval | ANTHONY EGSON |
| Final | 6/4/2024 | OK to Issue CofO | ANTHONY EGSON |
| Service/Power Release | 6/4/2024 | Approved | ANTHONY EGSON |