8053 S KENTWOOD AVE 90045

Certificate Information: 8053 S KENTWOOD AVE 90045

Application / Permit
21014-10000-03793
Plan Check / Job No.
B21LA14014
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
PROPOSED ADDITION TO SINGLE FAMILY DWELLING
Permit Issued
Issued on 1/20/2022
Issuing Office
Current Status
CofO Issued on 3/3/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 7/28/2021 APPLICANT
Assigned to Plan Check Engineer 8/4/2021 SINA KHOSRAVI
Corrections Issued 8/4/2021 SINA KHOSRAVI
Applicant returned to address corrections 9/9/2021 SINA KHOSRAVI
Plan Check Approved 12/21/2021 DANIEL SANJUAN
Issued 1/20/2022 APPLICANT
Building Plans Picked Up 3/15/2022 APPLICANT
CofO in Progress 2/22/2023 HERBERT GIRON
Permit Finaled 3/3/2023 DANIEL ORRANTE
CofO Issued 3/3/2023 DANIEL ORRANTE
Permit Finaled 3/3/2023 DANIEL ORRANTE

Permit Application Clearance Information

Sewer availability Cleared 8/18/2021 STEVE MELGAR
Low Impact Development Cleared 11/8/2021 CHRIS VONG
Roof/Waste drainage to street Cleared 11/17/2021 DINAH GARIN
Eng Process Fee Ord 176,300 Cleared 11/18/2021 DINAH GARIN

Contact Information

Contractor J M E Construction; Lic. No.: 921816-B 1450 RONAN AVENUE      WILMINGTON, CA 90744
Engineer Castillo,, Margarito; Lic. No.: S4808 1205 PINE AVENUE      LONG BEACH, CA 90813

Inspector Information

MORRIS JACKSON, (310) 914-3885 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 4/1/2022 Partial Inspection JESUS RODRIGUEZ
Footing/Foundation/Slab 4/1/2022 Approved BOBBY KEY
Special/Order Compliance 4/1/2022 Corrections Issued BOBBY KEY
Floor/Roof Diaphrgm/Shear Wall 4/7/2022 Not Ready for Inspection RYAN SALAZAR
Insulation 4/7/2022 Partial Approval RYAN SALAZAR
PLUMBING-Rough 4/7/2022 Partial Approval RYAN SALAZAR
BUILDING-Rough-Frame 6/24/2022 Partial Approval STEPHANIE SWANSON
ELECTRICAL-Rough 6/24/2022 Corrections Issued STEPHANIE SWANSON
Floor/Roof Diaphrgm/Shear Wall 6/24/2022 Approved STEPHANIE SWANSON
Green Building Rough 6/24/2022 Not Ready for Inspection STEPHANIE SWANSON
HVAC-Rough 6/24/2022 Corrections Issued STEPHANIE SWANSON
METHANE-Rough 6/24/2022 Approved STEPHANIE SWANSON
PLUMBING-Rough 6/24/2022 Approved STEPHANIE SWANSON
BUILDING-Rough-Frame 7/11/2022 Not Ready for Inspection JESUS RODRIGUEZ
ELECTRICAL-Rough 7/11/2022 Approved JESUS RODRIGUEZ
Green Building Rough 7/11/2022 Not Ready for Inspection JESUS RODRIGUEZ
HVAC-Rough 7/11/2022 Approved JESUS RODRIGUEZ
BUILDING-Rough-Frame 7/20/2022 Not Ready for Inspection HERBERT GIRON
Green Building Rough 7/20/2022 Corrections Issued HERBERT GIRON
Insulation 7/20/2022 Not Ready for Inspection HERBERT GIRON
Interior/Exterior Lathing 7/20/2022 Partial Approval HERBERT GIRON
BUILDING-Rough-Frame 7/25/2022 Approved HERBERT GIRON
Green Building Rough 7/25/2022 Approved HERBERT GIRON
Insulation 7/25/2022 Approved HERBERT GIRON
Drywall Nailing 8/4/2022 Approved HERBERT GIRON
Shower Pan 8/4/2022 Approved HERBERT GIRON
Interior/Exterior Lathing 8/12/2022 Approved HERBERT GIRON
ELECTRICAL-Final 2/15/2023 Corrections Issued HERBERT GIRON
Final 2/15/2023 Corrections Issued HERBERT GIRON
Green Building Final 2/15/2023 Approved HERBERT GIRON
HVAC-Final 2/15/2023 Approved HERBERT GIRON
PLUMBING-Final 2/15/2023 Approved HERBERT GIRON
SGSOV-Seismic Gas S/O Valve 2/15/2023 SGSOV Approved HERBERT GIRON
Service/Power Release 2/15/2023 Not Ready for Inspection HERBERT GIRON
Smoke Detectors 2/15/2023 Approved HERBERT GIRON
Final 2/21/2023 OK to Issue CofO HERBERT GIRON
Service/Power Release 2/21/2023 Approved HERBERT GIRON