1468 E MONTECITO DR 90031

Certificate Information: 1468 E MONTECITO DR 90031

Application / Permit
21014-10000-03769
Plan Check / Job No.
B21LA13918
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
167 S.F. ADDITION TO AN (E) LIVING ROOM WITH ROOF DECK ON TOP & 256 S.F. (N) OPEN DECK.
Permit Issued
Issued on 5/16/2022
Issuing Office
Metro
Current Status
CofO Issued on 5/15/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 7/30/2021 APPLICANT
Assigned to Plan Check Engineer 9/2/2021 CRYSTEL MAALOUF
Corrections Issued 9/20/2021 CRYSTEL MAALOUF
Quality Review Completed 9/29/2021 KEN GILL
Building Plans Picked Up 10/6/2021 APPLICANT
Plan Check Approved 5/4/2022 CRYSTEL MAALOUF
Issued 5/16/2022 APPLICANT
CofO in Progress 5/9/2025 LILIANA PORTILLO
Permit Finaled 5/15/2025 DEROLD HAUFF
CofO Issued 5/15/2025 DEROLD HAUFF
Permit Finaled 5/15/2025 DEROLD HAUFF

Permit Application Clearance Information

Grading Pre-Inspection Cleared 2/24/2022 VASIL MIHALEV
"D" conditions Cleared 2/28/2022 LOUIS ORTEGA
"Q" conditions Cleared 2/28/2022 LOUIS ORTEGA
ZI Cleared 2/28/2022 LOUIS ORTEGA
GPI Written Notices Cleared 5/4/2022 CRYSTEL MAALOUF

Contact Information

Contractor Cpc Builders Inc; Lic. No.: 881106-B 2315 NORTH LAMER STREET      BURBANK, CA 91504
Engineer Le,, Thang Huu; Lic. No.: S4978 507 MAGELLAN RD      ARCADIA, CA 91007

Inspector Information

No Data Available.

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 5/19/2022 Conditional Approval AMY COLIN
Footing/Foundation/Slab 6/10/2022 Approved AMY COLIN
Floor/Roof Diaphrgm/Shear Wall 7/7/2022 Corrections Issued AMY COLIN
Insulation 7/8/2022 Approved AMY COLIN
Deputy Wood Construction 9/1/2022 Conditional Approval AMY COLIN
BUILDING-Rough-Frame 10/13/2022 Approved AMY COLIN
Green Building Rough 10/13/2022 Not Ready for Inspection AMY COLIN
Interior/Exterior Lathing 10/20/2022 Approved AMY COLIN
Insulation 11/4/2022 Approved AMY COLIN
Drywall Nailing 11/14/2022 Approved AMY COLIN
BUILDING-Rough-Frame 4/12/2023 Approved AMY COLIN
Final 4/12/2023 Corrections Issued AMY COLIN
Green Building Final 4/12/2023 Approved AMY COLIN
Green Building Rough 4/12/2023 Approved AMY COLIN
SGSOV-Seismic Gas S/O Valve 4/12/2023 SGSOV Not Ready AMY COLIN
Smoke Detectors 4/12/2023 Corrections Issued AMY COLIN
Final 4/21/2023 Not Ready for Inspection AMY COLIN
SGSOV-Seismic Gas S/O Valve 4/21/2023 SGSOV Approved AMY COLIN
Smoke Detectors 4/21/2023 Approved AMY COLIN
Final 5/8/2025 OK to Issue CofO LILIANA PORTILLO