6242 N CARPENTER AVE 91606
Certificate Information: 6242 N CARPENTER AVE 91606
- Application / Permit
- 21014-10000-03740
- Plan Check / Job No.
- B21LA13822
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- 855 SF ADDITION TO EXISTING DETACHED GARAGE AND CONVERT TO ACCESSORY DWELLING UNIT. PER LAMC 12.22 A.33(c) AND (d) "THE LID CLEARANCE HAS BEEN DEFERRED. APPROVAL FOR LID REQUIREMENTS SHALL BE OBTAINED FROM LASAN PRIOR TO THE ISSUANCE OF THE CERTIFICATE OF OCCUPANCY"
- Permit Issued
- Issued on 2/10/2022
- Issuing Office
- Current Status
- CofO Issued on 4/4/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/28/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 8/5/2021 | GEORGE ALVAREZ |
| Corrections Issued | 8/11/2021 | GEORGE ALVAREZ |
| Applicant returned to address corrections | 11/24/2021 | LUISANGEL VALENZUELA |
| Issued | 2/10/2022 | APPLICANT |
| Building Plans Picked Up | 2/17/2022 | APPLICANT |
| CofO in Progress | 4/3/2023 | JOHN HAYES |
| Permit Finaled | 4/4/2023 | RONALD MYRICK |
| CofO Issued | 4/4/2023 | RONALD MYRICK |
| Permit Finaled | 4/4/2023 | RONALD MYRICK |
Permit Application Clearance Information
| Address approval | Cleared | 10/13/2021 | CARLOS AGUILERA |
| Roof/Waste drainage to street | Cleared | 10/13/2021 | CARLOS AGUILERA |
| Eng Process Fee Ord 176,300 | Cleared | 11/18/2021 | CARLOS AGUILERA |
| Sewer availability | Cleared | 11/18/2021 | CARLOS AGUILERA |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Martirossyan,, Armen; Lic. No.: C64223 | 802 PORTOLA AVE GLENDALE, CA 91206 |
Inspector Information
| GAREN HAYRAPETYAN, (818) 374-1171 | Office Hours: 7:00-8:00 AM MON-FRI |
| ROBERTO PALACIOS-LOPEZ, (818) 374-1171 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 4/12/2022 | Partial Approval | MATT KELLERMAN |
| Deputy Drilled-In Anchors | 4/20/2022 | Conditional Approval | CALEB MEISTER |
| Excavation/Setback/Form/Re-Bar | 4/20/2022 | Approved | JACK KARGODORIAN |
| Footing/Foundation/Slab | 4/20/2022 | Approved | JACK KARGODORIAN |
| Floor/Roof Diaphrgm/Shear Wall | 6/14/2022 | Partial Approval | JOHN HAYES |
| BUILDING-Rough-Frame | 6/17/2022 | Not Ready for Inspection | JOHN HAYES |
| Rough-Elec/Plmb/HVAC | 6/17/2022 | Corrections Issued | JOHN HAYES |
| BUILDING-Rough-Frame | 6/29/2022 | Approved | JOHN HAYES |
| Green Building Rough | 6/29/2022 | Approved | JOHN HAYES |
| Rough-Elec/Plmb/HVAC | 6/29/2022 | Approved | JOHN HAYES |
| Sewer | 6/29/2022 | Approved | JOHN HAYES |
| Insulation | 7/13/2022 | Corrections Issued | MISAEL ESPARZA |
| Interior/Exterior Lathing | 7/13/2022 | Partial Approval | MISAEL ESPARZA |
| Wood Frame | 7/13/2022 | Approved | MISAEL ESPARZA |
| Insulation | 8/2/2022 | Approved | ALAN MORELOS |
| Interior/Exterior Lathing | 8/2/2022 | Approved | ALAN MORELOS |
| Shower Pan | 8/2/2022 | Approved | ALAN MORELOS |
| Drywall Nailing | 8/10/2022 | Approved | CALEB MEISTER |
| Final | 9/19/2022 | Not Ready for Inspection | JOHN HAYES |
| Gas Test | 9/19/2022 | Approved | JOHN HAYES |
| Green Building Final | 9/19/2022 | Not Ready for Inspection | JOHN HAYES |
| SGSOV-Seismic Gas S/O Valve | 9/19/2022 | SGSOV Not Ready | JOHN HAYES |
| Smoke Detectors | 9/19/2022 | Not Ready for Inspection | JOHN HAYES |
| Final | 10/6/2022 | Corrections Issued | JOHN HAYES |
| Green Building Final | 10/6/2022 | Not Ready for Inspection | JOHN HAYES |
| SGSOV-Seismic Gas S/O Valve | 10/6/2022 | SGSOV Not Ready | JOHN HAYES |
| Smoke Detectors | 10/6/2022 | Not Ready for Inspection | JOHN HAYES |
| Final | 2/8/2023 | Corrections Issued | JOHN HAYES |
| Green Building Final | 2/8/2023 | Not Ready for Inspection | JOHN HAYES |
| SGSOV-Seismic Gas S/O Valve | 2/8/2023 | SGSOV Not Ready | JOHN HAYES |
| Smoke Detectors | 2/8/2023 | Not Ready for Inspection | JOHN HAYES |
| Final | 2/27/2023 | Corrections Issued | JOHN HAYES |
| Green Building Final | 2/27/2023 | Approved | JOHN HAYES |
| SGSOV-Seismic Gas S/O Valve | 2/27/2023 | SGSOV Not Ready | JOHN HAYES |
| Smoke Detectors | 2/27/2023 | Approved | JOHN HAYES |
| Final | 3/15/2023 | Corrections Issued | JOHN HAYES |
| SGSOV-Seismic Gas S/O Valve | 3/15/2023 | SGSOV Not Ready | JOHN HAYES |
| Final | 3/22/2023 | Corrections Issued | THOMAS FINNILA |
| SGSOV-Seismic Gas S/O Valve | 3/22/2023 | SGSOV Approved | THOMAS FINNILA |
| Final | 4/3/2023 | OK to Issue CofO | JOHN HAYES |