2221 N HOLLY DR 90068

Certificate Information: 2221 N HOLLY DR 90068

Application / Permit
21014-10000-03729
Plan Check / Job No.
B21LA13791
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERTING THE EXISTING GARAGE AND ADDITION TO AN ADU (560 SQFT). [N] STORAGE (176 SQ.FT)
Permit Issued
Issued on 12/1/2021
Issuing Office
Current Status
Issued on 12/1/2021
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 7/23/2021 APPLICANT
Assigned to Plan Check Engineer 8/19/2021 JOE VO
Corrections Issued 8/21/2021 JOE VO
Quality Review Completed 8/31/2021 MICHAEL PEREZ
Applicant returned to address corrections 9/23/2021 JOE VO
Plan Check Approved 11/8/2021 JOE VO
Issued 12/1/2021 APPLICANT

Permit Application Clearance Information

Address approval Cleared 8/25/2021 WALLIE JONG
BHO/Hillside ordinance Cleared 8/25/2021 WALLIE JONG
BHO/Hillside ordinance Cleared 8/25/2021 WALLIE JONG
BHO/Hillside ordinance Cleared 8/25/2021 WALLIE JONG
BHO/Hillside ordinance Cleared 8/25/2021 WALLIE JONG
BHO/Hillside ordinance Cleared 8/25/2021 WALLIE JONG
Eng Process Fee Ord 176,300 Cleared 8/26/2021 WALLIE JONG
Sewer availability Cleared 8/26/2021 WALLIE JONG
Miscellaneous Cleared 9/20/2021 ALBERT TAM
Low Impact Development Cleared 10/22/2021 SUNG JOON WON
Roof/Waste drainage to street Cleared 10/25/2021 WALLIE JONG
Grading Pre-Inspection Cleared 11/8/2021 JOE VO

Contact Information

Contractor Owner-Builder       ,

Inspector Information

CRAIG VAUGHAN, (213) 202-3250 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 4/18/2024 Not Ready for Inspection ROY SPAULDING
Footing/Foundation/Slab 9/9/2024 Partial Inspection CRAIG VAUGHAN
Footing/Foundation/Slab 9/19/2024 Partial Approval CRAIG VAUGHAN
PLUMBING-Rough 9/19/2024 Partial Approval CRAIG VAUGHAN
Excavation/Setback/Form/Re-Bar 9/27/2024 Partial Approval CRAIG VAUGHAN
Footing/Foundation/Slab 10/15/2024 Approved CRAIG VAUGHAN
Floor/Roof Diaphrgm/Shear Wall 11/20/2024 Corrections Issued CRAIG VAUGHAN
Wood Frame 11/20/2024 Partial Approval CRAIG VAUGHAN
ELECTRICAL-Rough 12/13/2024 Approved NICHOLAS LOPEZ
HVAC-Rough 12/13/2024 Corrections Issued NICHOLAS LOPEZ
PLUMBING-Rough 12/13/2024 Approved NICHOLAS LOPEZ
HVAC-Rough 12/27/2024 Approved NICHOLAS LOPEZ
Interior/Exterior Lathing 12/27/2024 Partial Approval NICHOLAS LOPEZ
BUILDING-Rough-Frame 12/30/2024 Approved CRAIG VAUGHAN
Green Building Rough 12/30/2024 Approved CRAIG VAUGHAN
MERV13>=Rough 12/30/2024 Approved CRAIG VAUGHAN
Insulation 1/7/2025 Approved NICHOLAS LOPEZ
Shower Pan 1/7/2025 Approved NICHOLAS LOPEZ
Drywall Nailing 1/14/2025 Approved BRIAN SULLIVAN
Interior/Exterior Lathing 1/17/2025 Approved BRENDAN MORELLI
Rough-Elec/Plmb/HVAC 5/5/2025 Approved CRAIG VAUGHAN
Sewer 5/5/2025 Approved CRAIG VAUGHAN
Underground Mechanical 5/5/2025 Approved CRAIG VAUGHAN
ELECTRICAL-Final 6/4/2025 Corrections Issued CRAIG VAUGHAN
PLUMBING-Final 6/4/2025 Corrections Issued CRAIG VAUGHAN
ELECTRICAL-Final 6/11/2025 Approved CRAIG VAUGHAN
Gas Test 6/11/2025 Approved CRAIG VAUGHAN
PLUMBING-Final 6/11/2025 Approved CRAIG VAUGHAN
SGSOV-Seismic Gas S/O Valve 6/11/2025 SGSOV Approved CRAIG VAUGHAN
Smoke Detectors 6/11/2025 Approved CRAIG VAUGHAN