5517 N DENNY AVE 91601
Certificate Information: 5517 N DENNY AVE 91601
- Application / Permit
- 21014-10000-03726
- Plan Check / Job No.
- B21LA13790
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT AND ADD TO DETACHED GARAGE TO CREATE AN A.D.U. PER LAMC 12.22 A.33(c) AND (d)
- Permit Issued
- Issued on 1/17/2022
- Issuing Office
- Current Status
- Issued on 1/17/2022
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 7/22/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 7/28/2021 | LAWRENCE QUIRANTE |
| Corrections Issued | 7/29/2021 | LAWRENCE QUIRANTE |
| Plan Check Approved | 10/4/2021 | RICARDO RAMIREZ |
| Issued | 1/17/2022 | APPLICANT |
| Building Plans Picked Up | 3/22/2022 | APPLICANT |
Permit Application Clearance Information
| Address approval | Cleared | 9/9/2021 | DAGOVERTO GUERRERO |
| Roof/Waste drainage to street | Cleared | 9/9/2021 | DAGOVERTO GUERRERO |
| Eng Process Fee Ord 176,300 | Cleared | 9/20/2021 | DAGOVERTO GUERRERO |
| Sewer availability | Cleared | 9/20/2021 | DAGOVERTO GUERRERO |
Contact Information
| Contractor | Levet Inc; Lic. No.: 1027447-B | 3401 OCEAN VIEW BLVD GLENDALE, CA 91208 |
| Engineer | Khatchadourian,, Vicken; Lic. No.: S3141 | 1221 N CEDAR ST GLENDALE, CA 92107 |
Inspector Information
| GAREN HAYRAPETYAN, (818) 374-1171 | Office Hours: 7:00-8:00 AM MON-FRI |
| ROBERTO PALACIOS-LOPEZ, (818) 374-1171 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 3/22/2022 | Corrections Issued | ARAM AVEDISIAN |
| PLUMBING-Rough | 3/22/2022 | Partial Approval | ARAM AVEDISIAN |
| Sewer | 3/22/2022 | Approved | ARAM AVEDISIAN |
| Underground Mechanical | 3/22/2022 | Partial Approval | ARAM AVEDISIAN |
| Excavation/Setback/Form/Re-Bar | 4/5/2022 | Not Ready for Inspection | JACK KARGODORIAN |
| Excavation/Setback/Form/Re-Bar | 4/11/2022 | Corrections Issued | MISAEL ESPARZA |
| ELECTRICAL-Rough | 7/29/2022 | Corrections Issued | CALEB MEISTER |
| Floor/Roof Diaphrgm/Shear Wall | 7/29/2022 | Approved | CALEB MEISTER |
| HVAC-Rough | 7/29/2022 | Corrections Issued | CALEB MEISTER |
| PLUMBING-Rough | 7/29/2022 | Approved | CALEB MEISTER |
| ELECTRICAL-Rough | 8/10/2022 | Approved | JOHN HAYES |
| HVAC-Rough | 8/10/2022 | Approved | JOHN HAYES |
| Interior/Exterior Lathing | 8/10/2022 | Partial Approval | JOHN HAYES |
| Insulation | 8/24/2022 | Not Ready for Inspection | JOHN HAYES |
| Drywall Nailing | 9/1/2022 | Approved | ALAN MORELOS |
| BUILDING-Rough-Frame | 1/4/2023 | Not Ready for Inspection | JOHN HAYES |
| Final | 1/4/2023 | Corrections Issued | JOHN HAYES |
| Footing/Foundation/Slab | 1/4/2023 | Not Ready for Inspection | JOHN HAYES |
| Green Building Final | 1/4/2023 | Not Ready for Inspection | JOHN HAYES |
| Green Building Rough | 1/4/2023 | Not Ready for Inspection | JOHN HAYES |
| METHANE-Barrier | 1/4/2023 | Not Ready for Inspection | JOHN HAYES |
| METHANE-Final | 1/4/2023 | Not Ready for Inspection | JOHN HAYES |
| METHANE-Rough | 1/4/2023 | Not Ready for Inspection | JOHN HAYES |
| METHANE-Subgrade | 1/4/2023 | Not Ready for Inspection | JOHN HAYES |
| SGSOV-Seismic Gas S/O Valve | 1/4/2023 | SGSOV Not Ready | JOHN HAYES |
| Smoke Detectors | 1/4/2023 | Not Ready for Inspection | JOHN HAYES |
| BUILDING-Rough-Frame | 1/23/2023 | Not Ready for Inspection | JOHN HAYES |
| Final | 1/23/2023 | Corrections Issued | JOHN HAYES |
| Footing/Foundation/Slab | 1/23/2023 | Not Ready for Inspection | JOHN HAYES |
| Green Building Final | 1/23/2023 | Not Ready for Inspection | JOHN HAYES |
| Green Building Rough | 1/23/2023 | Not Ready for Inspection | JOHN HAYES |
| METHANE-Barrier | 1/23/2023 | Not Ready for Inspection | JOHN HAYES |
| METHANE-Final | 1/23/2023 | Not Ready for Inspection | JOHN HAYES |
| METHANE-Rough | 1/23/2023 | Not Ready for Inspection | JOHN HAYES |
| METHANE-Subgrade | 1/23/2023 | Not Ready for Inspection | JOHN HAYES |
| SGSOV-Seismic Gas S/O Valve | 1/23/2023 | SGSOV Not Ready | JOHN HAYES |
| Smoke Detectors | 1/23/2023 | Not Ready for Inspection | JOHN HAYES |
| BUILDING-Rough-Frame | 2/9/2023 | Approved | JOHN HAYES |
| Final | 2/9/2023 | Not Ready for Inspection | JOHN HAYES |
| Footing/Foundation/Slab | 2/9/2023 | Approved | JOHN HAYES |
| Green Building Final | 2/9/2023 | Approved | JOHN HAYES |
| Green Building Rough | 2/9/2023 | Approved | JOHN HAYES |
| METHANE-Barrier | 2/9/2023 | Approved | JOHN HAYES |
| METHANE-Final | 2/9/2023 | Approved | JOHN HAYES |
| METHANE-Rough | 2/9/2023 | Approved | JOHN HAYES |
| METHANE-Subgrade | 2/9/2023 | Approved | JOHN HAYES |
| SGSOV-Seismic Gas S/O Valve | 2/9/2023 | SGSOV Approved | JOHN HAYES |
| Service/Power Release | 2/9/2023 | Approved | JOHN HAYES |
| Smoke Detectors | 2/9/2023 | Approved | JOHN HAYES |