8312 N OAKDALE AVE 91306
Certificate Information: 8312 N OAKDALE AVE 91306
- Application / Permit
- 21014-10000-03718
- Plan Check / Job No.
- B21LA13768
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT DETACHED GARAGE TO ADU AND ADDITION PER WFPP
- Permit Issued
- Issued on 2/28/2022
- Issuing Office
- Current Status
- CofO Issued on 7/14/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/24/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 8/2/2021 | JESSE JIMENEZ |
| Corrections Issued | 8/3/2021 | JESSE JIMENEZ |
| Plan Check Approved | 11/24/2021 | SINA KHOSRAVI |
| Building Plans Picked Up | 2/1/2022 | APPLICANT |
| Issued | 2/28/2022 | APPLICANT |
| CofO in Progress | 7/11/2023 | JOHN KIDWELL |
| CofO Issued | 7/14/2023 | JOHN JANSON |
| Permit Finaled | 7/14/2023 | JOHN JANSON |
Permit Application Clearance Information
| Address approval | Cleared | 8/10/2021 | DAGOVERTO GUERRERO |
| Roof/Waste drainage to street | Cleared | 8/10/2021 | DAGOVERTO GUERRERO |
| Eng Process Fee Ord 176,300 | Cleared | 8/13/2021 | DAGOVERTO GUERRERO |
| Sewer availability | Cleared | 8/13/2021 | DAGOVERTO GUERRERO |
| Hydrant and Access approval | Cleared | 11/15/2021 | KURT CORRAL |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| JACK KARGODORIAN, (818) 774-4319 | Office Hours: 7:00-8:00 AM MON-FRI |
| KRISTEN CAUSEY, (818) 774-4319 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 3/29/2022 | Approved | TROY SANDERS |
| Footing/Foundation/Slab | 3/29/2022 | Approved | TROY SANDERS |
| PLUMBING-Rough | 3/29/2022 | Partial Approval | TROY SANDERS |
| BUILDING-Rough-Frame | 5/18/2022 | Approved | JEFFREY PARD |
| ELECTRICAL-Rough | 5/18/2022 | Approved | JEFFREY PARD |
| Green Building Rough | 5/18/2022 | Not Ready for Inspection | JEFFREY PARD |
| PLUMBING-Rough | 5/18/2022 | Approved | JEFFREY PARD |
| Sewer | 5/18/2022 | Approved | JEFFREY PARD |
| Insulation | 6/1/2022 | Approved | JEFFREY PARD |
| Interior/Exterior Lathing | 6/1/2022 | Approved | JEFFREY PARD |
| Drywall Nailing | 6/16/2022 | Approved | KRISTEN CAUSEY |
| Gas Test | 6/16/2022 | Approved | KRISTEN CAUSEY |
| ELECTRICAL-Final | 8/26/2022 | Not Ready for Inspection | JEFFREY PARD |
| Service/Power Release | 8/26/2022 | Not Ready for Inspection | JEFFREY PARD |
| BUILDING-Rough-Frame | 5/16/2023 | Approved | JOHN KIDWELL |
| Final | 5/16/2023 | Corrections Issued | JOHN KIDWELL |
| Green Building Final | 5/16/2023 | Approved | JOHN KIDWELL |
| Green Building Rough | 5/16/2023 | Approved | JOHN KIDWELL |
| SGSOV-Seismic Gas S/O Valve | 5/16/2023 | SGSOV Not Ready | JOHN KIDWELL |
| Smoke Detectors | 5/16/2023 | Approved | JOHN KIDWELL |
| SGSOV-Seismic Gas S/O Valve | 5/25/2023 | SGSOV Not Ready | JOHN KIDWELL |
| ELECTRICAL-Final | 5/30/2023 | No Access for Inspection | JOHN KIDWELL |
| SGSOV-Seismic Gas S/O Valve | 6/2/2023 | SGSOV Not Ready | JOHN KIDWELL |
| ELECTRICAL-Rough | 6/7/2023 | Partial Inspection | JOHN KIDWELL |
| Final | 7/5/2023 | Corrections Issued | HORACE FULTZ |
| SGSOV-Seismic Gas S/O Valve | 7/5/2023 | SGSOV Approved | HORACE FULTZ |
| Pre-Inspection | 7/7/2023 | Approved | JOHN KIDWELL |
| Final | 7/11/2023 | OK to Issue CofO | JOHN KIDWELL |