8312 N OAKDALE AVE 91306

Certificate Information: 8312 N OAKDALE AVE 91306

Application / Permit
21014-10000-03718
Plan Check / Job No.
B21LA13768
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT DETACHED GARAGE TO ADU AND ADDITION PER WFPP
Permit Issued
Issued on 2/28/2022
Issuing Office
Current Status
CofO Issued on 7/14/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 7/24/2021 APPLICANT
Assigned to Plan Check Engineer 8/2/2021 JESSE JIMENEZ
Corrections Issued 8/3/2021 JESSE JIMENEZ
Plan Check Approved 11/24/2021 SINA KHOSRAVI
Building Plans Picked Up 2/1/2022 APPLICANT
Issued 2/28/2022 APPLICANT
CofO in Progress 7/11/2023 JOHN KIDWELL
CofO Issued 7/14/2023 JOHN JANSON
Permit Finaled 7/14/2023 JOHN JANSON

Permit Application Clearance Information

Address approval Cleared 8/10/2021 DAGOVERTO GUERRERO
Roof/Waste drainage to street Cleared 8/10/2021 DAGOVERTO GUERRERO
Eng Process Fee Ord 176,300 Cleared 8/13/2021 DAGOVERTO GUERRERO
Sewer availability Cleared 8/13/2021 DAGOVERTO GUERRERO
Hydrant and Access approval Cleared 11/15/2021 KURT CORRAL

Contact Information

Contractor Owner-Builder       ,

Inspector Information

JACK KARGODORIAN, (818) 774-4319 Office Hours: 7:00-8:00 AM MON-FRI
KRISTEN CAUSEY, (818) 774-4319 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 3/29/2022 Approved TROY SANDERS
Footing/Foundation/Slab 3/29/2022 Approved TROY SANDERS
PLUMBING-Rough 3/29/2022 Partial Approval TROY SANDERS
BUILDING-Rough-Frame 5/18/2022 Approved JEFFREY PARD
ELECTRICAL-Rough 5/18/2022 Approved JEFFREY PARD
Green Building Rough 5/18/2022 Not Ready for Inspection JEFFREY PARD
PLUMBING-Rough 5/18/2022 Approved JEFFREY PARD
Sewer 5/18/2022 Approved JEFFREY PARD
Insulation 6/1/2022 Approved JEFFREY PARD
Interior/Exterior Lathing 6/1/2022 Approved JEFFREY PARD
Drywall Nailing 6/16/2022 Approved KRISTEN CAUSEY
Gas Test 6/16/2022 Approved KRISTEN CAUSEY
ELECTRICAL-Final 8/26/2022 Not Ready for Inspection JEFFREY PARD
Service/Power Release 8/26/2022 Not Ready for Inspection JEFFREY PARD
BUILDING-Rough-Frame 5/16/2023 Approved JOHN KIDWELL
Final 5/16/2023 Corrections Issued JOHN KIDWELL
Green Building Final 5/16/2023 Approved JOHN KIDWELL
Green Building Rough 5/16/2023 Approved JOHN KIDWELL
SGSOV-Seismic Gas S/O Valve 5/16/2023 SGSOV Not Ready JOHN KIDWELL
Smoke Detectors 5/16/2023 Approved JOHN KIDWELL
SGSOV-Seismic Gas S/O Valve 5/25/2023 SGSOV Not Ready JOHN KIDWELL
ELECTRICAL-Final 5/30/2023 No Access for Inspection JOHN KIDWELL
SGSOV-Seismic Gas S/O Valve 6/2/2023 SGSOV Not Ready JOHN KIDWELL
ELECTRICAL-Rough 6/7/2023 Partial Inspection JOHN KIDWELL
Final 7/5/2023 Corrections Issued HORACE FULTZ
SGSOV-Seismic Gas S/O Valve 7/5/2023 SGSOV Approved HORACE FULTZ
Pre-Inspection 7/7/2023 Approved JOHN KIDWELL
Final 7/11/2023 OK to Issue CofO JOHN KIDWELL