5941 N ETIWANDA AVE 91356
Certificate Information: 5941 N ETIWANDA AVE 91356
- Application / Permit
- 21014-10000-03715
- Plan Check / Job No.
- B21LA13762
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- ADDITION TO EXISTING ONE STORY SINGLE FAMIL DWELLING WITH ATTACHED GARAGE AT THE RARE OF THE BUILDING. NFPA-13D THRU OUT
- Permit Issued
- Issued on 12/29/2021
- Issuing Office
- Current Status
- CofO Issued on 4/18/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/22/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 7/28/2021 | RICARDO RAMIREZ |
| Corrections Issued | 7/29/2021 | RICARDO RAMIREZ |
| Applicant returned to address corrections | 11/26/2021 | ZAW HAN |
| Plan Check Approved | 11/29/2021 | ZAW HAN |
| Building Plans Picked Up | 12/1/2021 | APPLICANT |
| Issued | 12/29/2021 | APPLICANT |
| CofO in Progress | 6/8/2023 | JON MCHUGH |
| No Progress | 6/14/2023 | SEAN WIRCH |
| CofO in Progress | 11/1/2023 | JON MCHUGH |
| Permit Finaled | 4/18/2024 | DANIEL ORRANTE |
| CofO Issued | 4/18/2024 | DANIEL ORRANTE |
| Permit Finaled | 4/18/2024 | DANIEL ORRANTE |
Permit Application Clearance Information
| Miscellaneous | Cleared | 8/12/2021 | DAGOVERTO GUERRERO |
| Miscellaneous | Cleared | 8/12/2021 | DAGOVERTO GUERRERO |
| Sewer availability | Cleared | 8/12/2021 | DAGOVERTO GUERRERO |
| Eng Process Fee Ord 176,300 | Cleared | 9/8/2021 | DAGOVERTO GUERRERO |
| Low Impact Development | Cleared | 11/17/2021 | SAHIL SHARMA |
| Roof/Waste drainage to street | Cleared | 11/19/2021 | DAGOVERTO GUERRERO |
Contact Information
| Contractor | Master Co; Lic. No.: 577769-B | 2426 WEST 8TH STREET #222 LOS ANGELES, CA 90057 |
| Engineer | Park,, Juntae; Lic. No.: C65104 | 3055 WILSHIRE BLVD 880 LOS ANGELES, CA 90010 |
Inspector Information
| JON MCHUGH, (818) 774-4348 | Office Hours: 7:00-8:00 AM MON-FRI |
| IVAN SARABIA, (818) 774-4348 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 4/19/2022 | Not Ready for Inspection | SEAN HAUPT |
| PLUMBING-Rough | 4/19/2022 | Not Ready for Inspection | SEAN HAUPT |
| Deputy Drilled-In Anchors | 4/20/2022 | Approved | SEAN HAUPT |
| Excavation/Setback/Form/Re-Bar | 4/20/2022 | Approved | SEAN HAUPT |
| Footing/Foundation/Slab | 4/20/2022 | Approved | SEAN HAUPT |
| Underground Mechanical | 4/20/2022 | Not Ready for Inspection | SEAN HAUPT |
| PLUMBING-Rough | 5/31/2022 | Not Ready for Inspection | SEAN HAUPT |
| Wood Frame | 5/31/2022 | Partial Approval | SEAN HAUPT |
| Insulation | 6/16/2022 | Approved | SEAN HAUPT |
| PLUMBING-Rough | 6/16/2022 | Approved | SEAN HAUPT |
| Floor/Roof Diaphrgm/Shear Wall | 6/28/2022 | Approved | SEAN HAUPT |
| Deputy Drilled-In Anchors | 8/11/2022 | Partial Approval | SEAN HAUPT |
| Floor/Roof Diaphrgm/Shear Wall | 8/16/2022 | Approved | SEAN HAUPT |
| BUILDING-Rough-Frame | 9/12/2022 | Approved | SEAN HAUPT |
| ELECTRICAL-Rough | 9/12/2022 | Approved | SEAN HAUPT |
| Green Building Rough | 9/12/2022 | Approved | SEAN HAUPT |
| HVAC-Rough | 9/12/2022 | Approved | SEAN HAUPT |
| PLUMBING-Rough | 9/12/2022 | Approved | SEAN HAUPT |
| Insulation | 10/4/2022 | Corrections Issued | MORRIS JACKSON |
| Shower Pan | 10/4/2022 | Approved | MORRIS JACKSON |
| Insulation | 10/18/2022 | Approved | MORRIS JACKSON |
| Interior/Exterior Lathing | 10/18/2022 | Partial Approval | MORRIS JACKSON |
| Drywall Nailing | 11/4/2022 | Approved | SEAN HAUPT |
| Interior/Exterior Lathing | 11/4/2022 | Approved | SEAN HAUPT |
| Final | 3/14/2023 | Corrections Issued | JON MCHUGH |
| Green Building Final | 3/14/2023 | Corrections Issued | JON MCHUGH |
| SGSOV-Seismic Gas S/O Valve | 3/14/2023 | SGSOV Not Ready | JON MCHUGH |
| Smoke Detectors | 3/14/2023 | Approved | JON MCHUGH |
| Final | 5/25/2023 | Corrections Issued | JON MCHUGH |
| Green Building Final | 5/25/2023 | Not Ready for Inspection | JON MCHUGH |
| SGSOV-Seismic Gas S/O Valve | 5/25/2023 | SGSOV Approved | JON MCHUGH |
| Final | 6/7/2023 | OK to Issue CofO | JON MCHUGH |
| Green Building Final | 6/7/2023 | Approved | JON MCHUGH |
| Service/Power Release | 6/13/2023 | Approved | JON MCHUGH |