421 E 92ND ST 90003

Certificate Information: 421 E 92ND ST 90003

Application / Permit
21014-10000-03662
Plan Check / Job No.
B21LA13605
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
CONVERT COVERED SERVICE PORCH TO LAUNDRY/PANTRY 99 S.F., ADD MASTER BED AND BATH WITH WALK IN CLOSET. 377 S.F.
Permit Issued
Issued on 8/31/2021
Issuing Office
Current Status
Issued on 8/31/2021
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 7/20/2021 APPLICANT
Assigned to Plan Check Engineer 7/26/2021 RICARDO RAMIREZ
Corrections Issued 7/27/2021 RICARDO RAMIREZ
Building Plans Picked Up 7/28/2021 APPLICANT
Plan Check Approved 8/11/2021 JOSEPH RAFOLS
Issued 8/31/2021 APPLICANT

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 8/4/2021 JEANIE LAM
Roof/Waste drainage to street Cleared 8/4/2021 JEANIE LAM
Sewer availability Cleared 8/4/2021 JEANIE LAM

Contact Information

Contractor Crockett Construction Services; Lic. No.: 898696-B P O BOX 2041      INGLEWOOD, CA 90305

Inspector Information

JOHN QUINTANILLA, (213) 792-6055 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 9/8/2021 Not Ready for Inspection JOHN KLARIN
Excavation/Setback/Form/Re-Bar 9/10/2021 Corrections Issued EUGENE CASSIDY
Footing/Foundation/Slab 9/14/2021 Corrections Issued CRAIG DAVIS
Excavation/Setback/Form/Re-Bar 9/15/2021 Approved CRAIG DAVIS
Grounding or Bonding 9/15/2021 Approved CRAIG DAVIS
Footing/Foundation/Slab 9/29/2021 Not Ready for Inspection FREDDIE RIVERA
Insulation 9/29/2021 Partial Approval FREDDIE RIVERA
PLUMBING-Rough 9/29/2021 Partial Approval FREDDIE RIVERA
Floor/Roof Diaphrgm/Shear Wall 10/13/2021 Partial Approval ALEJANDRO DE ARTOLA
ELECTRICAL-Rough 10/18/2021 Corrections Issued ALEJANDRO DE ARTOLA
Interior/Exterior Lathing 10/18/2021 Corrections Issued ALEJANDRO DE ARTOLA
PLUMBING-Rough 10/18/2021 Corrections Issued ALEJANDRO DE ARTOLA
ELECTRICAL-Rough 11/8/2021 Approved SABAS ALONSO
Insulation 11/8/2021 Not Ready for Inspection SABAS ALONSO
Interior/Exterior Lathing 11/8/2021 Not Ready for Inspection SABAS ALONSO
PLUMBING-Rough 11/8/2021 Approved SABAS ALONSO
Insulation 11/15/2021 Corrections Issued ALEJANDRO DE ARTOLA
Interior/Exterior Lathing 11/15/2021 Corrections Issued ALEJANDRO DE ARTOLA
Insulation 11/18/2021 Not Ready for Inspection JOAQUIN GREENOUGH
Interior/Exterior Lathing 11/18/2021 Corrections Issued JOAQUIN GREENOUGH
BUILDING-Rough-Frame 11/23/2021 Approved STUART CHAPMAN
Green Building Rough 11/23/2021 Approved STUART CHAPMAN
Insulation 11/23/2021 Corrections Issued STUART CHAPMAN
Interior/Exterior Lathing 11/23/2021 Partial Approval STUART CHAPMAN
Drywall Nailing 12/6/2021 Conditional Approval SABAS ALONSO
Final 12/6/2021 Not Ready for Inspection SABAS ALONSO
Footing/Foundation/Slab 12/6/2021 Not Ready for Inspection SABAS ALONSO
Green Building Final 12/6/2021 Not Ready for Inspection SABAS ALONSO
Insulation 12/6/2021 Not Ready for Inspection SABAS ALONSO
SGSOV-Seismic Gas S/O Valve 12/6/2021 SGSOV Not Ready SABAS ALONSO
Smoke Detectors 12/6/2021 Not Ready for Inspection SABAS ALONSO
SGSOV-Seismic Gas S/O Valve 6/13/2022 SGSOV Not Ready HORACE FULTZ
Final 12/12/2022 Corrections Issued MICHAEL LEWIS
Footing/Foundation/Slab 12/12/2022 Approved MICHAEL LEWIS
Green Building Final 12/12/2022 Approved MICHAEL LEWIS
SGSOV-Seismic Gas S/O Valve 12/12/2022 SGSOV Not Ready MICHAEL LEWIS
Smoke Detectors 12/12/2022 Approved MICHAEL LEWIS