519 N NEVA PL 90042

Certificate Information: 519 N NEVA PL 90042

Application / Permit
21014-10000-03632
Plan Check / Job No.
B21LA13476
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
ONE-STORY ADDITION (31'-10" X 24'-2"): ADD BEDROOM/BATH/CLOSET, 2 BEDROOMS AND REMODELING (E) BATHROOM/KITCHEN/LIVING ROOM. NEW ELECTRICAL PANEL, NEW TANKLESS WATER HEATER AND HVAC.
Permit Issued
Issued on 6/21/2022
Issuing Office
Metro
Current Status
CofO Issued on 8/7/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 7/20/2021 APPLICANT
Assigned to Plan Check Engineer 7/26/2021 JESSE JIMENEZ
Corrections Issued 7/28/2021 JESSE JIMENEZ
Applicant returned to address corrections 10/13/2021 RAHEL BEYENE
Building Plans Picked Up 10/19/2021 APPLICANT
Plan Check Approved 6/21/2022 KHUONG TRUONG
Issued 6/21/2022 APPLICANT
CofO in Progress 8/7/2023 CRAIG VAUGHAN
CofO Issued 8/7/2023 RONALD MYRICK
Permit Finaled 8/7/2023 RONALD MYRICK

Permit Application Clearance Information

Sewer availability Cleared 8/16/2021 RENZ SORIANO
Grading Pre-Inspection Cleared 8/19/2021 PATRICK MISCHLICH
Eng Process Fee Ord 176,300 Cleared 8/20/2021 RENZ SORIANO
GPI Written Notices Cleared 10/15/2021 JESSE JIMENEZ
Low Impact Development Cleared 5/2/2022 ORVAL HERNANDEZ-MARCI
Roof/Waste drainage to street Cleared 5/6/2022 CHRISTOPHER ROCHA

Contact Information

Contractor G A Design Build; Lic. No.: 941130-B 8449 EVEREST ST      DOWNEY, CA 90242
Engineer Carrillo,, Jesus Eduardo; Lic. No.: C77737 8207 BROOKGREEN RD      DOWNEY, CA 90240

Inspector Information

No Data Available.

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 7/6/2022 Approved RUBEN SALAS
BUILDING-Rough-Frame 7/27/2022 Partial Approval CRAIG VAUGHAN
PLUMBING-Rough 7/27/2022 Partial Approval CRAIG VAUGHAN
ELECTRICAL-Rough 9/27/2022 Approved CRAIG VAUGHAN
Floor/Roof Diaphrgm/Shear Wall 9/27/2022 Not Ready for Inspection CRAIG VAUGHAN
HVAC-Rough 9/27/2022 Partial Approval CRAIG VAUGHAN
PLUMBING-Rough 9/27/2022 Approved CRAIG VAUGHAN
BUILDING-Rough-Frame 10/13/2022 Corrections Issued CRAIG VAUGHAN
Floor/Roof Diaphrgm/Shear Wall 10/13/2022 Approved CRAIG VAUGHAN
Green Building Rough 10/13/2022 Approved CRAIG VAUGHAN
HVAC-Rough 10/13/2022 Approved CRAIG VAUGHAN
Shower Pan 10/13/2022 Approved CRAIG VAUGHAN
Verify Sprinkler Sign Off 10/13/2022 Not Ready for Inspection CRAIG VAUGHAN
Interior/Exterior Lathing 11/17/2022 Partial Approval SCOTT FINNILA
BUILDING-Rough-Frame 1/3/2023 Approved CRAIG VAUGHAN
Verify Sprinkler Sign Off 1/3/2023 Approved CRAIG VAUGHAN
Insulation 1/6/2023 Approved CRAIG VAUGHAN
Interior/Exterior Lathing 1/6/2023 Approved CRAIG VAUGHAN
Drywall Nailing 1/12/2023 Approved OSVALDO PARAMO
ELECTRICAL-Final 3/21/2023 Corrections Issued CRAIG VAUGHAN
Final 3/21/2023 Corrections Issued CRAIG VAUGHAN
Gas Test 3/21/2023 Approved CRAIG VAUGHAN
Green Building Final 3/21/2023 Approved CRAIG VAUGHAN
HVAC-Final 3/21/2023 Corrections Issued CRAIG VAUGHAN
PLUMBING-Final 3/21/2023 Approved CRAIG VAUGHAN
SGSOV-Seismic Gas S/O Valve 3/21/2023 SGSOV Not Ready CRAIG VAUGHAN
Smoke Detectors 3/21/2023 Approved CRAIG VAUGHAN
ELECTRICAL-Final 7/24/2023 Approved CRAIG VAUGHAN
Final 7/24/2023 Not Ready for Inspection CRAIG VAUGHAN
HVAC-Final 7/24/2023 Corrections Issued CRAIG VAUGHAN
PLUMBING-Final 7/24/2023 Approved CRAIG VAUGHAN
SGSOV-Seismic Gas S/O Valve 7/24/2023 SGSOV Approved CRAIG VAUGHAN
Service/Power Release 7/24/2023 Approved CRAIG VAUGHAN
ELECTRICAL-Final 7/27/2023 Approved CRAIG VAUGHAN
HVAC-Final 7/27/2023 Not Ready for Inspection CRAIG VAUGHAN
PLUMBING-Final 7/27/2023 Approved CRAIG VAUGHAN
Final 8/4/2023 OK to Issue CofO CRAIG VAUGHAN
HVAC-Final 8/4/2023 Approved CRAIG VAUGHAN
HVAC-Rough 8/4/2023 Approved CRAIG VAUGHAN