2104 W 79TH ST 90047

Certificate Information: 2104 W 79TH ST 90047

Application / Permit
21014-10000-03629
Plan Check / Job No.
B21LA13465
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
Eplan. Convert detached existing two car garage to Accessory dwelling unit with small addition per GCS 65852.2(e)(1)(A)
Permit Issued
Issued on 7/21/2022
Issuing Office
Current Status
CofO Issued on 8/13/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 8/3/2021 APPLICANT
Assigned to Plan Check Engineer 8/5/2021 MONICA RAMIREZ
Corrections Issued 8/6/2021 MONICA RAMIREZ
Applicant returned to address corrections 5/21/2022 DANIEL SANJUAN
Applicant returned to address corrections 6/4/2022 DANIEL SANJUAN
Plan Check Approved 6/7/2022 DANIEL SANJUAN
Issued 7/21/2022 APPLICANT
CofO in Progress 8/10/2023 ENRIQUE MIRELES
CofO in Progress 8/10/2023 ENRIQUE MIRELES
Permit Finaled 8/13/2023 DEROLD HAUFF
CofO Issued 8/13/2023 DEROLD HAUFF
Permit Finaled 8/13/2023 DEROLD HAUFF

Permit Application Clearance Information

Construction near power lines Cleared 11/2/2021 RIDWAN HARDY
Address approval Cleared 1/4/2022 AMAAN MALIK
Roof/Waste drainage to street Cleared 1/4/2022 AMAAN MALIK
Eng Process Fee Ord 176,300 Cleared 1/6/2022 AMAAN MALIK
Sewer availability Cleared 1/6/2022 AMAAN MALIK

Contact Information

Contractor Lone Star Renovation & Construction Inc; Lic. No.: 350486-B       ,
Contractor Lone Star; Lic. No.: 350486-B       ,
Engineer Adzhemyan,, Arsen; Lic. No.: C89103 1010 RALEIGH ST APT 107      GLENDALE, CA 91205

Inspector Information

SALVADOR MARTINEZ, (213) 202-3479 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 9/8/2022 Approved ENRIQUE MIRELES
Underground Mechanical 10/13/2022 Approved ENRIQUE MIRELES
Deputy Drilled-In Anchors 10/24/2022 Conditional Approval FREDDIE RIVERA
Excavation/Setback/Form/Re-Bar 10/24/2022 Approved ANTHONY EGSON
Footing/Foundation/Slab 10/24/2022 Corrections Issued ANTHONY EGSON
Excavation/Setback/Form/Re-Bar 11/2/2022 Approved ENRIQUE MIRELES
Footing/Foundation/Slab 11/2/2022 Approved ENRIQUE MIRELES
BUILDING-Rough-Frame 1/31/2023 Corrections Issued ENRIQUE MIRELES
ELECTRICAL-Rough 1/31/2023 Approved ENRIQUE MIRELES
Floor/Roof Diaphrgm/Shear Wall 1/31/2023 Approved ENRIQUE MIRELES
Green Building Rough 1/31/2023 Approved ENRIQUE MIRELES
HVAC-Rough 1/31/2023 Approved ENRIQUE MIRELES
PLUMBING-Rough 1/31/2023 Approved ENRIQUE MIRELES
BUILDING-Rough-Frame 2/7/2023 Approved ENRIQUE MIRELES
ELECTRICAL-Rough 2/7/2023 Approved ENRIQUE MIRELES
Floor/Roof Diaphrgm/Shear Wall 2/7/2023 Approved ENRIQUE MIRELES
HVAC-Rough 2/7/2023 Approved ENRIQUE MIRELES
PLUMBING-Rough 2/7/2023 Approved ENRIQUE MIRELES
Insulation 2/17/2023 Approved ENRIQUE MIRELES
Interior/Exterior Lathing 2/17/2023 Approved ENRIQUE MIRELES
Drywall Nailing 3/2/2023 Approved ANTHONY EGSON
Interior/Exterior Lathing 3/2/2023 Approved ANTHONY EGSON
Shower Pan 3/2/2023 Approved ANTHONY EGSON
Final 7/27/2023 Corrections Issued ENRIQUE MIRELES
Green Building Final 7/27/2023 Approved ENRIQUE MIRELES
SGSOV-Seismic Gas S/O Valve 7/27/2023 SGSOV Approved ENRIQUE MIRELES
Smoke Detectors 7/27/2023 Approved ENRIQUE MIRELES
Final 8/8/2023 OK to Issue CofO ENRIQUE MIRELES
HVAC-Final 8/8/2023 Approved ENRIQUE MIRELES
PLUMBING-Final 8/8/2023 Approved ENRIQUE MIRELES
Service/Power Release 8/8/2023 Approved ENRIQUE MIRELES