1209 W 21ST ST 90731
Certificate Information: 1209 W 21ST ST 90731
- Application / Permit
- 21014-10000-03615
- Plan Check / Job No.
- B21LA13403
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- 1-STORY ADDITION TO (E) 1-STORY DWELLING
- Permit Issued
- Issued on 11/2/2021
- Issuing Office
- Current Status
- CofO Issued on 11/12/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/16/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 7/23/2021 | FERNANDO FLORES |
| Corrections Issued | 7/24/2021 | FERNANDO FLORES |
| Building Plans Picked Up | 8/3/2021 | APPLICANT |
| Plan Check Approved | 11/2/2021 | JOSEPH RAFOLS |
| Issued | 11/2/2021 | APPLICANT |
| CofO in Progress | 11/7/2024 | JOSEPH MCGARRY |
| Permit Finaled | 11/12/2024 | ANSON MAGLASANG |
| CofO Issued | 11/12/2024 | ANSON MAGLASANG |
| Permit Finaled | 11/12/2024 | ANSON MAGLASANG |
Permit Application Clearance Information
| Roof/Waste drainage to street | Cleared | 8/27/2021 | JOSE HERNANDEZ |
| Eng Process Fee Ord 176,300 | Cleared | 8/30/2021 | JOSE HERNANDEZ |
| Grading Pre-Inspection | Cleared | 10/26/2021 | FERNANDO FLORES |
Contact Information
| Architect | Browning,, Jeffrey Carleton; Lic. No.: C34782 | 1570 WEST 9TH STREET SAN PEDRO, CA 90732 |
| Contractor | B C Construction; Lic. No.: 676747-B | 1137 EAST 46TH STREET LONG BEACH, CA 90807 |
Inspector Information
| JOSEPH MCGARRY, (310) 732-4559 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 12/2/2021 | Corrections Issued | ANSON MAGLASANG |
| Footing/Foundation/Slab | 12/9/2021 | Approved | ANSON MAGLASANG |
| BUILDING-Rough-Frame | 12/27/2021 | Partial Approval | ANSON MAGLASANG |
| PLUMBING-Rough | 12/27/2021 | Partial Approval | ANSON MAGLASANG |
| Floor/Roof Diaphrgm/Shear Wall | 1/24/2022 | Partial Approval | ANSON MAGLASANG |
| Green Building Rough | 1/24/2022 | Not Ready for Inspection | ANSON MAGLASANG |
| BUILDING-Rough-Frame | 3/15/2022 | Conditional Approval | ANSON MAGLASANG |
| Green Building Rough | 3/15/2022 | Not Ready for Inspection | ANSON MAGLASANG |
| Insulation | 3/23/2022 | Approved | ANSON MAGLASANG |
| Interior/Exterior Lathing | 3/23/2022 | Not Ready for Inspection | ANSON MAGLASANG |
| Drywall Nailing | 3/30/2022 | Approved | ANSON MAGLASANG |
| Interior/Exterior Lathing | 3/30/2022 | Partial Approval | ANSON MAGLASANG |
| Shower Pan | 4/15/2022 | Not Ready for Inspection | EUGENE CASSIDY |
| Shower Pan | 4/20/2022 | Approved | ANSON MAGLASANG |
| Interior/Exterior Lathing | 6/27/2022 | Partial Approval | EUGENE CASSIDY |
| BUILDING-Rough-Frame | 11/15/2022 | Approved | ANSON MAGLASANG |
| Final | 11/15/2022 | Conditional Approval | ANSON MAGLASANG |
| Green Building Final | 11/15/2022 | Approved | ANSON MAGLASANG |
| Green Building Rough | 11/15/2022 | Approved | ANSON MAGLASANG |
| SGSOV-Seismic Gas S/O Valve | 11/15/2022 | SGSOV Gas Company | ANSON MAGLASANG |
| Smoke Detectors | 11/15/2022 | Approved | ANSON MAGLASANG |
| Final | 11/7/2024 | OK to Issue CofO | JOSEPH MCGARRY |