3000 S SYCAMORE AVE 90016
Certificate Information: 3000 S SYCAMORE AVE 90016
- Application / Permit
- 21014-10000-03586
- Plan Check / Job No.
- B21LA13291
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- ePlan Addition create Study room within (E) Dwelling
- Permit Issued
- Issued on 10/6/2021
- Issuing Office
- Current Status
- CofO Issued on 2/26/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/15/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 7/19/2021 | HERNAN ARREOLA |
| Corrections Issued | 7/19/2021 | HERNAN ARREOLA |
| Applicant returned to address corrections | 8/11/2021 | HERNAN ARREOLA |
| Building Plans Picked Up | 8/11/2021 | APPLICANT |
| Plan Check Approved | 8/30/2021 | HERNAN ARREOLA |
| Issued | 10/6/2021 | APPLICANT |
| CofO in Progress | 2/18/2022 | JOSE AVILA |
| Permit Finaled | 2/26/2022 | DEROLD HAUFF |
| CofO Issued | 2/26/2022 | DEROLD HAUFF |
| Permit Finaled | 2/26/2022 | DEROLD HAUFF |
Permit Application Clearance Information
| Tenant Habitability Plan | Cleared | 8/12/2021 | JEFFREY BULL |
| Roof/Waste drainage to street | Cleared | 8/18/2021 | CELINA MORENO |
| Sewer availability | Cleared | 8/18/2021 | CELINA MORENO |
| Eng Process Fee Ord 176,300 | Cleared | 8/23/2021 | CELINA MORENO |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Melchor,, Oscar Elias; Lic. No.: C76828 | 21243 VENTURA BLVD SUITE 119 WOODLAND HILLS, CA 91364 |
Inspector Information
| DAVID WILLIAMS, (213) 202-3126 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 10/14/2021 | Approved | LILIANA PORTILLO |
| Special/Order Compliance | 10/14/2021 | Approved | RUBEN SALAS |
| Special/Order Compliance | 10/14/2021 | Partial Inspection | JUSTIN HAWLEY |
| BUILDING-Rough-Frame | 10/20/2021 | Partial Approval | JOSE AVILA |
| BUILDING-Rough-Frame | 10/28/2021 | Approved | JOSE AVILA |
| ELECTRICAL-Rough | 10/28/2021 | Approved | JOSE AVILA |
| Insulation | 11/2/2021 | Approved | JOSE AVILA |
| Interior/Exterior Lathing | 11/2/2021 | Approved | JOSE AVILA |
| Drywall Nailing | 11/4/2021 | Approved | LILIANA PORTILLO |
| HVAC-Rough | 11/4/2021 | Approved | LILIANA PORTILLO |
| Final | 11/15/2021 | Corrections Issued | JOSE AVILA |
| SGSOV-Seismic Gas S/O Valve | 11/15/2021 | SGSOV Approved | JOSE AVILA |
| Smoke Detectors | 11/15/2021 | Approved | JOSE AVILA |
| Final | 11/16/2021 | Corrections Issued | JOSE AVILA |
| Final | 2/18/2022 | OK to Issue CofO | JOSE AVILA |