686 E 48TH ST 90011
Certificate Information: 686 E 48TH ST 90011
- Application / Permit
- 21014-10000-03519
- Plan Check / Job No.
- B21LA13037
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERSION (E) 2 CAR GARGAE AND GROUND FLOOR ADDITION TO CREAT ADU PER LAMC 12.22 A.33(c) AND (d) WITH ATTACHED STORAGE
- Permit Issued
- Issued on 5/2/2022
- Issuing Office
- Metro
- Current Status
- CofO Issued on 3/18/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/12/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 8/19/2021 | KHEDER ALRAZAA |
| Corrections Issued | 8/20/2021 | KHEDER ALRAZAA |
| Quality Review Completed | 8/26/2021 | JASON HEALEY |
| Building Plans Picked Up | 9/1/2021 | APPLICANT |
| Applicant returned to address corrections | 10/28/2021 | KHEDER ALRAZAA |
| Plan Check Approved | 4/12/2022 | KHEDER ALRAZAA |
| Issued | 5/2/2022 | APPLICANT |
| CofO in Progress | 3/11/2025 | ALEJANDRO DE ARTOLA |
| Permit Finaled | 3/18/2025 | DEROLD HAUFF |
| CofO Issued | 3/18/2025 | DEROLD HAUFF |
| Permit Finaled | 3/18/2025 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 10/4/2021 | RENZ SORIANO |
| Eng Process Fee Ord 176,300 | Cleared | 10/12/2021 | RENZ SORIANO |
| Sewer availability | Cleared | 10/12/2021 | RENZ SORIANO |
| Low Impact Development | Cleared | 12/10/2021 | CHRIS PARK |
| Hydrant and Access approval | Cleared | 1/29/2022 | GILBERT URREA |
| Roof/Waste drainage to street | Cleared | 3/10/2022 | AMAAN MALIK |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Schaefer,, Jeffrey Ambrose; Lic. No.: C91734 | 3325 E 4TH ST LONG BEACH, CA 90814 |
Inspector Information
| ALEJANDRO DE ARTOLA, (213) 202-3128 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 5/3/2023 | Corrections Issued | BRENDAN MORELLI |
| Footing/Foundation/Slab | 5/30/2023 | Corrections Issued | BRENDAN MORELLI |
| Footing/Foundation/Slab | 6/29/2023 | Not Ready for Inspection | ALIZAH MAYAGOITIA |
| Footing/Foundation/Slab | 7/13/2023 | Approved | BRENDAN MORELLI |
| BUILDING-Rough-Frame | 7/27/2023 | Partial Approval | ALEJANDRO DE ARTOLA |
| Gas Test | 7/27/2023 | Corrections Issued | ALEJANDRO DE ARTOLA |
| PLUMBING-Rough | 7/27/2023 | Partial Approval | ALEJANDRO DE ARTOLA |
| Sewer | 7/27/2023 | Partial Approval | ALEJANDRO DE ARTOLA |
| Gas Test | 8/3/2023 | Partial Approval | ALEJANDRO DE ARTOLA |
| Insulation | 8/3/2023 | Partial Approval | ALEJANDRO DE ARTOLA |
| Sewer | 8/3/2023 | Partial Approval | ALEJANDRO DE ARTOLA |
| Floor/Roof Diaphrgm/Shear Wall | 8/4/2023 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Floor/Roof Diaphrgm/Shear Wall | 8/9/2023 | Partial Approval | ALEJANDRO DE ARTOLA |
| BUILDING-Rough-Frame | 8/25/2023 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Floor/Roof Diaphrgm/Shear Wall | 8/25/2023 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Green Building Rough | 8/25/2023 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Wood Frame | 8/25/2023 | Corrections Issued | ALEJANDRO DE ARTOLA |
| ELECTRICAL-Rough | 9/8/2023 | Corrections Issued | ALEJANDRO DE ARTOLA |
| PLUMBING-Rough | 9/8/2023 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Shower Pan | 9/8/2023 | Corrections Issued | ALEJANDRO DE ARTOLA |
| ELECTRICAL-Rough | 9/14/2023 | Not Ready for Inspection | JOSEPH MCGARRY |
| HVAC-Rough | 9/14/2023 | Corrections Issued | JOSEPH MCGARRY |
| Interior/Exterior Lathing | 9/14/2023 | Not Ready for Inspection | JOSEPH MCGARRY |
| PLUMBING-Rough | 9/14/2023 | Approved | JOSEPH MCGARRY |
| Sewer | 9/14/2023 | Approved | JOSEPH MCGARRY |
| Shower Pan | 9/14/2023 | Approved | JOSEPH MCGARRY |
| BUILDING-Rough-Frame | 9/26/2023 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Green Building Rough | 9/26/2023 | Corrections Issued | ALEJANDRO DE ARTOLA |
| HVAC-Rough | 9/26/2023 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Interior/Exterior Lathing | 9/26/2023 | Partial Approval | ALEJANDRO DE ARTOLA |
| BUILDING-Rough-Frame | 11/28/2023 | Approved | ALEJANDRO DE ARTOLA |
| ELECTRICAL-Rough | 11/28/2023 | Approved | ALEJANDRO DE ARTOLA |
| Green Building Rough | 11/28/2023 | Approved | ALEJANDRO DE ARTOLA |
| HVAC-Rough | 11/28/2023 | Approved | ALEJANDRO DE ARTOLA |
| Insulation | 11/28/2023 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Drywall Nailing | 1/22/2024 | Approved | JOSE MACIAS |
| HVAC-Rough | 7/16/2024 | Not Ready for Inspection | DAVID FEILER |
| ELECTRICAL-Final | 8/22/2024 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Green Building Final | 8/22/2024 | Approved | ALEJANDRO DE ARTOLA |
| HVAC-Final | 8/22/2024 | Corrections Issued | ALEJANDRO DE ARTOLA |
| PLUMBING-Final | 8/22/2024 | Corrections Issued | ALEJANDRO DE ARTOLA |
| ELECTRICAL-Final | 9/5/2024 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Final | 9/5/2024 | Corrections Issued | ALEJANDRO DE ARTOLA |
| HVAC-Final | 9/5/2024 | Approved | ALEJANDRO DE ARTOLA |
| PLUMBING-Final | 9/5/2024 | Corrections Issued | ALEJANDRO DE ARTOLA |
| ELECTRICAL-Final | 9/10/2024 | Approved | ALEJANDRO DE ARTOLA |
| Green Building Final | 9/10/2024 | Corrections Issued | ALEJANDRO DE ARTOLA |
| HVAC-Final | 9/10/2024 | Approved | ALEJANDRO DE ARTOLA |
| Final | 10/1/2024 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Gas Test | 10/1/2024 | Approved | ALEJANDRO DE ARTOLA |
| PLUMBING-Final | 10/1/2024 | Approved | ALEJANDRO DE ARTOLA |
| SGSOV-Seismic Gas S/O Valve | 10/1/2024 | SGSOV Approved | ALEJANDRO DE ARTOLA |
| Service/Power Release | 10/1/2024 | Approved | ALEJANDRO DE ARTOLA |
| Smoke Detectors | 10/1/2024 | Approved | ALEJANDRO DE ARTOLA |
| Final | 3/3/2025 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Green Building Final | 3/3/2025 | Corrections Issued | ALEJANDRO DE ARTOLA |
| ELECTRICAL-Final | 3/6/2025 | Approved | ALEJANDRO DE ARTOLA |
| Final | 3/6/2025 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Green Building Final | 3/6/2025 | Approved | ALEJANDRO DE ARTOLA |
| Final | 3/10/2025 | OK to Issue CofO | ALEJANDRO DE ARTOLA |