5066 E HENDERSON ST 90032

Certificate Information: 5066 E HENDERSON ST 90032

Application / Permit
21014-10000-03515
Plan Check / Job No.
B21LA13021
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
eplan CONVERT EXISTING DETACHED GARAGE INTO AN ACCESSORY DWELLING UNIT PER ORDINANCE (WITH NEW GROUND FLOOR ADDITION).
Permit Issued
Issued on 5/17/2022
Issuing Office
Current Status
CofO Issued on 9/10/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 7/22/2021 APPLICANT
Assigned to Plan Check Engineer 7/27/2021 MICHAEL LOPEZ
Corrections Issued 7/27/2021 MICHAEL LOPEZ
Applicant returned to address corrections 4/6/2022 MICHAEL LOPEZ
Applicant returned to address corrections 4/18/2022 MICHAEL LOPEZ
Applicant returned to address corrections 5/12/2022 MICHAEL LOPEZ
Plan Check Approved 5/16/2022 MICHAEL LOPEZ
Issued 5/17/2022 APPLICANT
CofO in Progress 9/6/2024 LILIANA PORTILLO
CofO Issued 9/10/2024 RUBEN SALAS
Permit Finaled 9/10/2024 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 10/9/2021 CECILIO NAVARRO
Roof/Waste drainage to street Cleared 10/9/2021 CECILIO NAVARRO
Sewer availability Cleared 10/9/2021 CECILIO NAVARRO
Eng Process Fee Ord 176,300 Cleared 10/13/2021 CECILIO NAVARRO
Hydrant and Access approval Cleared 11/5/2021 KURT CORRAL
"D" conditions Cleared 3/17/2022 ANACANY HURTADO
"Q" conditions Cleared 3/17/2022 ANACANY HURTADO
ZI Cleared 3/17/2022 ANACANY HURTADO
GPI Written Notices Cleared 4/6/2022 MICHAEL LOPEZ
Grading Pre-Inspection Cleared 4/6/2022 MATTHEW JENKINS
Miscellaneous Cleared 4/13/2022 ALBERT TAM

Contact Information

Contractor Owner-Builder       ,
Engineer Park,, Juntae; Lic. No.: C65104 3055 WILSHIRE BLVD 880      LOS ANGELES, CA 90010

Inspector Information

No Data Available.

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 12/5/2022 Partial Approval ALIZAH MAYAGOITIA
Footing/Foundation/Slab 12/15/2022 Corrections Issued AMY COLIN
Footing/Foundation/Slab 12/21/2022 Not Ready for Inspection AMY COLIN
Excavation/Setback/Form/Re-Bar 1/27/2023 Corrections Issued AMY COLIN
Footing/Foundation/Slab 1/27/2023 Not Ready for Inspection AMY COLIN
Excavation/Setback/Form/Re-Bar 2/15/2023 Approved AMY COLIN
Footing/Foundation/Slab 2/15/2023 Approved AMY COLIN
Pre-Inspection 4/26/2023 Partial Inspection AMY COLIN
Pre-Inspection 6/15/2023 Approved AMY COLIN
BUILDING-Rough-Frame 7/21/2023 Approved AMY COLIN
ELECTRICAL-Rough 7/21/2023 Approved AMY COLIN
Green Building Rough 7/21/2023 Approved AMY COLIN
HVAC-Rough 7/21/2023 Partial Approval AMY COLIN
PLUMBING-Rough 7/21/2023 Approved AMY COLIN
Sewer 7/21/2023 Approved AMY COLIN
Insulation 8/18/2023 Approved AMY COLIN
Interior/Exterior Lathing 8/18/2023 Approved AMY COLIN
Drywall Nailing 8/31/2023 Approved AMY COLIN
Interior/Exterior Lathing 8/31/2023 Partial Approval AMY COLIN
Shower Pan 8/31/2023 Approved AMY COLIN
Interior/Exterior Lathing 9/14/2023 Approved AMY COLIN
ELECTRICAL-Final 6/24/2024 Not Ready for Inspection LILIANA PORTILLO
Final 6/24/2024 Corrections Issued LILIANA PORTILLO
Green Building Final 6/24/2024 Not Ready for Inspection LILIANA PORTILLO
HVAC-Final 6/24/2024 Not Ready for Inspection LILIANA PORTILLO
PLUMBING-Final 6/24/2024 Not Ready for Inspection LILIANA PORTILLO
SGSOV-Seismic Gas S/O Valve 6/24/2024 SGSOV Not Ready LILIANA PORTILLO
Smoke Detectors 6/24/2024 Approved LILIANA PORTILLO
ELECTRICAL-Final 7/3/2024 Approved LILIANA PORTILLO
Final 7/3/2024 Corrections Issued LILIANA PORTILLO
Green Building Final 7/3/2024 Approved LILIANA PORTILLO
HVAC-Final 7/3/2024 Approved LILIANA PORTILLO
PLUMBING-Final 7/3/2024 Approved LILIANA PORTILLO
SGSOV-Seismic Gas S/O Valve 7/3/2024 SGSOV Approved LILIANA PORTILLO
Final 7/30/2024 Not Ready for Inspection LILIANA PORTILLO
Final 8/29/2024 Conditional Approval LILIANA PORTILLO
Final 9/6/2024 OK to Issue CofO LILIANA PORTILLO