630 N MICHELTORENA ST 90026

Certificate Information: 630 N MICHELTORENA ST 90026

Application / Permit
21014-10000-03497
Plan Check / Job No.
B21LA12946
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
CONVERT EXISTING ATTACHED GARAGE TO LIVING SPACE AND ADDITIONS TO EXISTING SINGLE FAMILY DWELLING. REFRAME PORTIONS OF EXISTING ROOF AND FOUNDATION, INTERIOR AND EXTERIOR REMODEL. EXTERIOR ALTERATIONS FOR INFILL AND NEW OPENINGS. **PLAN CHECK ONLY WAS CHARGED UNDER 21014-10001-03497 FOR CHANGES** **SEE COMMENTS
Permit Issued
Issued on 9/14/2022
Issuing Office
Metro
Current Status
CofO Issued on 3/8/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 7/9/2021 APPLICANT
Assigned to Plan Check Engineer 7/15/2021 AUNG SOE
Corrections Issued 7/20/2021 AUNG SOE
Applicant returned to address corrections 12/1/2021 LUKE GONZALES
Applicant returned to address corrections 3/1/2022 RACHEL BEYENE
Applicant returned to address corrections 8/16/2022 GEORGE ALVAREZ
Building Plans Picked Up 8/19/2022 APPLICANT
Issued 9/14/2022 APPLICANT
CofO in Progress 12/20/2023 ALIZAH MAYAGOITIA
CofO Issued 3/8/2024 DEROLD HAUFF
Permit Finaled 3/8/2024 DEROLD HAUFF

Permit Application Clearance Information

Sewer availability Cleared 7/30/2021 CECILIO NAVARRO
Eng Process Fee Ord 176,300 Cleared 8/3/2021 CECILIO NAVARRO
GPI Written Notices Cleared 8/3/2021 AUNG SOE
Grading Pre-Inspection Cleared 8/3/2021 BRIAN MILLER
ZA Case Cleared 8/4/2021 LOUIS ORTEGA
Hydrant and Access approval Cleared 9/13/2021 RUEL COLE
Low Impact Development Cleared 3/8/2022 LONDY ALVARADO
Roof/Waste drainage to street Cleared 8/25/2022 AMAAN MALIK

Contact Information

Contractor Golden Age Construction Inc; Lic. No.: 1040171-B 8265 SUNSET BLVD UNIT 205      WEST HOLLYWOOD, CA 90046
Engineer Manesh,, Behnam Abraham; Lic. No.: C38454 17337 VENTURA BLVD STE 112      ENCINO, CA 91316

Inspector Information

FREDDIE RIVERA, (213) 202-3437 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 3/30/2023 Conditional Approval FREDDIE RIVERA
Footing/Foundation/Slab 4/4/2023 Approved FREDDIE RIVERA
METHANE-Barrier 4/4/2023 Approved FREDDIE RIVERA
METHANE-Subgrade 4/4/2023 Approved FREDDIE RIVERA
Wood Frame 4/19/2023 Corrections Issued FREDDIE RIVERA
ELECTRICAL-Rough 6/6/2023 Approved FREDDIE RIVERA
HVAC-Rough 6/6/2023 Approved FREDDIE RIVERA
PLUMBING-Rough 6/6/2023 Approved FREDDIE RIVERA
BUILDING-Rough-Frame 6/13/2023 Partial Inspection FREDDIE RIVERA
Deputy Wood Construction 6/13/2023 Conditional Approval FREDDIE RIVERA
Green Building Rough 6/13/2023 Partial Inspection FREDDIE RIVERA
METHANE-Rough 6/13/2023 Corrections Issued FREDDIE RIVERA
BUILDING-Rough-Frame 6/21/2023 Approved FREDDIE RIVERA
Green Building Rough 6/21/2023 Approved FREDDIE RIVERA
METHANE-Rough 6/21/2023 Approved FREDDIE RIVERA
Shower Pan 6/21/2023 Partial Approval FREDDIE RIVERA
Interior/Exterior Lathing 6/28/2023 Partial Approval FREDDIE RIVERA
Shower Pan 6/28/2023 Approved FREDDIE RIVERA
Insulation 7/18/2023 Corrections Issued FREDDIE RIVERA
Interior/Exterior Lathing 7/18/2023 Partial Inspection FREDDIE RIVERA
Insulation 7/24/2023 Approved FREDDIE RIVERA
Interior/Exterior Lathing 7/24/2023 Approved FREDDIE RIVERA
Drywall Nailing 8/31/2023 Approved FREDDIE RIVERA
ELECTRICAL-Final 11/28/2023 Approved FREDDIE RIVERA
Final 11/28/2023 Corrections Issued FREDDIE RIVERA
Green Building Final 11/28/2023 Approved FREDDIE RIVERA
HVAC-Final 11/28/2023 Approved FREDDIE RIVERA
PLUMBING-Final 11/28/2023 Approved FREDDIE RIVERA
SGSOV-Seismic Gas S/O Valve 11/28/2023 SGSOV Approved FREDDIE RIVERA
Smoke Detectors 11/28/2023 Approved FREDDIE RIVERA
Final 12/19/2023 OK to Issue CofO ALIZAH MAYAGOITIA