4447 N BELLINGHAM AVE 91604
Certificate Information: 4447 N BELLINGHAM AVE 91604
- Application / Permit
- 21014-10000-03465
- Plan Check / Job No.
- B21LA12821
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- ADDITION AT REAR OF EXISTING ONE STORY SINGLE FAMILY DWELLING WITH COVERED PATIO PER ENGINEER DESIGN. NFPA 13D THROUGHOUT.
- Permit Issued
- Issued on 2/12/2022
- Issuing Office
- Current Status
- CofO Issued on 12/4/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/8/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 7/14/2021 | ZAW HAN |
| Corrections Issued | 7/21/2021 | ZAW HAN |
| Applicant returned to address corrections | 1/26/2022 | GEORGE ALVAREZ |
| Plan Check Approved | 2/1/2022 | GEORGE ALVAREZ |
| Issued | 2/12/2022 | APPLICANT |
| Building Plans Picked Up | 2/23/2022 | APPLICANT |
| CofO in Progress | 11/14/2024 | CHRISTOPHE COCHRAN |
| Permit Finaled | 12/4/2024 | RUBEN SALAS |
| CofO Issued | 12/4/2024 | RUBEN SALAS |
| Permit Finaled | 12/4/2024 | RUBEN SALAS |
Permit Application Clearance Information
| ZI | Cleared | 9/16/2021 | MIGUEL GAMBOA |
| Sewer availability | Cleared | 9/17/2021 | CARLOS AGUILERA |
| Eng Process Fee Ord 176,300 | Cleared | 10/13/2021 | CARLOS AGUILERA |
| Low Impact Development | Cleared | 11/10/2021 | TA ANH |
| Roof/Waste drainage to street | Cleared | 11/13/2021 | CARLOS AGUILERA |
| Hydrant and Access approval | Cleared | 12/17/2021 | GILBERT URREA |
Contact Information
| Contractor | Brennan Construction; Lic. No.: 965776-B | 445 N. FLORENCE ST BURBANK, CA 91505 |
| Engineer | Espino,, Manuel A; Lic. No.: C55526 | 12109 WOODRUFF AVE DOWNEY, CA 90241 |
Inspector Information
| CHRISTOPHE COCHRAN, (818) 374-1165 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 3/22/2022 | Conditional Approval | CALEB MEISTER |
| Footing/Foundation/Slab | 3/22/2022 | Partial Approval | ARAM AVEDISIAN |
| Deputy Drilled-In Anchors | 4/6/2022 | Conditional Approval | ARAM AVEDISIAN |
| BUILDING-Rough-Frame | 4/7/2022 | Partial Approval | ARAM AVEDISIAN |
| Footing/Foundation/Slab | 4/7/2022 | Partial Approval | ARAM AVEDISIAN |
| PLUMBING-Rough | 4/26/2022 | Partial Approval | ARAM AVEDISIAN |
| Deputy Drilled-In Anchors | 6/27/2022 | Conditional Approval | CHRISTOPHE COCHRAN |
| Floor/Roof Diaphrgm/Shear Wall | 6/30/2022 | Partial Approval | CHRISTOPHE COCHRAN |
| Footing/Foundation/Slab | 6/30/2022 | Approved | CHRISTOPHE COCHRAN |
| Insulation | 8/16/2022 | Partial Approval | CHRISTOPHE COCHRAN |
| BUILDING-Rough-Frame | 11/9/2022 | Not Ready for Inspection | CHRISTOPHE COCHRAN |
| ELECTRICAL-Rough | 11/9/2022 | Not Ready for Inspection | CHRISTOPHE COCHRAN |
| Green Building Rough | 11/9/2022 | Approved | CHRISTOPHE COCHRAN |
| HVAC-Rough | 11/9/2022 | Not Ready for Inspection | CHRISTOPHE COCHRAN |
| PLUMBING-Rough | 11/9/2022 | Not Ready for Inspection | CHRISTOPHE COCHRAN |
| Rough-Elec/Plmb/HVAC | 11/9/2022 | Not Ready for Inspection | CHRISTOPHE COCHRAN |
| BUILDING-Rough-Frame | 11/17/2022 | Corrections Issued | ROBERT GOLD |
| ELECTRICAL-Rough | 11/17/2022 | Approved | ROBERT GOLD |
| HVAC-Rough | 11/17/2022 | Conditional Approval | ROBERT GOLD |
| PLUMBING-Rough | 11/17/2022 | Approved | ROBERT GOLD |
| Rough-Elec/Plmb/HVAC | 11/17/2022 | Not Ready for Inspection | ROBERT GOLD |
| Insulation | 11/23/2022 | Approved | CHRISTOPHE COCHRAN |
| Interior/Exterior Lathing | 11/23/2022 | Partial Approval | CHRISTOPHE COCHRAN |
| Drywall Nailing | 12/7/2022 | Not Ready for Inspection | MICHEL ABAJAN |
| Drywall Nailing | 12/12/2022 | Approved | CHRISTOPHE COCHRAN |
| Shower Pan | 1/30/2023 | Approved | CHRISTOPHE COCHRAN |
| Interior/Exterior Lathing | 2/6/2023 | Approved | THOMAS FINNILA |
| Gas Test | 7/24/2023 | Approved | CHRISTOPHE COCHRAN |
| BUILDING-Rough-Frame | 1/19/2024 | Approved | CHRISTOPHE COCHRAN |
| Final | 1/19/2024 | Corrections Issued | CHRISTOPHE COCHRAN |
| Green Building Final | 1/19/2024 | Not Ready for Inspection | CHRISTOPHE COCHRAN |
| SGSOV-Seismic Gas S/O Valve | 1/19/2024 | SGSOV Approved | CHRISTOPHE COCHRAN |
| Smoke Detectors | 1/19/2024 | Not Ready for Inspection | CHRISTOPHE COCHRAN |
| Wood Frame | 3/28/2024 | Approved | CHRISTOPHE COCHRAN |
| Final | 11/14/2024 | OK to Issue CofO | CHRISTOPHE COCHRAN |
| Green Building Final | 11/14/2024 | Approved | CHRISTOPHE COCHRAN |
| Smoke Detectors | 11/14/2024 | Approved | CHRISTOPHE COCHRAN |