1037 N ILIFF ST 90272
Certificate Information: 1037 N ILIFF ST 90272
- Application / Permit
- 21014-10000-03451
- Plan Check / Job No.
- B21LA12777
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- ADDITION TO (E) SFD AND INTERIOR REMODEL WITH WINDOW CHANGE OUT
- Permit Issued
- Issued on 11/16/2021
- Issuing Office
- Current Status
- Permit Finaled on 2/28/2024
Permit Application Status History
| Submitted | 7/13/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 7/21/2021 | FERNANDO FLORES |
| Corrections Issued | 7/22/2021 | FERNANDO FLORES |
| Applicant returned to address corrections | 10/14/2021 | GEORGE ALVAREZ |
| Plan Check Approved | 11/4/2021 | JOSEPH RAFOLS |
| Issued | 11/16/2021 | APPLICANT |
| Building Plans Picked Up | 11/18/2021 | APPLICANT |
| CofO in Progress | 9/27/2023 | OGANES TARAKHCHYAN |
| Permit Finaled | 2/28/2024 | KENNETH NAGLE |
| No Progress | 2/28/2024 | KENNETH NAGLE |
| CofO in Progress | 2/28/2024 | KENNETH NAGLE |
Permit Application Clearance Information
| Roof/Waste drainage to street | Cleared | 9/8/2021 | DINAH GARIN |
| Eng Process Fee Ord 176,300 | Cleared | 9/10/2021 | DINAH GARIN |
| Grading Pre-Inspection | Cleared | 10/14/2021 | FERNANDO FLORES |
Contact Information
| Architect | Herrero,, Andre; Lic. No.: C38434 | 6253 HOLLY MONT DR LOS ANGELES, CA 90068 |
| Contractor | Lyons Development; Lic. No.: 969576-B | 8560 W SUNSET BLVD STE 424 WEST HOLLYWOOD, CA 90069 |
| Engineer | Khanjian,, Hovik J; Lic. No.: C51609 | 326 S. SPARKS STREET BURBANK, CA 91506 |
Inspector Information
| TEMISTOCLES CAAL, (213) 653-1908 | Office Hours: 7:00-8:00 AM MON-FRI |
| JESUS PINEDA, (213) 653-1908 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 11/18/2021 | Partial Inspection | JOHN KIDWELL |
| Deputy Drilled-In Anchors | 1/12/2022 | Partial Approval | JOHN KIDWELL |
| Footing/Foundation/Slab | 1/18/2022 | Corrections Issued | JOHN KIDWELL |
| Footing/Foundation/Slab | 1/21/2022 | Approved | JOHN KIDWELL |
| Floor/Roof Diaphrgm/Shear Wall | 8/25/2022 | Partial Inspection | KEVIN SARGSYAN |
| Deputy Wood Construction | 8/31/2022 | Conditional Approval | KEVIN SARGSYAN |
| Floor/Roof Diaphrgm/Shear Wall | 9/8/2022 | Partial Approval | KEVIN SARGSYAN |
| PLUMBING-Rough | 9/23/2022 | No Access for Inspection | KEVIN SARGSYAN |
| HVAC-Rough | 9/26/2022 | Corrections Issued | KEVIN SARGSYAN |
| ELECTRICAL-Rough | 9/28/2022 | Corrections Issued | KEVIN SARGSYAN |
| PLUMBING-Rough | 9/30/2022 | Corrections Issued | KEVIN SARGSYAN |
| HVAC-Rough | 10/7/2022 | Corrections Issued | CLAYTON GRAHAM |
| Deputy Wood Construction | 10/12/2022 | Conditional Approval | KEVIN SARGSYAN |
| ELECTRICAL-Rough | 10/18/2022 | Not Ready for Inspection | KEVIN SARGSYAN |
| HVAC-Rough | 10/18/2022 | Approved | KEVIN SARGSYAN |
| PLUMBING-Rough | 10/20/2022 | Partial Approval | KEVIN SARGSYAN |
| Floor/Roof Diaphrgm/Shear Wall | 10/21/2022 | Partial Approval | KEVIN SARGSYAN |
| ELECTRICAL-Rough | 10/24/2022 | Approved | KEVIN SARGSYAN |
| Interior/Exterior Lathing | 10/24/2022 | Not Ready for Inspection | KEVIN SARGSYAN |
| PLUMBING-Rough | 10/24/2022 | Not Ready for Inspection | KEVIN SARGSYAN |
| PLUMBING-Rough | 10/26/2022 | Approved | KEVIN SARGSYAN |
| Deputy Wood Construction | 10/27/2022 | Conditional Approval | KEVIN SARGSYAN |
| Floor/Roof Diaphrgm/Shear Wall | 10/28/2022 | Approved | KEVIN SARGSYAN |
| Green Building Rough | 10/28/2022 | Corrections Issued | KEVIN SARGSYAN |
| Shower Pan | 10/28/2022 | Not Ready for Inspection | KEVIN SARGSYAN |
| Shower Pan | 11/1/2022 | Approved | KEVIN SARGSYAN |
| BUILDING-Rough-Frame | 11/2/2022 | Corrections Issued | KEVIN SARGSYAN |
| Green Building Rough | 11/2/2022 | Approved | KEVIN SARGSYAN |
| Interior/Exterior Lathing | 11/2/2022 | Partial Approval | KEVIN SARGSYAN |
| Deputy Wood Construction | 11/21/2022 | No Access for Inspection | KENNETH NAGLE |
| BUILDING-Rough-Frame | 11/23/2022 | Approved | JUAN VALENZUELA |
| Insulation | 12/2/2022 | Approved | KEVIN SARGSYAN |
| Interior/Exterior Lathing | 12/9/2022 | Approved | KEVIN SARGSYAN |
| Drywall Nailing | 12/13/2022 | Approved | KEVIN SARGSYAN |
| Interior/Exterior Lathing | 5/10/2023 | Not Ready for Inspection | OGANES TARAKHCHYAN |
| Footing/Foundation/Slab | 5/12/2023 | Partial Approval | GERMAN RODRIGUEZ MENDOZA |
| Interior/Exterior Lathing | 5/12/2023 | Partial Approval | GERMAN RODRIGUEZ MENDOZA |
| ELECTRICAL-Final | 8/9/2023 | Not Ready for Inspection | OGANES TARAKHCHYAN |
| Service/Power Release | 8/9/2023 | Approved | OGANES TARAKHCHYAN |
| PLUMBING-Final | 8/10/2023 | Not Ready for Inspection | OGANES TARAKHCHYAN |
| HVAC-Final | 8/17/2023 | Not Ready for Inspection | OGANES TARAKHCHYAN |
| HVAC-Final | 8/29/2023 | Approved | ARAM AVEDISIAN |
| ELECTRICAL-Final | 9/11/2023 | Approved | OGANES TARAKHCHYAN |
| ELECTRICAL-Final | 9/14/2023 | Approved | OGANES TARAKHCHYAN |
| PLUMBING-Final | 9/14/2023 | Approved | OGANES TARAKHCHYAN |
| Final | 9/15/2023 | Corrections Issued | OGANES TARAKHCHYAN |
| Footing/Foundation/Slab | 9/15/2023 | Approved | OGANES TARAKHCHYAN |
| Green Building Final | 9/15/2023 | Approved | OGANES TARAKHCHYAN |
| SGSOV-Seismic Gas S/O Valve | 9/15/2023 | SGSOV Approved | OGANES TARAKHCHYAN |
| Smoke Detectors | 9/15/2023 | Approved | OGANES TARAKHCHYAN |
| Final | 9/21/2023 | Partial Approval | OGANES TARAKHCHYAN |
| Final | 9/26/2023 | Conditional Approval | OGANES TARAKHCHYAN |
| Final | 2/28/2024 | Permit Finaled | KENNETH NAGLE |