6418 E PLANADA AVE 90042
Certificate Information: 6418 E PLANADA AVE 90042
- Application / Permit
- 21014-10000-03434
- Plan Check / Job No.
- B21LA12744
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- FRIST STORY ADDITION TO (E) SFD FOR NEW TWO CAR GARAGE AND ACCESSORY DWELLING UNIT AND 2ND STORY ADDITION TO (E) SFD per ZA-2019-4511-ZAA-COA and AA-2019-4513-PMLA
- Permit Issued
- Issued on 11/4/2024
- Issuing Office
- Metro
- Current Status
- Issued on 11/4/2024
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 7/8/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 8/12/2021 | FARSHAD ALIMOHAMADI |
| Corrections Issued | 8/19/2021 | FARSHAD ALIMOHAMADI |
| Quality Review Completed | 8/20/2021 | SAI KHUM |
| Applicant returned to address corrections | 11/3/2021 | FARSHAD ALIMOHAMADI |
| Building Plans Picked Up | 11/19/2021 | APPLICANT |
| Applicant returned to address corrections | 8/14/2023 | FARSHAD ALIMOHAMADI |
| Applicant returned to address corrections | 12/1/2023 | FARSHAD ALIMOHAMADI |
| Applicant returned to address corrections | 12/6/2023 | FARSHAD ALIMOHAMADI |
| Plan Check Approved | 12/7/2023 | FARSHAD ALIMOHAMADI |
| Issued | 11/4/2024 | APPLICANT |
| Intent to Revoke-Status Void | 12/26/2025 | ALLEN MANALANSAN |
| Re-Activate Permit | 4/1/2026 | ALLEN MANALANSAN |
Permit Application Clearance Information
| Address approval | Cleared | 9/1/2021 | JEANIE LAM |
| Eng Process Fee Ord 176,300 | Cleared | 9/3/2021 | JEANIE LAM |
| Sewer availability | Cleared | 9/3/2021 | JEANIE LAM |
| Miscellaneous | Cleared | 9/8/2021 | TERRI OSBORNE |
| Tenant Habitability Plan | Cleared | 9/21/2021 | JEFFREY BULL |
| Hydrant and Access approval | Cleared | 10/20/2021 | MATTHEW CRAIG |
| Trees in Parkway | Cleared | 11/17/2021 | ADALBERTO VERA |
| Low Impact Development | Cleared | 2/15/2022 | SARAH YOUSSEF |
| Roof/Waste drainage to street | Cleared | 2/18/2022 | THAN WIN |
| Grading Pre-Inspection | Cleared | 3/31/2022 | FARSHAD ALIMOHAMADI |
| GPI Written Notices | Cleared | 4/5/2022 | FARSHAD ALIMOHAMADI |
| Permit | Cleared | 6/29/2023 | EVERARDO SANTOS |
| HPOZ | Cleared | 8/10/2023 | DANIEL CORONADO |
| ZA Case | Cleared | 8/10/2023 | DANIEL CORONADO |
| Tract Map conditions | Cleared | 9/8/2023 | DANIEL CORONADO |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Castillo,, Margarito; Lic. No.: S4808 | 1205 PINE AVE SUITE 201 LONG BEACH, CA 90813 |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 4/14/2025 | Approved | DAVID WILLIAMS |
| Deputy Drilled-In Anchors | 5/8/2025 | Approved | DAVID WILLIAMS |
| Excavation/Setback/Form/Re-Bar | 5/8/2025 | Not Ready for Inspection | DAVID WILLIAMS |
| Excavation/Setback/Form/Re-Bar | 5/27/2025 | Not Ready for Inspection | DAVID WILLIAMS |
| Footing/Foundation/Slab | 5/27/2025 | Not Ready for Inspection | DAVID WILLIAMS |
| Underground Mechanical | 7/1/2025 | Approved | DAVID WILLIAMS |
| Excavation/Setback/Form/Re-Bar | 7/9/2025 | Not Ready for Inspection | DAVID WILLIAMS |
| Footing/Foundation/Slab | 7/9/2025 | Approved | DAVID WILLIAMS |
| Underground Mechanical | 7/9/2025 | Approved | DAVID WILLIAMS |
| Footing/Foundation/Slab | 7/11/2025 | Approved | DAVID WILLIAMS |
| Floor/Roof Diaphrgm/Shear Wall | 9/22/2025 | Approved | DAVID WILLIAMS |
| Floor/Roof Diaphrgm/Shear Wall | 9/25/2025 | Partial Approval | NICHOLAS LOPEZ |
| Deputy Wood Construction | 11/26/2025 | Conditional Approval | DAVID WILLIAMS |
| Floor/Roof Diaphrgm/Shear Wall | 12/4/2025 | Corrections Issued | DAVID WILLIAMS |
| Wood Frame | 12/4/2025 | Corrections Issued | DAVID WILLIAMS |
| Floor/Roof Diaphrgm/Shear Wall | 12/10/2025 | Corrections Issued | DAVID WILLIAMS |
| Special/Order Compliance | 12/26/2025 | Corrections Issued | DAVID WILLIAMS |
| Drywall Nailing | 4/15/2026 | Partial Approval | DAVID WILLIAMS |
| Interior/Exterior Lathing | 4/15/2026 | Partial Approval | DAVID WILLIAMS |
| Drywall Nailing | 4/28/2026 | Approved | DAVID WILLIAMS |
| Interior/Exterior Lathing | 4/28/2026 | Partial Approval | DAVID WILLIAMS |
| Shower Pan | 4/28/2026 | Approved | DAVID WILLIAMS |