6418 E PLANADA AVE 90042

Certificate Information: 6418 E PLANADA AVE 90042

Application / Permit
21014-10000-03434
Plan Check / Job No.
B21LA12744
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
FRIST STORY ADDITION TO (E) SFD FOR NEW TWO CAR GARAGE AND ACCESSORY DWELLING UNIT AND 2ND STORY ADDITION TO (E) SFD per ZA-2019-4511-ZAA-COA and AA-2019-4513-PMLA
Permit Issued
Issued on 11/4/2024
Issuing Office
Metro
Current Status
Issued on 11/4/2024
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 7/8/2021 APPLICANT
Assigned to Plan Check Engineer 8/12/2021 FARSHAD ALIMOHAMADI
Corrections Issued 8/19/2021 FARSHAD ALIMOHAMADI
Quality Review Completed 8/20/2021 SAI KHUM
Applicant returned to address corrections 11/3/2021 FARSHAD ALIMOHAMADI
Building Plans Picked Up 11/19/2021 APPLICANT
Applicant returned to address corrections 8/14/2023 FARSHAD ALIMOHAMADI
Applicant returned to address corrections 12/1/2023 FARSHAD ALIMOHAMADI
Applicant returned to address corrections 12/6/2023 FARSHAD ALIMOHAMADI
Plan Check Approved 12/7/2023 FARSHAD ALIMOHAMADI
Issued 11/4/2024 APPLICANT
Intent to Revoke-Status Void 12/26/2025 ALLEN MANALANSAN
Re-Activate Permit 4/1/2026 ALLEN MANALANSAN

Permit Application Clearance Information

Address approval Cleared 9/1/2021 JEANIE LAM
Eng Process Fee Ord 176,300 Cleared 9/3/2021 JEANIE LAM
Sewer availability Cleared 9/3/2021 JEANIE LAM
Miscellaneous Cleared 9/8/2021 TERRI OSBORNE
Tenant Habitability Plan Cleared 9/21/2021 JEFFREY BULL
Hydrant and Access approval Cleared 10/20/2021 MATTHEW CRAIG
Trees in Parkway Cleared 11/17/2021 ADALBERTO VERA
Low Impact Development Cleared 2/15/2022 SARAH YOUSSEF
Roof/Waste drainage to street Cleared 2/18/2022 THAN WIN
Grading Pre-Inspection Cleared 3/31/2022 FARSHAD ALIMOHAMADI
GPI Written Notices Cleared 4/5/2022 FARSHAD ALIMOHAMADI
Permit Cleared 6/29/2023 EVERARDO SANTOS
HPOZ Cleared 8/10/2023 DANIEL CORONADO
ZA Case Cleared 8/10/2023 DANIEL CORONADO
Tract Map conditions Cleared 9/8/2023 DANIEL CORONADO

Contact Information

Contractor Owner-Builder       ,
Engineer Castillo,, Margarito; Lic. No.: S4808 1205 PINE AVE   SUITE 201    LONG BEACH, CA 90813

Inspector Information

No Data Available.

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 4/14/2025 Approved DAVID WILLIAMS
Deputy Drilled-In Anchors 5/8/2025 Approved DAVID WILLIAMS
Excavation/Setback/Form/Re-Bar 5/8/2025 Not Ready for Inspection DAVID WILLIAMS
Excavation/Setback/Form/Re-Bar 5/27/2025 Not Ready for Inspection DAVID WILLIAMS
Footing/Foundation/Slab 5/27/2025 Not Ready for Inspection DAVID WILLIAMS
Underground Mechanical 7/1/2025 Approved DAVID WILLIAMS
Excavation/Setback/Form/Re-Bar 7/9/2025 Not Ready for Inspection DAVID WILLIAMS
Footing/Foundation/Slab 7/9/2025 Approved DAVID WILLIAMS
Underground Mechanical 7/9/2025 Approved DAVID WILLIAMS
Footing/Foundation/Slab 7/11/2025 Approved DAVID WILLIAMS
Floor/Roof Diaphrgm/Shear Wall 9/22/2025 Approved DAVID WILLIAMS
Floor/Roof Diaphrgm/Shear Wall 9/25/2025 Partial Approval NICHOLAS LOPEZ
Deputy Wood Construction 11/26/2025 Conditional Approval DAVID WILLIAMS
Floor/Roof Diaphrgm/Shear Wall 12/4/2025 Corrections Issued DAVID WILLIAMS
Wood Frame 12/4/2025 Corrections Issued DAVID WILLIAMS
Floor/Roof Diaphrgm/Shear Wall 12/10/2025 Corrections Issued DAVID WILLIAMS
Special/Order Compliance 12/26/2025 Corrections Issued DAVID WILLIAMS
Drywall Nailing 4/15/2026 Partial Approval DAVID WILLIAMS
Interior/Exterior Lathing 4/15/2026 Partial Approval DAVID WILLIAMS
Drywall Nailing 4/28/2026 Approved DAVID WILLIAMS
Interior/Exterior Lathing 4/28/2026 Partial Approval DAVID WILLIAMS
Shower Pan 4/28/2026 Approved DAVID WILLIAMS