15629 W LASSEN ST 91343

Certificate Information: 15629 W LASSEN ST 91343

Application / Permit
21014-10000-03429
Plan Check / Job No.
B21LA12718
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
ONE-STORY GROUND FLOOR ADDITION @ REAR OF (E) ONE STORY SFD
Permit Issued
Issued on 1/26/2022
Issuing Office
Current Status
CofO Issued on 7/8/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 7/7/2021 APPLICANT
Assigned to Plan Check Engineer 7/15/2021 AUNG SOE
Corrections Issued 7/20/2021 AUNG SOE
Applicant returned to address corrections 9/15/2021 SAMUEL GONZALEZ
Applicant returned to address corrections 12/16/2021 AUNG SOE
Plan Check Approved 12/21/2021 AUNG SOE
Building Plans Picked Up 12/23/2021 APPLICANT
Issued 1/26/2022 APPLICANT
CofO in Progress 6/27/2025 CHRISTOPHER ROJAS
Permit Finaled 7/8/2025 RUBEN SALAS
CofO Issued 7/8/2025 RUBEN SALAS
Permit Finaled 7/8/2025 RUBEN SALAS

Permit Application Clearance Information

Roof/Waste drainage to street Cleared 8/17/2021 LEE GUILBEAUX
Sewer availability Cleared 8/17/2021 LEE GUILBEAUX
Eng Process Fee Ord 176,300 Cleared 8/18/2021 LEE GUILBEAUX
Public Works-Highway Ded. Cleared 8/18/2021 LEE GUILBEAUX
Public Works-Sewers Cleared 8/18/2021 LEE GUILBEAUX
Hydrant and Access approval Cleared 9/10/2021 MATTHEW CRAIG

Contact Information

Contractor R & M Construction; Lic. No.: 847093-B 11329 COLLETT AVE      GRANADA HILLS, CA 91344
Engineer Le,, Thang Huu; Lic. No.: S4978 507 MAGELLAN RD      ARCADIA, CA 91007

Inspector Information

CHRISTOPHER ROJAS, (818) 374-1160 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Sewer 1/31/2022 Conditional Approval JESUS RODRIGUEZ
Deputy Drilled-In Anchors 2/1/2022 Conditional Approval JESUS RODRIGUEZ
Excavation/Setback/Form/Re-Bar 2/2/2022 Approved RAUL OLAGI
Footing/Foundation/Slab 2/2/2022 Approved RAUL OLAGI
Deputy Wood Construction 2/16/2022 Conditional Approval JESUS RODRIGUEZ
Deputy Wood Construction 2/18/2022 Conditional Approval JESUS RODRIGUEZ
Floor/Roof Diaphrgm/Shear Wall 2/18/2022 Partial Approval ROBERT GOLD
BUILDING-Rough-Frame 3/2/2022 Partial Approval JENNIFER RABUCHIN
ELECTRICAL-Rough 3/2/2022 Approved JENNIFER RABUCHIN
Green Building Rough 3/2/2022 Not Ready for Inspection JENNIFER RABUCHIN
HVAC-Rough 3/2/2022 Corrections Issued JENNIFER RABUCHIN
MERV13>=Rough 3/2/2022 Approved JENNIFER RABUCHIN
PLUMBING-Rough 3/2/2022 Approved JENNIFER RABUCHIN
HVAC-Rough 3/9/2022 Approved KRISTEN CAUSEY
Insulation 3/9/2022 Approved KRISTEN CAUSEY
Interior/Exterior Lathing 3/9/2022 Partial Approval KRISTEN CAUSEY
Shower Pan 3/9/2022 Approved KRISTEN CAUSEY
Drywall Nailing 3/14/2022 Not Ready for Inspection KRISTEN CAUSEY
Interior/Exterior Lathing 3/14/2022 Approved KRISTEN CAUSEY
Drywall Nailing 3/15/2022 Approved KRISTEN CAUSEY
Interior/Exterior Lathing 3/16/2022 Not Ready for Inspection MICHAEL TEMPLE
BUILDING-Rough-Frame 4/6/2022 Approved JENNIFER RABUCHIN
ELECTRICAL-Final 4/6/2022 Approved JENNIFER RABUCHIN
Final 4/6/2022 Corrections Issued JENNIFER RABUCHIN
Green Building Final 4/6/2022 Approved JENNIFER RABUCHIN
Green Building Rough 4/6/2022 Approved JENNIFER RABUCHIN
HVAC-Final 4/6/2022 Approved JENNIFER RABUCHIN
Interior/Exterior Lathing 4/6/2022 Approved JENNIFER RABUCHIN
MERV13>=Final 4/6/2022 Approved JENNIFER RABUCHIN
PLUMBING-Final 4/6/2022 Approved JENNIFER RABUCHIN
SGSOV-Seismic Gas S/O Valve 4/6/2022 SGSOV Approved JENNIFER RABUCHIN
Smoke Detectors 4/6/2022 Approved JENNIFER RABUCHIN
Final 6/27/2025 OK to Issue CofO CHRISTOPHER ROJAS