15641 W HIGH KNOLL ROAD 91436
Certificate Information: 15641 W HIGH KNOLL ROAD 91436
- Application / Permit
- 21014-10000-03406
- Plan Check / Job No.
- B21LA12639
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- ADDITION AND REMODEL TO SFD : ONE STORY ADDITION, REMODEL (E) KITCHEN, ADD NEW BATH TO BEDROOM #3. CONVERT NOOK TO (N) BEDROOM W/BATH, REMODEL POWDER ROOM.
- Permit Issued
- Issued on 10/12/2021
- Issuing Office
- Current Status
- CofO Issued on 2/2/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/6/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 7/12/2021 | JESSE JIMENEZ |
| Corrections Issued | 7/13/2021 | JESSE JIMENEZ |
| Plan Check Approved | 9/15/2021 | TSE MING HUANG |
| Issued | 10/12/2021 | APPLICANT |
| Building Plans Picked Up | 10/13/2021 | APPLICANT |
| CofO in Progress | 1/6/2023 | VINCENT HANLEY |
| Permit Finaled | 2/2/2023 | JOHN JANSON |
| CofO Issued | 2/2/2023 | JOHN JANSON |
Permit Application Clearance Information
| Grading Pre-Inspection | Cleared | 7/26/2021 | TIMOTHY POWELL |
| Eng Process Fee Ord 176,300 | Cleared | 8/26/2021 | CARLOS AGUILERA |
| Roof/Waste drainage to street | Cleared | 8/26/2021 | CARLOS AGUILERA |
| Sewer availability | Cleared | 8/26/2021 | CARLOS AGUILERA |
Contact Information
| Contractor | Flip It Homes Inc; Lic. No.: 1043456-B | 20501 VENTURA BLVD #135 WOODLAND HILLS, CA 91364 |
| Engineer | Madero,, Fidencio; Lic. No.: C81695 | 10002 PANGBORN AVE DOWNEY, CA 90240 |
Inspector Information
| THOMAS FINNILA, (818) 774-4324 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 1/11/2022 | Corrections Issued | DAVID SANDOVAL |
| Footing/Foundation/Slab | 1/19/2022 | Approved | DAVID SANDOVAL |
| PLUMBING-Rough | 2/22/2022 | Corrections Issued | DAVID SANDOVAL |
| Wood Frame | 4/27/2022 | Corrections Issued | DAVID SANDOVAL |
| BUILDING-Rough-Frame | 5/9/2022 | Approved | DAVID SANDOVAL |
| ELECTRICAL-Rough | 5/9/2022 | Approved | DAVID SANDOVAL |
| Floor/Roof Diaphrgm/Shear Wall | 5/9/2022 | Partial Approval | DAVID SANDOVAL |
| Green Building Rough | 5/9/2022 | Not Ready for Inspection | DAVID SANDOVAL |
| PLUMBING-Rough | 5/9/2022 | Not Ready for Inspection | DAVID SANDOVAL |
| Green Building Rough | 5/17/2022 | Not Ready for Inspection | DAVID SANDOVAL |
| PLUMBING-Rough | 5/17/2022 | Not Ready for Inspection | DAVID SANDOVAL |
| BUILDING-Rough-Frame | 5/20/2022 | Corrections Issued | VINCENT HANLEY |
| ELECTRICAL-Rough | 5/20/2022 | Approved | VINCENT HANLEY |
| HVAC-Rough | 5/20/2022 | Approved | VINCENT HANLEY |
| PLUMBING-Rough | 5/20/2022 | Partial Approval | VINCENT HANLEY |
| BUILDING-Rough-Frame | 6/15/2022 | Approved | VINCENT HANLEY |
| Floor/Roof Diaphrgm/Shear Wall | 6/15/2022 | Approved | VINCENT HANLEY |
| Green Building Rough | 6/15/2022 | Approved | VINCENT HANLEY |
| HVAC-Rough | 6/15/2022 | Approved | VINCENT HANLEY |
| PLUMBING-Rough | 6/15/2022 | Approved | VINCENT HANLEY |
| Insulation | 6/24/2022 | Approved | MORRIS JACKSON |
| Interior/Exterior Lathing | 6/24/2022 | Partial Approval | MORRIS JACKSON |
| Interior/Exterior Lathing | 6/30/2022 | Partial Approval | VINCENT HANLEY |
| Shower Pan | 6/30/2022 | Approved | VINCENT HANLEY |
| Drywall Nailing | 7/7/2022 | Approved | MORRIS JACKSON |
| Gas Test | 7/27/2022 | No Access for Inspection | VINCENT HANLEY |
| ELECTRICAL-Final | 11/7/2022 | Approved | VINCENT HANLEY |
| Final | 11/7/2022 | Corrections Issued | VINCENT HANLEY |
| Green Building Final | 11/7/2022 | Approved | VINCENT HANLEY |
| HVAC-Final | 11/7/2022 | Approved | VINCENT HANLEY |
| PLUMBING-Final | 11/7/2022 | Approved | VINCENT HANLEY |
| SGSOV-Seismic Gas S/O Valve | 11/7/2022 | SGSOV Approved | VINCENT HANLEY |
| Smoke Detectors | 11/7/2022 | Approved | VINCENT HANLEY |
| Final | 1/6/2023 | OK to Issue CofO | VINCENT HANLEY |