6022 N FAIR AVE 91606
Certificate Information: 6022 N FAIR AVE 91606
- Application / Permit
- 21014-10000-03403
- Plan Check / Job No.
- B21LA12605
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- ADDITION TO EXISTING 2 STORY SINGLE FAMILY DEWLLING WITH BREEZEWAY ATTACHED ADU. NEW DECK ON 2ND FLOOR AND NEW PORCH. "COMPLY WITH DEPARTMENT ORDER. PERMIT WILL EXPIRE 30 DAYS FROM ISSUANCE DATE."
- Permit Issued
- Issued on 2/23/2022
- Issuing Office
- Current Status
- Issued on 2/23/2022
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 7/14/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 7/21/2021 | RICARDO RAMIREZ |
| Corrections Issued | 7/21/2021 | RICARDO RAMIREZ |
| Applicant returned to address corrections | 9/1/2021 | ADAM HEGAZI |
| Applicant returned to address corrections | 10/26/2021 | SAMUEL GONZALEZ |
| Applicant returned to address corrections | 11/17/2021 | SHANGQIN XIE |
| Applicant returned to address corrections | 11/30/2021 | JOSEPH RAFOLS |
| Applicant returned to address corrections | 1/5/2022 | AUNG SOE |
| Applicant returned to address corrections | 1/15/2022 | LAWRENCE QUIRANTE |
| Applicant returned to address corrections | 1/28/2022 | LUKE GONZALES |
| Plan Check Approved | 2/18/2022 | JOSEPH RAFOLS |
| Issued | 2/23/2022 | APPLICANT |
| Building Plans Picked Up | 2/25/2022 | APPLICANT |
Permit Application Clearance Information
| ZA Case | Cleared | 7/27/2021 | LAUREN PADICK |
| ZA Case | Cleared | 7/27/2021 | LAUREN PADICK |
| Roof/Waste drainage to street | Cleared | 7/29/2021 | DAGOVERTO GUERRERO |
| Eng Process Fee Ord 176,300 | Cleared | 8/3/2021 | DAGOVERTO GUERRERO |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Ng,, Edward Tw; Lic. No.: C38552 | 979 E MUNCIE AVE FRESNO, CA 93720 |
Inspector Information
| ARA SINANIAN, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| HASANTHA WEERASEKARA, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| SCOTT SHUSTER, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| JOEL GUARDADO, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| MARIYA MIHALEVA, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| JOSE RUBIO, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| DAVID JAMES, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| DAVID HICKMAN, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| JOHN HAMILTON, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| JOHN STEPHENS, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| PIERRE VEGA, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| MARK VAN SLOOTEN, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| MICKEY YAMASHITA, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| KIM BEAUCHAMP, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| MARK DOVICO, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| THOMAS WOODS, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| RAUL VASQUEZ, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| AUGUSTUS ALBAS, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| LEO MILBAUER, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| MARIO CUEVAS, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 5/26/2022 | Partial Approval | KIM BEAUCHAMP |
| ELECTRICAL-Rough | 6/14/2022 | Partial Inspection | BRYAN MEYER |
| PLUMBING-Rough | 6/14/2022 | Partial Inspection | BRYAN MEYER |
| BUILDING-Rough-Frame | 6/15/2022 | Corrections Issued | KIM BEAUCHAMP |
| Green Building Rough | 6/15/2022 | Corrections Issued | KIM BEAUCHAMP |
| BUILDING-Rough-Frame | 6/23/2022 | Corrections Issued | KIM BEAUCHAMP |
| Green Building Rough | 6/23/2022 | Not Ready for Inspection | KIM BEAUCHAMP |
| Interior/Exterior Lathing | 7/8/2022 | Approved | KIM BEAUCHAMP |
| BUILDING-Rough-Frame | 10/14/2022 | Corrections Issued | KIM BEAUCHAMP |
| Final | 10/14/2022 | Not Ready for Inspection | KIM BEAUCHAMP |
| Footing/Foundation/Slab | 10/14/2022 | Not Ready for Inspection | KIM BEAUCHAMP |
| Green Building Final | 10/14/2022 | Not Ready for Inspection | KIM BEAUCHAMP |
| Green Building Rough | 10/14/2022 | Not Ready for Inspection | KIM BEAUCHAMP |
| SGSOV-Seismic Gas S/O Valve | 10/14/2022 | SGSOV Not Ready | KIM BEAUCHAMP |
| Smoke Detectors | 10/14/2022 | Not Ready for Inspection | KIM BEAUCHAMP |
| PLUMBING-Final | 11/16/2022 | Approved | KIM BEAUCHAMP |
| BUILDING-Rough-Frame | 9/11/2024 | Approved | THOMAS WOODS |
| ELECTRICAL-Final | 9/11/2024 | Not Ready for Inspection | THOMAS WOODS |
| Final | 9/11/2024 | Not Ready for Inspection | THOMAS WOODS |
| Green Building Final | 9/11/2024 | Not Ready for Inspection | THOMAS WOODS |
| Green Building Rough | 9/11/2024 | Approved | THOMAS WOODS |
| SGSOV-Seismic Gas S/O Valve | 9/11/2024 | SGSOV Approved | THOMAS WOODS |
| Smoke Detectors | 9/11/2024 | Approved | THOMAS WOODS |
| Final | 9/16/2024 | Not Ready for Inspection | THOMAS WOODS |
| Footing/Foundation/Slab | 9/16/2024 | Not Ready for Inspection | THOMAS WOODS |
| Green Building Final | 9/16/2024 | Not Ready for Inspection | THOMAS WOODS |
| Final | 3/3/2026 | Not Ready for Inspection | THOMAS WOODS |
| Footing/Foundation/Slab | 3/3/2026 | Not Ready for Inspection | THOMAS WOODS |
| Green Building Final | 3/3/2026 | Not Ready for Inspection | THOMAS WOODS |
| Final | 3/9/2026 | Not Ready for Inspection | THOMAS WOODS |
| Footing/Foundation/Slab | 3/9/2026 | Approved | THOMAS WOODS |
| Green Building Final | 3/9/2026 | Not Ready for Inspection | THOMAS WOODS |