3211 N TYBURN ST 90039

Certificate Information: 3211 N TYBURN ST 90039

Application / Permit
21014-10000-03393
Plan Check / Job No.
B21LA12560
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
ONE-STORY ADDITION TO SFD/GARAGE: ADD 78.5 SQ.FT. TO GARAGE AND CONVERTED TO FAMILY ROOM, BATHROOM AND LAUNDRY ROOM. ADD ATTACHED 2-CAR CARPORT. WIDEN DRIVEWAY ACCESS.
Permit Issued
Issued on 5/5/2022
Issuing Office
Metro
Current Status
CofO Issued on 2/12/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 7/6/2021 APPLICANT
Assigned to Plan Check Engineer 7/12/2021 JESSE JIMENEZ
Corrections Issued 7/13/2021 JESSE JIMENEZ
Applicant returned to address corrections 12/3/2021 DANIEL SANJUAN
Plan Check Approved 1/25/2022 DANIEL SANJUAN
Building Plans Picked Up 1/28/2022 APPLICANT
Issued 5/5/2022 APPLICANT
CofO in Progress 9/5/2022 CRAIG VAUGHAN
Permit Finaled 2/12/2023 DANIEL ORRANTE
CofO Issued 2/12/2023 DANIEL ORRANTE
Permit Finaled 2/12/2023 DANIEL ORRANTE

Permit Application Clearance Information

Miscellaneous Cleared 8/25/2021 JESSE JIMENEZ
Roof/Waste drainage to street Cleared 9/7/2021 NAZILA NOORIFAR
Sewer availability Cleared 9/7/2021 NAZILA NOORIFAR
Eng Process Fee Ord 176,300 Cleared 9/14/2021 NAZILA NOORIFAR

Contact Information

Contractor Owner-Builder       ,
Engineer Baich,, Brendon Chad; Lic. No.: C83347 PO BOX 8840      POMONA, CA 91701

Inspector Information

NICHOLAS LOPEZ, (213) 202-3224 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 5/9/2022 Not Ready for Inspection HAMIK HARTOUNIAN
Underground Mechanical 5/9/2022 Corrections Issued HAMIK HARTOUNIAN
PLUMBING-Rough 5/24/2022 Approved AMY COLIN
Underground Mechanical 5/24/2022 Approved AMY COLIN
Excavation/Setback/Form/Re-Bar 5/31/2022 Approved SCOTT FINNILA
Footing/Foundation/Slab 5/31/2022 Approved SCOTT FINNILA
ELECTRICAL-Rough 6/30/2022 Approved HAMIK HARTOUNIAN
Floor/Roof Diaphrgm/Shear Wall 6/30/2022 Partial Approval HAMIK HARTOUNIAN
HVAC-Rough 6/30/2022 Approved HAMIK HARTOUNIAN
PLUMBING-Rough 6/30/2022 Approved HAMIK HARTOUNIAN
Wood Frame 6/30/2022 Corrections Issued HAMIK HARTOUNIAN
Insulation 7/8/2022 Conditional Approval HAMIK HARTOUNIAN
Interior/Exterior Lathing 7/8/2022 Not Ready for Inspection HAMIK HARTOUNIAN
BUILDING-Rough-Frame 7/13/2022 Not Ready for Inspection HAMIK HARTOUNIAN
Green Building Rough 7/13/2022 Approved HAMIK HARTOUNIAN
Insulation 7/13/2022 Corrections Issued HAMIK HARTOUNIAN
BUILDING-Rough-Frame 7/21/2022 Approved HAMIK HARTOUNIAN
Insulation 7/21/2022 Approved HAMIK HARTOUNIAN
Interior/Exterior Lathing 7/21/2022 Conditional Approval HAMIK HARTOUNIAN
Drywall Nailing 7/25/2022 Approved CHARLES BOGHOSKHAN
ELECTRICAL-Final 9/2/2022 Approved CRAIG VAUGHAN
Final 9/2/2022 OK to Issue CofO CRAIG VAUGHAN
Green Building Final 9/2/2022 Approved CRAIG VAUGHAN
HVAC-Final 9/2/2022 Approved CRAIG VAUGHAN
PLUMBING-Final 9/2/2022 Approved CRAIG VAUGHAN
SGSOV-Seismic Gas S/O Valve 9/2/2022 SGSOV Approved CRAIG VAUGHAN
Smoke Detectors 9/2/2022 Approved CRAIG VAUGHAN