3211 N TYBURN ST 90039
Certificate Information: 3211 N TYBURN ST 90039
- Application / Permit
- 21014-10000-03393
- Plan Check / Job No.
- B21LA12560
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- ONE-STORY ADDITION TO SFD/GARAGE: ADD 78.5 SQ.FT. TO GARAGE AND CONVERTED TO FAMILY ROOM, BATHROOM AND LAUNDRY ROOM. ADD ATTACHED 2-CAR CARPORT. WIDEN DRIVEWAY ACCESS.
- Permit Issued
- Issued on 5/5/2022
- Issuing Office
- Metro
- Current Status
- CofO Issued on 2/12/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/6/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 7/12/2021 | JESSE JIMENEZ |
| Corrections Issued | 7/13/2021 | JESSE JIMENEZ |
| Applicant returned to address corrections | 12/3/2021 | DANIEL SANJUAN |
| Plan Check Approved | 1/25/2022 | DANIEL SANJUAN |
| Building Plans Picked Up | 1/28/2022 | APPLICANT |
| Issued | 5/5/2022 | APPLICANT |
| CofO in Progress | 9/5/2022 | CRAIG VAUGHAN |
| Permit Finaled | 2/12/2023 | DANIEL ORRANTE |
| CofO Issued | 2/12/2023 | DANIEL ORRANTE |
| Permit Finaled | 2/12/2023 | DANIEL ORRANTE |
Permit Application Clearance Information
| Miscellaneous | Cleared | 8/25/2021 | JESSE JIMENEZ |
| Roof/Waste drainage to street | Cleared | 9/7/2021 | NAZILA NOORIFAR |
| Sewer availability | Cleared | 9/7/2021 | NAZILA NOORIFAR |
| Eng Process Fee Ord 176,300 | Cleared | 9/14/2021 | NAZILA NOORIFAR |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Baich,, Brendon Chad; Lic. No.: C83347 | PO BOX 8840 POMONA, CA 91701 |
Inspector Information
| NICHOLAS LOPEZ, (213) 202-3224 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 5/9/2022 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| Underground Mechanical | 5/9/2022 | Corrections Issued | HAMIK HARTOUNIAN |
| PLUMBING-Rough | 5/24/2022 | Approved | AMY COLIN |
| Underground Mechanical | 5/24/2022 | Approved | AMY COLIN |
| Excavation/Setback/Form/Re-Bar | 5/31/2022 | Approved | SCOTT FINNILA |
| Footing/Foundation/Slab | 5/31/2022 | Approved | SCOTT FINNILA |
| ELECTRICAL-Rough | 6/30/2022 | Approved | HAMIK HARTOUNIAN |
| Floor/Roof Diaphrgm/Shear Wall | 6/30/2022 | Partial Approval | HAMIK HARTOUNIAN |
| HVAC-Rough | 6/30/2022 | Approved | HAMIK HARTOUNIAN |
| PLUMBING-Rough | 6/30/2022 | Approved | HAMIK HARTOUNIAN |
| Wood Frame | 6/30/2022 | Corrections Issued | HAMIK HARTOUNIAN |
| Insulation | 7/8/2022 | Conditional Approval | HAMIK HARTOUNIAN |
| Interior/Exterior Lathing | 7/8/2022 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| BUILDING-Rough-Frame | 7/13/2022 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| Green Building Rough | 7/13/2022 | Approved | HAMIK HARTOUNIAN |
| Insulation | 7/13/2022 | Corrections Issued | HAMIK HARTOUNIAN |
| BUILDING-Rough-Frame | 7/21/2022 | Approved | HAMIK HARTOUNIAN |
| Insulation | 7/21/2022 | Approved | HAMIK HARTOUNIAN |
| Interior/Exterior Lathing | 7/21/2022 | Conditional Approval | HAMIK HARTOUNIAN |
| Drywall Nailing | 7/25/2022 | Approved | CHARLES BOGHOSKHAN |
| ELECTRICAL-Final | 9/2/2022 | Approved | CRAIG VAUGHAN |
| Final | 9/2/2022 | OK to Issue CofO | CRAIG VAUGHAN |
| Green Building Final | 9/2/2022 | Approved | CRAIG VAUGHAN |
| HVAC-Final | 9/2/2022 | Approved | CRAIG VAUGHAN |
| PLUMBING-Final | 9/2/2022 | Approved | CRAIG VAUGHAN |
| SGSOV-Seismic Gas S/O Valve | 9/2/2022 | SGSOV Approved | CRAIG VAUGHAN |
| Smoke Detectors | 9/2/2022 | Approved | CRAIG VAUGHAN |