3936-3938 S SUTRO AVE 90008

Certificate Information: 3936-3938 S SUTRO AVE 90008

Application / Permit
21014-10000-03392
Plan Check / Job No.
B21LA12553
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
CONSTRUCT (N) ATTACHED ADU TO EXISTING ONE STORY SINGLE FAMILY DEWLLING (Attached ADU per Ordinance,LAMC 12.22 A.33(c) and (e)) INCLUDES (2) OPEN STANDARD STALLS.
Permit Issued
Issued on 4/26/2022
Issuing Office
Metro
Current Status
CofO Issued on 9/3/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 7/7/2021 APPLICANT
Assigned to Plan Check Engineer 7/14/2021 SINA KHOSRAVI
Corrections Issued 7/15/2021 SINA KHOSRAVI
Applicant returned to address corrections 9/14/2021 RACHEL BEYENE
Applicant returned to address corrections 1/24/2022 LUKE GONZALES
Applicant returned to address corrections 2/10/2022 AUNG SOE
Applicant returned to address corrections 2/13/2022 AUNG SOE
Applicant returned to address corrections 2/24/2022 TSE MING HUANG
Building Plans Picked Up 3/2/2022 APPLICANT
Applicant returned to address corrections 3/14/2022 MINA HABILI
Applicant returned to address corrections 3/22/2022 LAWRENCE QUIRANTE
Applicant returned to address corrections 4/1/2022 LAWRENCE QUIRANTE
Plan Check Approved 4/20/2022 LAWRENCE QUIRANTE
Issued 4/26/2022 APPLICANT
CofO Issued 9/3/2024 RUBEN SALAS
Permit Finaled 9/3/2024 RUBEN SALAS

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 7/28/2021 WALLIE JONG
Address approval Cleared 7/29/2021 WALLIE JONG
Roof/Waste drainage to street Cleared 7/29/2021 WALLIE JONG
Sewer availability Cleared 8/2/2021 WALLIE JONG
Construction near power lines Cleared 3/4/2022 TINA MIRANDA
Miscellaneous Cleared 3/17/2022 ALBERT TAM

Contact Information

Contractor Owner-Builder       ,

Inspector Information

LUIS CASTRO, (213) 202-3436 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 4/29/2022 Approved ANTHONY EGSON
ELECTRICAL-Rough 7/19/2022 Corrections Issued ANTHONY EGSON
Floor/Roof Diaphrgm/Shear Wall 7/19/2022 Approved ANTHONY EGSON
Green Building Rough 7/19/2022 Not Ready for Inspection ANTHONY EGSON
PLUMBING-Rough 7/19/2022 Corrections Issued ANTHONY EGSON
ELECTRICAL-Rough 8/5/2022 Approved ANTHONY EGSON
PLUMBING-Rough 8/30/2022 Approved ANTHONY EGSON
BUILDING-Rough-Frame 12/9/2022 Approved ALIZAH MAYAGOITIA
Green Building Rough 12/9/2022 Approved ALIZAH MAYAGOITIA
Insulation 12/14/2022 Approved ANTHONY EGSON
Interior/Exterior Lathing 12/14/2022 Approved ANTHONY EGSON
PLUMBING-Rough 6/14/2023 Partial Inspection ANTHONY EGSON
Drywall Nailing 7/17/2023 Approved ANTHONY EGSON
Interior/Exterior Lathing 9/25/2023 Approved ANTHONY EGSON
Shower Pan 9/25/2023 Approved ANTHONY EGSON
ELECTRICAL-Final 6/5/2024 Corrections Issued ANTHONY EGSON
Final 6/5/2024 Corrections Issued ANTHONY EGSON
Green Building Final 6/5/2024 Corrections Issued ANTHONY EGSON
PLUMBING-Final 6/5/2024 Approved ANTHONY EGSON
SGSOV-Seismic Gas S/O Valve 6/5/2024 SGSOV Approved ANTHONY EGSON
Smoke Detectors 6/5/2024 Approved ANTHONY EGSON
ELECTRICAL-Final 7/12/2024 Not Ready for Inspection ANTHONY EGSON
Final 7/12/2024 Not Ready for Inspection ANTHONY EGSON
Green Building Final 7/12/2024 Approved ANTHONY EGSON
Final 7/24/2024 Not Ready for Inspection ANTHONY EGSON
ELECTRICAL-Final 7/31/2024 Approved ANTHONY EGSON