6209 1/2 S BRYNHURST AVE 90043
Certificate Information: 6209 1/2 S BRYNHURST AVE 90043
- Application / Permit
- 21014-10000-03391
- Plan Check / Job No.
- B21LA12550
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW 2ND STORY (400 S.F) ADU ADDITION ABOVE (E) ONE STORY DETACHED GARAGE & ( 138.7 S.F ) GROUND FLOOR STORAGE ADDITION TO (E) GARAGE.
- Permit Issued
- Issued on 7/6/2022
- Issuing Office
- Metro
- Current Status
- CofO Issued on 9/5/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/6/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 8/12/2021 | GARO TELMI |
| Corrections Issued | 8/25/2021 | GARO TELMI |
| Quality Review Completed | 9/2/2021 | KEN GILL |
| Building Plans Picked Up | 9/8/2021 | APPLICANT |
| Applicant returned to address corrections | 11/3/2021 | GARO TELMI |
| Applicant returned to address corrections | 12/3/2021 | GARO TELMI |
| Applicant returned to address corrections | 2/18/2022 | GARO TELMI |
| Plan Check Approved | 5/6/2022 | GARO TELMI |
| Issued | 7/6/2022 | APPLICANT |
| CofO in Progress | 8/17/2023 | ENRIQUE MIRELES |
| CofO in Progress | 8/17/2023 | ENRIQUE MIRELES |
| Permit Finaled | 9/5/2023 | DEROLD HAUFF |
| CofO Issued | 9/5/2023 | DEROLD HAUFF |
| Permit Finaled | 9/5/2023 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 11/10/2021 | STEVE MELGAR |
| Low Impact Development | Cleared | 1/31/2022 | LONDY ALVARADO |
| Construction near power lines | Cleared | 2/16/2022 | RIDWAN HARDY |
| Roof/Waste drainage to street | Cleared | 5/18/2022 | JEANIE LAM |
| Eng Process Fee Ord 176,300 | Cleared | 5/19/2022 | JEANIE LAM |
| Sewer availability | Cleared | 5/19/2022 | JEANIE LAM |
Contact Information
| Contractor | Certified Construction & H V A C Services Inc; Lic. No.: 685117-B | 5827 ROSE AVE LONG BEACH, CA 90805 |
| Engineer | Espino,, Manuel A; Lic. No.: C55526 | 12109 WOODRUFF AVE DOWNEY, CA 90241 |
Inspector Information
| SALVADOR MARTINEZ, (213) 202-3479 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 7/29/2022 | Corrections Issued | JOAQUIN GREENOUGH |
| Footing/Foundation/Slab | 7/29/2022 | Not Ready for Inspection | JOAQUIN GREENOUGH |
| Underground Mechanical | 8/4/2022 | Approved | ENRIQUE MIRELES |
| Footing/Foundation/Slab | 8/9/2022 | Corrections Issued | ENRIQUE MIRELES |
| Gas Test | 8/9/2022 | Approved | ENRIQUE MIRELES |
| Excavation/Setback/Form/Re-Bar | 8/31/2022 | Approved | ENRIQUE MIRELES |
| Wood Frame | 11/8/2022 | Approved | ENRIQUE MIRELES |
| BUILDING-Rough-Frame | 12/5/2022 | Corrections Issued | ENRIQUE MIRELES |
| ELECTRICAL-Rough | 12/5/2022 | Not Ready for Inspection | ENRIQUE MIRELES |
| Green Building Rough | 12/5/2022 | Approved | ENRIQUE MIRELES |
| HVAC-Rough | 12/5/2022 | Not Ready for Inspection | ENRIQUE MIRELES |
| PLUMBING-Rough | 12/5/2022 | Not Ready for Inspection | ENRIQUE MIRELES |
| ELECTRICAL-Rough | 12/15/2022 | Approved | ENRIQUE MIRELES |
| Gas Test | 12/15/2022 | Approved | ENRIQUE MIRELES |
| PLUMBING-Rough | 12/15/2022 | Approved | ENRIQUE MIRELES |
| Rough-Elec/Plmb/HVAC | 1/3/2023 | Approved | ENRIQUE MIRELES |
| Wood Frame | 1/3/2023 | Approved | ENRIQUE MIRELES |
| Floor/Roof Diaphrgm/Shear Wall | 1/6/2023 | Approved | ENRIQUE MIRELES |
| Insulation | 1/6/2023 | Approved | ENRIQUE MIRELES |
| Drywall Nailing | 1/13/2023 | Approved | ENRIQUE MIRELES |
| Interior/Exterior Lathing | 1/13/2023 | Not Ready for Inspection | ENRIQUE MIRELES |
| Shower Pan | 1/13/2023 | Approved | ENRIQUE MIRELES |
| Interior/Exterior Lathing | 2/3/2023 | Approved | ENRIQUE MIRELES |
| ELECTRICAL-Final | 3/22/2023 | No Access for Inspection | ENRIQUE MIRELES |
| HVAC-Final | 3/22/2023 | No Access for Inspection | ENRIQUE MIRELES |
| PLUMBING-Final | 3/22/2023 | No Access for Inspection | ENRIQUE MIRELES |
| Service/Power Release | 3/22/2023 | No Access for Inspection | ENRIQUE MIRELES |
| BUILDING-Rough-Frame | 6/6/2023 | Approved | ENRIQUE MIRELES |
| ELECTRICAL-Final | 6/6/2023 | Approved | ENRIQUE MIRELES |
| Final | 6/6/2023 | Corrections Issued | ENRIQUE MIRELES |
| Footing/Foundation/Slab | 6/6/2023 | Approved | ENRIQUE MIRELES |
| Gas Test | 6/6/2023 | Approved | ENRIQUE MIRELES |
| Green Building Final | 6/6/2023 | Approved | ENRIQUE MIRELES |
| HVAC-Final | 6/6/2023 | Approved | ENRIQUE MIRELES |
| PLUMBING-Final | 6/6/2023 | Approved | ENRIQUE MIRELES |
| SGSOV-Seismic Gas S/O Valve | 6/6/2023 | SGSOV Approved | ENRIQUE MIRELES |
| Smoke Detectors | 6/6/2023 | Approved | ENRIQUE MIRELES |
| ELECTRICAL-Final | 7/24/2023 | Approved | ENRIQUE MIRELES |
| Final | 7/24/2023 | Corrections Issued | ENRIQUE MIRELES |
| Gas Test | 7/24/2023 | Approved | ENRIQUE MIRELES |
| PLUMBING-Final | 7/24/2023 | Approved | ENRIQUE MIRELES |
| Final | 8/11/2023 | OK to Issue CofO | ENRIQUE MIRELES |