6209 1/2 S BRYNHURST AVE 90043

Certificate Information: 6209 1/2 S BRYNHURST AVE 90043

Application / Permit
21014-10000-03391
Plan Check / Job No.
B21LA12550
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW 2ND STORY (400 S.F) ADU ADDITION ABOVE (E) ONE STORY DETACHED GARAGE & ( 138.7 S.F ) GROUND FLOOR STORAGE ADDITION TO (E) GARAGE.
Permit Issued
Issued on 7/6/2022
Issuing Office
Metro
Current Status
CofO Issued on 9/5/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 7/6/2021 APPLICANT
Assigned to Plan Check Engineer 8/12/2021 GARO TELMI
Corrections Issued 8/25/2021 GARO TELMI
Quality Review Completed 9/2/2021 KEN GILL
Building Plans Picked Up 9/8/2021 APPLICANT
Applicant returned to address corrections 11/3/2021 GARO TELMI
Applicant returned to address corrections 12/3/2021 GARO TELMI
Applicant returned to address corrections 2/18/2022 GARO TELMI
Plan Check Approved 5/6/2022 GARO TELMI
Issued 7/6/2022 APPLICANT
CofO in Progress 8/17/2023 ENRIQUE MIRELES
CofO in Progress 8/17/2023 ENRIQUE MIRELES
Permit Finaled 9/5/2023 DEROLD HAUFF
CofO Issued 9/5/2023 DEROLD HAUFF
Permit Finaled 9/5/2023 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 11/10/2021 STEVE MELGAR
Low Impact Development Cleared 1/31/2022 LONDY ALVARADO
Construction near power lines Cleared 2/16/2022 RIDWAN HARDY
Roof/Waste drainage to street Cleared 5/18/2022 JEANIE LAM
Eng Process Fee Ord 176,300 Cleared 5/19/2022 JEANIE LAM
Sewer availability Cleared 5/19/2022 JEANIE LAM

Contact Information

Contractor Certified Construction & H V A C Services Inc; Lic. No.: 685117-B 5827 ROSE AVE      LONG BEACH, CA 90805
Engineer Espino,, Manuel A; Lic. No.: C55526 12109 WOODRUFF AVE      DOWNEY, CA 90241

Inspector Information

SALVADOR MARTINEZ, (213) 202-3479 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 7/29/2022 Corrections Issued JOAQUIN GREENOUGH
Footing/Foundation/Slab 7/29/2022 Not Ready for Inspection JOAQUIN GREENOUGH
Underground Mechanical 8/4/2022 Approved ENRIQUE MIRELES
Footing/Foundation/Slab 8/9/2022 Corrections Issued ENRIQUE MIRELES
Gas Test 8/9/2022 Approved ENRIQUE MIRELES
Excavation/Setback/Form/Re-Bar 8/31/2022 Approved ENRIQUE MIRELES
Wood Frame 11/8/2022 Approved ENRIQUE MIRELES
BUILDING-Rough-Frame 12/5/2022 Corrections Issued ENRIQUE MIRELES
ELECTRICAL-Rough 12/5/2022 Not Ready for Inspection ENRIQUE MIRELES
Green Building Rough 12/5/2022 Approved ENRIQUE MIRELES
HVAC-Rough 12/5/2022 Not Ready for Inspection ENRIQUE MIRELES
PLUMBING-Rough 12/5/2022 Not Ready for Inspection ENRIQUE MIRELES
ELECTRICAL-Rough 12/15/2022 Approved ENRIQUE MIRELES
Gas Test 12/15/2022 Approved ENRIQUE MIRELES
PLUMBING-Rough 12/15/2022 Approved ENRIQUE MIRELES
Rough-Elec/Plmb/HVAC 1/3/2023 Approved ENRIQUE MIRELES
Wood Frame 1/3/2023 Approved ENRIQUE MIRELES
Floor/Roof Diaphrgm/Shear Wall 1/6/2023 Approved ENRIQUE MIRELES
Insulation 1/6/2023 Approved ENRIQUE MIRELES
Drywall Nailing 1/13/2023 Approved ENRIQUE MIRELES
Interior/Exterior Lathing 1/13/2023 Not Ready for Inspection ENRIQUE MIRELES
Shower Pan 1/13/2023 Approved ENRIQUE MIRELES
Interior/Exterior Lathing 2/3/2023 Approved ENRIQUE MIRELES
ELECTRICAL-Final 3/22/2023 No Access for Inspection ENRIQUE MIRELES
HVAC-Final 3/22/2023 No Access for Inspection ENRIQUE MIRELES
PLUMBING-Final 3/22/2023 No Access for Inspection ENRIQUE MIRELES
Service/Power Release 3/22/2023 No Access for Inspection ENRIQUE MIRELES
BUILDING-Rough-Frame 6/6/2023 Approved ENRIQUE MIRELES
ELECTRICAL-Final 6/6/2023 Approved ENRIQUE MIRELES
Final 6/6/2023 Corrections Issued ENRIQUE MIRELES
Footing/Foundation/Slab 6/6/2023 Approved ENRIQUE MIRELES
Gas Test 6/6/2023 Approved ENRIQUE MIRELES
Green Building Final 6/6/2023 Approved ENRIQUE MIRELES
HVAC-Final 6/6/2023 Approved ENRIQUE MIRELES
PLUMBING-Final 6/6/2023 Approved ENRIQUE MIRELES
SGSOV-Seismic Gas S/O Valve 6/6/2023 SGSOV Approved ENRIQUE MIRELES
Smoke Detectors 6/6/2023 Approved ENRIQUE MIRELES
ELECTRICAL-Final 7/24/2023 Approved ENRIQUE MIRELES
Final 7/24/2023 Corrections Issued ENRIQUE MIRELES
Gas Test 7/24/2023 Approved ENRIQUE MIRELES
PLUMBING-Final 7/24/2023 Approved ENRIQUE MIRELES
Final 8/11/2023 OK to Issue CofO ENRIQUE MIRELES