3035 1/2 S EDGEHILL DR 90018
Certificate Information: 3035 1/2 S EDGEHILL DR 90018
- Application / Permit
- 21014-10000-03380
- Plan Check / Job No.
- B21LA12496
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- ePlan ADU addition. New Addition to Garage + Conversion of Garage into an Accessory Dwelling Unit
- Permit Issued
- Issued on 1/25/2022
- Issuing Office
- Current Status
- CofO Issued on 6/27/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/5/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 8/12/2021 | ARSALAN SHABESTARI |
| Corrections Issued | 8/14/2021 | ARSALAN SHABESTARI |
| Quality Review Completed | 8/27/2021 | MICHAEL PEREZ |
| Applicant returned to address corrections | 12/14/2021 | ARSALAN SHABESTARI |
| Plan Check Approved | 1/16/2022 | ARSALAN SHABESTARI |
| Issued | 1/25/2022 | APPLICANT |
| CofO in Progress | 6/12/2023 | STUART CHAPMAN |
| Permit Finaled | 6/27/2023 | DEROLD HAUFF |
| CofO Issued | 6/27/2023 | DEROLD HAUFF |
| Permit Finaled | 6/27/2023 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 9/10/2021 | JEANIE LAM |
| Roof/Waste drainage to street | Cleared | 9/10/2021 | JEANIE LAM |
| Eng Process Fee Ord 176,300 | Cleared | 12/29/2021 | JEANIE LAM |
| Sewer availability | Cleared | 12/29/2021 | JEANIE LAM |
Contact Information
| Contractor | Vicrez Construction Co; Lic. No.: 1022661-B | 2805 PRIMERA VISTA BAKERSFIELD, CA 93306 |
Inspector Information
| JUSTIN HAWLEY, (213) 202-3432 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 1/28/2022 | Corrections Issued | STUART CHAPMAN |
| PLUMBING-Rough | 1/28/2022 | Partial Approval | STUART CHAPMAN |
| Footing/Foundation/Slab | 2/4/2022 | Partial Approval | STUART CHAPMAN |
| Excavation/Setback/Form/Re-Bar | 2/22/2022 | Corrections Issued | STUART CHAPMAN |
| Footing/Foundation/Slab | 2/22/2022 | Corrections Issued | STUART CHAPMAN |
| Deputy Drilled-In Anchors | 2/28/2022 | Approved | STUART CHAPMAN |
| Footing/Foundation/Slab | 3/1/2022 | Approved | STUART CHAPMAN |
| ELECTRICAL-Rough | 4/1/2022 | Corrections Issued | LILIANA PORTILLO |
| PLUMBING-Rough | 4/1/2022 | Corrections Issued | LILIANA PORTILLO |
| BUILDING-Rough-Frame | 4/7/2022 | Corrections Issued | STUART CHAPMAN |
| Green Building Rough | 4/7/2022 | Not Ready for Inspection | STUART CHAPMAN |
| BUILDING-Rough-Frame | 4/19/2022 | Approved | STUART CHAPMAN |
| Green Building Rough | 4/19/2022 | Approved | STUART CHAPMAN |
| Interior/Exterior Lathing | 4/19/2022 | Partial Approval | STUART CHAPMAN |
| Insulation | 5/4/2022 | Corrections Issued | STUART CHAPMAN |
| Drywall Nailing | 5/10/2022 | Conditional Approval | STUART CHAPMAN |
| Interior/Exterior Lathing | 5/31/2022 | Corrections Issued | STUART CHAPMAN |
| Sewer | 6/14/2022 | Approved | STUART CHAPMAN |
| Final | 8/4/2022 | Corrections Issued | STUART CHAPMAN |
| Green Building Final | 8/4/2022 | Approved | STUART CHAPMAN |
| SGSOV-Seismic Gas S/O Valve | 8/4/2022 | SGSOV Approved | STUART CHAPMAN |
| Smoke Detectors | 8/4/2022 | Approved | STUART CHAPMAN |
| ELECTRICAL-Final | 8/11/2022 | Approved | STUART CHAPMAN |
| Final | 8/11/2022 | Corrections Issued | STUART CHAPMAN |
| Green Building Final | 8/11/2022 | Approved | STUART CHAPMAN |
| HVAC-Final | 8/11/2022 | Approved | STUART CHAPMAN |
| PLUMBING-Final | 8/11/2022 | Approved | STUART CHAPMAN |
| Final | 5/31/2023 | Not Ready for Inspection | CALEB MEISTER |
| Final | 6/12/2023 | OK to Issue CofO | STUART CHAPMAN |
| Service/Power Release | 6/12/2023 | Approved | STUART CHAPMAN |