4321 N BERENICE AVE 90031
Certificate Information: 4321 N BERENICE AVE 90031
- Application / Permit
- 21014-10000-03350
- Plan Check / Job No.
- B21LA12407
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- E-PLAN: Conversion of existing detached garage to a new ADU per P/BC 2023-150
- Permit Issued
- Issued on 4/30/2024
- Issuing Office
- Current Status
- CofO Issued on 6/11/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/7/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 8/12/2021 | KEVIN MORALES |
| Corrections Issued | 8/19/2021 | MICHAEL LOPEZ |
| Quality Review Completed | 8/20/2021 | PRANITA SHAH |
| Applicant returned to address corrections | 11/11/2021 | MICHAEL LOPEZ |
| Applicant returned to address corrections | 11/12/2021 | MICHAEL LOPEZ |
| Applicant returned to address corrections | 12/16/2021 | MICHAEL LOPEZ |
| Applicant returned to address corrections | 1/28/2022 | MICHAEL LOPEZ |
| Plan Check Approved | 4/26/2024 | KEVIN MORALES |
| Issued | 4/30/2024 | APPLICANT |
| CofO in Progress | 6/8/2026 | OSVALDO PARAMO |
| Permit Finaled | 6/11/2026 | DEROLD HAUFF |
| CofO Issued | 6/11/2026 | DEROLD HAUFF |
| Permit Finaled | 6/11/2026 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 9/24/2021 | NAZILA NOORIFAR |
| Sewer availability | Cleared | 9/24/2021 | NAZILA NOORIFAR |
| CPC | Cleared | 9/28/2021 | KATIE DEBIASE |
| Eng Process Fee Ord 176,300 | Cleared | 9/28/2021 | NAZILA NOORIFAR |
| HPOZ | Cleared | 9/28/2021 | KATIE DEBIASE |
| "D" conditions | Cleared | 10/26/2021 | MIGUEL GAMBOA |
| "Q" conditions | Cleared | 10/26/2021 | MIGUEL GAMBOA |
| ZI | Cleared | 10/26/2021 | MIGUEL GAMBOA |
Contact Information
| Architect | Chavira,, Richard Anthony; Lic. No.: NA12349 | , |
| Contractor | Owner-Builder | , |
| Engineer | Chiu,, Ivan Wai-Kuen; Lic. No.: C44672 | 2160 PARNELL WY ALTADENA, CA 91001 |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 1/24/2025 | Approved | ANTHONY RAMOS |
| Pre-Inspection | 2/7/2025 | Partial Inspection | RUBEN SALAS |
| Footing/Foundation/Slab | 3/28/2025 | Partial Approval | LILIANA PORTILLO |
| Deputy Drilled-In Anchors | 6/16/2025 | Conditional Approval | LILIANA PORTILLO |
| ELECTRICAL-Rough | 6/27/2025 | Not Ready for Inspection | LILIANA PORTILLO |
| Footing/Foundation/Slab | 6/27/2025 | Approved | LILIANA PORTILLO |
| PLUMBING-Rough | 6/27/2025 | Corrections Issued | LILIANA PORTILLO |
| Underground Mechanical | 6/27/2025 | Partial Approval | LILIANA PORTILLO |
| ELECTRICAL-Rough | 9/22/2025 | Corrections Issued | LILIANA PORTILLO |
| PLUMBING-Rough | 9/22/2025 | Partial Approval | LILIANA PORTILLO |
| ELECTRICAL-Rough | 10/14/2025 | Corrections Issued | LILIANA PORTILLO |
| BUILDING-Rough-Frame | 10/22/2025 | Approved | LILIANA PORTILLO |
| ELECTRICAL-Rough | 10/22/2025 | Approved | LILIANA PORTILLO |
| HVAC-Rough | 10/22/2025 | Approved | LILIANA PORTILLO |
| MERV13>=Rough | 10/22/2025 | Approved | LILIANA PORTILLO |
| PLUMBING-Rough | 10/22/2025 | Partial Approval | LILIANA PORTILLO |
| Wood Frame | 10/22/2025 | Conditional Approval | LILIANA PORTILLO |
| Floor/Roof Diaphrgm/Shear Wall | 10/29/2025 | Approved | LILIANA PORTILLO |
| Insulation | 10/29/2025 | Approved | LILIANA PORTILLO |
| Interior/Exterior Lathing | 10/29/2025 | Partial Approval | LILIANA PORTILLO |
| Wood Frame | 10/29/2025 | Approved | LILIANA PORTILLO |
| Drywall Nailing | 10/31/2025 | Approved | REGINA MENDEZ |
| Final | 4/7/2026 | Corrections Issued | LILIANA PORTILLO |
| HVAC-Final | 4/7/2026 | Not Ready for Inspection | LILIANA PORTILLO |
| Sewer | 4/7/2026 | Corrections Issued | LILIANA PORTILLO |
| BUILDING-Rough-Frame | 4/13/2026 | Not Ready for Inspection | LILIANA PORTILLO |
| Final | 4/13/2026 | Not Ready for Inspection | LILIANA PORTILLO |
| Green Building Rough | 4/13/2026 | Approved | LILIANA PORTILLO |
| SGSOV-Seismic Gas S/O Valve | 4/14/2026 | SGSOV Not Ready | LILIANA PORTILLO |
| HVAC-Final | 4/21/2026 | Not Ready for Inspection | ALIZAH MAYAGOITIA |
| PLUMBING-Final | 4/21/2026 | Approved | ALIZAH MAYAGOITIA |
| Sewer | 4/21/2026 | Approved | ALIZAH MAYAGOITIA |
| ELECTRICAL-Final | 5/12/2026 | Corrections Issued | OSVALDO PARAMO |
| ELECTRICAL-Final | 5/15/2026 | Approved | OSVALDO PARAMO |
| BUILDING-Rough-Frame | 5/18/2026 | Approved | RONNIE MEDINA |
| Final | 5/18/2026 | Corrections Issued | RONNIE MEDINA |
| Green Building Final | 5/18/2026 | Approved | RONNIE MEDINA |
| Green Building Rough | 5/18/2026 | Approved | RONNIE MEDINA |
| MERV13>=Final | 5/18/2026 | Approved | RONNIE MEDINA |
| SGSOV-Seismic Gas S/O Valve | 5/18/2026 | SGSOV Approved | RONNIE MEDINA |
| Smoke Detectors | 5/18/2026 | Approved | RONNIE MEDINA |
| Final | 6/3/2026 | OK to Issue CofO | OSVALDO PARAMO |
| Service/Power Release | 6/3/2026 | Approved | OSVALDO PARAMO |