10369 N CALVIN AVE 91326
Certificate Information: 10369 N CALVIN AVE 91326
- Application / Permit
- 21014-10000-03340
- Plan Check / Job No.
- B21LA12368
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- ENCLOSE THE EXISTING OPEN PORCH AT 1ST FLOOR TO EXTEND KITCHEN/DINING ROOM AND ADDITION TO THE REAR PORTION OF AN EXISTING SINGLE FAMILY DWELLING.
- Permit Issued
- Issued on 11/23/2021
- Issuing Office
- Current Status
- CofO Issued on 8/23/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/7/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 7/13/2021 | RAHEL BEYENE |
| Corrections Issued | 7/15/2021 | RAHEL BEYENE |
| Applicant returned to address corrections | 8/19/2021 | RAHEL BEYENE |
| Applicant returned to address corrections | 9/10/2021 | LAWRENCE QUIRANTE |
| Applicant returned to address corrections | 10/15/2021 | GEORGE ALVAREZ |
| Plan Check Approved | 11/10/2021 | GEORGE ALVAREZ |
| Issued | 11/23/2021 | APPLICANT |
| Building Plans Picked Up | 12/3/2021 | APPLICANT |
| CofO in Progress | 8/13/2022 | JEFFREY PARD |
| Permit Finaled | 8/23/2022 | JOHN JANSON |
| CofO Issued | 8/23/2022 | JOHN JANSON |
| Permit Finaled | 8/23/2022 | JOHN JANSON |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 7/22/2021 | CARLOS AGUILERA |
| Roof/Waste drainage to street | Cleared | 7/22/2021 | CARLOS AGUILERA |
| Sewer availability | Cleared | 7/22/2021 | CARLOS AGUILERA |
| Grading Pre-Inspection | Cleared | 8/3/2021 | PATRICK MISCHLICH |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| JACK KARGODORIAN, (818) 774-4319 | Office Hours: 7:00-8:00 AM MON-FRI |
| KRISTEN CAUSEY, (818) 774-4319 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 12/16/2021 | Approved | JEFFREY PARD |
| Footing/Foundation/Slab | 12/16/2021 | Corrections Issued | JEFFREY PARD |
| Floor/Roof Diaphrgm/Shear Wall | 12/27/2021 | Approved | JEFFREY PARD |
| BUILDING-Rough-Frame | 1/12/2022 | Partial Approval | VINCENT HANLEY |
| ELECTRICAL-Rough | 1/12/2022 | Approved | VINCENT HANLEY |
| Green Building Rough | 1/12/2022 | Not Ready for Inspection | VINCENT HANLEY |
| HVAC-Rough | 1/12/2022 | Approved | VINCENT HANLEY |
| PLUMBING-Rough | 1/12/2022 | Approved | VINCENT HANLEY |
| BUILDING-Rough-Frame | 1/21/2022 | Approved | VINCENT HANLEY |
| Green Building Rough | 1/21/2022 | Approved | VINCENT HANLEY |
| Insulation | 1/21/2022 | Approved | VINCENT HANLEY |
| Drywall Nailing | 1/28/2022 | Approved | JEFFREY PARD |
| BUILDING-Rough-Frame | 4/8/2022 | Partial Approval | JEFFREY PARD |
| Final | 4/8/2022 | Not Ready for Inspection | JEFFREY PARD |
| Green Building Final | 4/8/2022 | Not Ready for Inspection | JEFFREY PARD |
| SGSOV-Seismic Gas S/O Valve | 4/8/2022 | SGSOV Not Ready | JEFFREY PARD |
| Smoke Detectors | 4/8/2022 | Not Ready for Inspection | JEFFREY PARD |
| BUILDING-Rough-Frame | 7/29/2022 | Approved | JEFFREY PARD |
| Final | 7/29/2022 | OK to Issue CofO | JEFFREY PARD |
| Footing/Foundation/Slab | 7/29/2022 | Approved | JEFFREY PARD |
| Green Building Final | 7/29/2022 | Approved | JEFFREY PARD |
| SGSOV-Seismic Gas S/O Valve | 7/29/2022 | SGSOV Approved | JEFFREY PARD |