10422-10424 N RESEDA BLVD 91326
Certificate Information: 10422-10424 N RESEDA BLVD 91326
- Application / Permit
- 21014-10000-03334
- Plan Check / Job No.
- B21LA12353
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- GROUND FLOOR & SECOND STORY ADDITION TO AN EXISTING 1-STORY SFD. ADDITION IS AN ADU PER LAMC 12.22 A.33 (c) AND (e).
- Permit Issued
- Issued on 4/29/2024
- Issuing Office
- Metro
- Current Status
- CofO Corrected on 2/10/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 6/30/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 8/5/2021 | KHEDER ALRAZAA |
| Corrections Issued | 8/12/2021 | KHEDER ALRAZAA |
| Quality Review Completed | 8/19/2021 | JASON HEALEY |
| Building Plans Picked Up | 9/7/2021 | APPLICANT |
| Applicant returned to address corrections | 1/24/2022 | KHEDER ALRAZAA |
| Plan Check Approved | 9/1/2022 | KHEDER ALRAZAA |
| Issued | 4/29/2024 | APPLICANT |
| CofO in Progress | 1/28/2026 | DAVID SCANTLIN |
| Re-Activate Permit | 2/10/2026 | JOHN JANSON |
| Permit Finaled-Status Void | 2/10/2026 | JOHN JANSON |
| CofO Issued-Status Void | 2/10/2026 | JOHN JANSON |
| Permit Finaled | 2/10/2026 | JOHN JANSON |
| CofO Corrected | 2/10/2026 | JOHN JANSON |
| Permit Finaled | 2/10/2026 | JOHN JANSON |
Permit Application Clearance Information
| Address approval | Cleared | 9/8/2021 | GABRIEL ROBLES |
| Eng Process Fee Ord 176,300 | Cleared | 4/13/2022 | CARLOS AGUILERA |
| Sewer availability | Cleared | 4/13/2022 | CARLOS AGUILERA |
| Low Impact Development | Cleared | 8/17/2022 | LONDY ALVARADO |
| Roof/Waste drainage to street | Cleared | 8/18/2022 | DAGOVERTO GUERRERO |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| JACK KARGODORIAN, (818) 774-4319 | Office Hours: 7:00-8:00 AM MON-FRI |
| KRISTEN CAUSEY, (818) 774-4319 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 5/1/2024 | Corrections Issued | DAVID SCANTLIN |
| PLUMBING-Rough | 5/1/2024 | Partial Approval | DAVID SCANTLIN |
| Excavation/Setback/Form/Re-Bar | 6/5/2024 | Corrections Issued | DAVID SCANTLIN |
| Footing/Foundation/Slab | 6/5/2024 | Not Ready for Inspection | DAVID SCANTLIN |
| Footing/Foundation/Slab | 7/11/2024 | Approved | KRISTEN CAUSEY |
| Deputy Wood Construction | 11/14/2024 | Conditional Approval | DAVID SCANTLIN |
| BUILDING-Rough-Frame | 11/15/2024 | Corrections Issued | DAVID SCANTLIN |
| Floor/Roof Diaphrgm/Shear Wall | 11/15/2024 | Partial Approval | DAVID SCANTLIN |
| Floor/Roof Diaphrgm/Shear Wall | 12/5/2024 | Corrections Issued | KRISTEN CAUSEY |
| Floor/Roof Diaphrgm/Shear Wall | 12/13/2024 | Partial Approval | DAVID SCANTLIN |
| BUILDING-Rough-Frame | 2/27/2025 | Corrections Issued | DAVID SCANTLIN |
| ELECTRICAL-Rough | 2/27/2025 | Approved | DAVID SCANTLIN |
| HVAC-Rough | 2/27/2025 | Approved | DAVID SCANTLIN |
| Interior/Exterior Lathing | 2/27/2025 | Partial Approval | DAVID SCANTLIN |
| PLUMBING-Rough | 2/27/2025 | Approved | DAVID SCANTLIN |
| Shower Pan | 2/27/2025 | Not Ready for Inspection | DAVID SCANTLIN |
| Insulation | 3/11/2025 | Not Ready for Inspection | DAVID SCANTLIN |
| BUILDING-Rough-Frame | 5/19/2025 | Approved | DAVID SCANTLIN |
| Drywall Nailing | 5/19/2025 | Approved | DAVID SCANTLIN |
| Green Building Rough | 5/19/2025 | Approved | DAVID SCANTLIN |
| Insulation | 5/19/2025 | Approved | DAVID SCANTLIN |
| Service/Power Release | 7/24/2025 | Not Ready for Inspection | DAVID SCANTLIN |
| Final | 1/6/2026 | Corrections Issued | DAVID SCANTLIN |
| Green Building Final | 1/6/2026 | Not Ready for Inspection | DAVID SCANTLIN |
| SGSOV-Seismic Gas S/O Valve | 1/6/2026 | SGSOV Approved | DAVID SCANTLIN |
| Smoke Detectors | 1/6/2026 | Approved | DAVID SCANTLIN |
| Final | 1/27/2026 | OK to Issue CofO | DAVID SCANTLIN |
| Green Building Final | 1/27/2026 | Approved | DAVID SCANTLIN |
| Service/Power Release | 1/27/2026 | Approved | DAVID SCANTLIN |
| Deputy Reinf. Concrete | 2/3/2026 | Approved | DAVID SCANTLIN |
| Special/Order Compliance | 2/3/2026 | Corrections Issued | DAVID SCANTLIN |