2287 N MORENO DR 90039

Certificate Information: 2287 N MORENO DR 90039

Application / Permit
21014-10000-03296
Plan Check / Job No.
B21LA12215
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW ADU ADDITION ABOVE EXISTING DETACHED GARAGE TO CREATE DETACHED ADU PER ORDINANCE (2-STORY)
Permit Issued
Issued on 1/12/2022
Issuing Office
Current Status
CofO Issued on 10/29/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/29/2021 APPLICANT
Assigned to Plan Check Engineer 7/22/2021 CARLOS MONTES
Corrections Issued 7/24/2021 CARLOS MONTES
Quality Review Completed 8/3/2021 WING SUEN
Building Plans Picked Up 8/5/2021 APPLICANT
Applicant returned to address corrections 9/8/2021 CARLOS MONTES
Plan Check Approved 1/12/2022 CARLOS MONTES
Issued 1/12/2022 APPLICANT
CofO in Progress 10/6/2022 JOSEPH MCGARRY
Permit Finaled 10/29/2022 DEROLD HAUFF
CofO Issued 10/29/2022 DEROLD HAUFF
Permit Finaled 10/29/2022 DEROLD HAUFF

Permit Application Clearance Information

Grading Pre-Inspection Cleared 7/26/2021 CARLOS MONTES
BHO/Hillside ordinance Cleared 8/27/2021 RENZ SORIANO
BHO/Hillside ordinance Cleared 8/27/2021 RENZ SORIANO
Eng Process Fee Ord 176,300 Cleared 9/2/2021 RENZ SORIANO
Address approval Cleared 9/8/2021 WALLIE JONG
Roof/Waste drainage to street Cleared 9/8/2021 WALLIE JONG
Sewer availability Cleared 9/9/2021 WALLIE JONG
Hydrant and Access approval Cleared 1/4/2022 RUEL COLE

Contact Information

Contractor After Collaborative Inc; Lic. No.: 1077530-B 4365 CLAYTON AVENUE      LOS ANGELES, CA 90631
Engineer Niaki,, Neman; Lic. No.: C46030 1107 CALIFORNIA AVE #2      SANTA MONICA, CA 90403

Inspector Information

ENRIQUE MIRELES, (213) 202-3438 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Wood Frame 1/24/2022 Corrections Issued CRAIG DAVIS
Wood Frame 1/24/2022 Corrections Issued SHAVONNE ESPINOZA
Excavation/Setback/Form/Re-Bar 1/25/2022 Approved JOSEPH MCGARRY
Underground Mechanical 1/25/2022 Partial Approval JOSEPH MCGARRY
ELECTRICAL-Rough 4/12/2022 Corrections Issued CRAIG DAVIS
Gas Test 4/12/2022 Corrections Issued CRAIG DAVIS
HVAC-Rough 4/12/2022 Corrections Issued CRAIG DAVIS
PLUMBING-Rough 4/12/2022 Corrections Issued CRAIG DAVIS
Sewer 4/12/2022 Corrections Issued CRAIG DAVIS
Wood Frame 4/12/2022 Corrections Issued CRAIG DAVIS
BUILDING-Rough-Frame 4/29/2022 Partial Approval JOSEPH MCGARRY
ELECTRICAL-Rough 4/29/2022 Partial Approval JOSEPH MCGARRY
Floor/Roof Diaphrgm/Shear Wall 4/29/2022 Partial Approval JOSEPH MCGARRY
Green Building Rough 4/29/2022 Approved JOSEPH MCGARRY
HVAC-Rough 4/29/2022 Partial Approval JOSEPH MCGARRY
PLUMBING-Rough 4/29/2022 Approved JOSEPH MCGARRY
Sewer 4/29/2022 Approved JOSEPH MCGARRY
Wood Frame 4/29/2022 Partial Approval JOSEPH MCGARRY
Insulation 5/10/2022 Corrections Issued JOSEPH MCGARRY
Insulation 5/20/2022 Partial Approval JOSEPH MCGARRY
BUILDING-Rough-Frame 6/7/2022 Conditional Approval JOSEPH MCGARRY
ELECTRICAL-Rough 6/7/2022 Approved JOSEPH MCGARRY
HVAC-Rough 6/7/2022 Approved JOSEPH MCGARRY
BUILDING-Rough-Frame 7/11/2022 Conditional Approval JOSEPH MCGARRY
Drywall Nailing 7/11/2022 Approved JOSEPH MCGARRY
Interior/Exterior Lathing 7/11/2022 Partial Approval JOSEPH MCGARRY
Shower Pan 7/11/2022 Approved JOSEPH MCGARRY
Interior/Exterior Lathing 7/29/2022 Approved JOSEPH MCGARRY
Special/Order Compliance 7/29/2022 Corrections Issued JOSEPH MCGARRY
Pre-Inspection 9/27/2022 Approved JOSEPH MCGARRY
BUILDING-Rough-Frame 10/5/2022 Approved JOSEPH MCGARRY
Final 10/5/2022 OK to Issue CofO JOSEPH MCGARRY
Footing/Foundation/Slab 10/5/2022 Approved JOSEPH MCGARRY
Green Building Final 10/5/2022 Approved JOSEPH MCGARRY
SGSOV-Seismic Gas S/O Valve 10/5/2022 SGSOV Approved JOSEPH MCGARRY
Smoke Detectors 10/5/2022 Approved JOSEPH MCGARRY