10339 N MT GLEASON AVE 91040

Certificate Information: 10339 N MT GLEASON AVE 91040

Application / Permit
21014-10000-03287
Plan Check / Job No.
B21LA12133
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
ADDITION OF BEDROOM AND EXTENSION TO LIVING ROOM TO EXISTING 1 STORY SINGLE FAMILY DWELLING PER ENGINEER DESIGN
Permit Issued
Issued on 9/20/2021
Issuing Office
Current Status
CofO Issued on 6/20/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/30/2021 APPLICANT
Assigned to Plan Check Engineer 7/8/2021 AUNG SOE
Plan Check Approved 8/17/2021 AUNG SOE
Building Plans Picked Up 8/18/2021 APPLICANT
Issued 9/20/2021 APPLICANT
CofO in Progress 6/15/2022 MATTHEW NELSON
Permit Finaled 6/20/2022 DANIEL ORRANTE
CofO Issued 6/20/2022 DANIEL ORRANTE
Permit Finaled 6/20/2022 DANIEL ORRANTE

Permit Application Clearance Information

Specific Plan Cleared 7/14/2021 KORA MCNAUGHTON
Eng Process Fee Ord 176,300 Cleared 7/15/2021 GABRIEL ROBLES
Roof/Waste drainage to street Cleared 7/15/2021 GABRIEL ROBLES
Sewer availability Cleared 7/15/2021 GABRIEL ROBLES
Grading Pre-Inspection Cleared 7/22/2021 BRIAN MILLER
GPI Written Notices Cleared 8/15/2021 AUNG SOE

Contact Information

Contractor Owner-Builder       ,
Engineer Melchor,, Oscar Elias; Lic. No.: C76828 21243 VENTURA BLVD SUITE 119      WOODLAND HILLS, CA 91364

Inspector Information

MATTHEW NELSON, (818) 374-1168 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 11/9/2021 Approved WILLIAM KUEHN
Pre-Inspection 11/9/2021 Not Ready for Inspection WILLIAM KUEHN
Floor/Roof Diaphrgm/Shear Wall 11/19/2021 Partial Inspection WILLIAM KUEHN
Green Building Rough 11/19/2021 Not Ready for Inspection WILLIAM KUEHN
Floor/Roof Diaphrgm/Shear Wall 12/6/2021 Partial Inspection WILLIAM KUEHN
Green Building Rough 12/6/2021 Not Ready for Inspection WILLIAM KUEHN
BUILDING-Rough-Frame 12/16/2021 Approved WILLIAM KUEHN
ELECTRICAL-Rough 12/16/2021 Approved WILLIAM KUEHN
Green Building Rough 12/16/2021 Approved WILLIAM KUEHN
Interior/Exterior Lathing 12/16/2021 Partial Inspection WILLIAM KUEHN
Drywall Nailing 12/23/2021 Approved WILLIAM KUEHN
Insulation 12/23/2021 Approved WILLIAM KUEHN
ELECTRICAL-Final 6/14/2022 Approved MATTHEW NELSON
Final 6/14/2022 OK to Issue CofO MATTHEW NELSON
Footing/Foundation/Slab 6/14/2022 Approved MATTHEW NELSON
Green Building Final 6/14/2022 Approved MATTHEW NELSON
HVAC-Final 6/14/2022 Approved MATTHEW NELSON
PLUMBING-Final 6/14/2022 Approved MATTHEW NELSON
SGSOV-Seismic Gas S/O Valve 6/14/2022 SGSOV Approved MATTHEW NELSON
Smoke Detectors 6/14/2022 Approved MATTHEW NELSON