6213 E BURWOOD AVE 90042

Certificate Information: 6213 E BURWOOD AVE 90042

Application / Permit
21014-10000-03284
Plan Check / Job No.
B21LA12123
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
ADDITION (553 SQ FT) TO EXISTING ONE STORY SFD, ENLARGE KITCHEN AND CREATE A NEW MASTER SUITE.
Permit Issued
Issued on 10/14/2022
Issuing Office
Metro
Current Status
CofO Issued on 4/9/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/28/2021 APPLICANT
Assigned to Plan Check Engineer 7/8/2021 TSE MING HUANG
Corrections Issued 7/8/2021 TSE MING HUANG
Applicant returned to address corrections 1/24/2022 RAHEL BEYENE
Building Plans Picked Up 1/26/2022 APPLICANT
Applicant returned to address corrections 8/22/2022 LAWRENCE QUIRANTE
Applicant returned to address corrections 9/2/2022 FERNANDO FLORES
Plan Check Approved 9/29/2022 JOSEPH RAFOLS
Issued 10/14/2022 APPLICANT
CofO in Progress 4/4/2024 ALIZAH MAYAGOITIA
Permit Finaled 4/9/2024 DEROLD HAUFF
CofO Issued 4/9/2024 DEROLD HAUFF
Permit Finaled 4/9/2024 DEROLD HAUFF

Permit Application Clearance Information

Sewer availability Cleared 8/5/2021 WALLIE JONG
Eng Process Fee Ord 176,300 Cleared 8/9/2021 WALLIE JONG
Low Impact Development Cleared 1/4/2022 SAHIL SHARMA
Grading Pre-Inspection Cleared 1/24/2022 TSE MING HUANG
Roof/Waste drainage to street Cleared 3/9/2022 WALLIE JONG
BHO/Hillside ordinance Cleared 9/24/2022 JEANETTE VONG
BHO/Hillside ordinance Cleared 9/24/2022 JEANETTE VONG
BHO/Hillside ordinance Cleared 9/24/2022 JEANETTE VONG
BHO/Hillside ordinance Cleared 9/24/2022 JEANETTE VONG

Contact Information

Contractor Owner-Builder       ,
Engineer Castillo,, Margarito; Lic. No.: S4808 1205 PINE AVENUE      LONG BEACH, CA 90813
Engineer Price,, Mark Erin; Lic. No.: L7764 18700 WELLHAVEN STREET      CANYON COUNTRY, CA 91351

Inspector Information

No Data Available.

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 2/2/2023 Corrections Issued AMY COLIN
Footing/Foundation/Slab 2/9/2023 Approved ALIZAH MAYAGOITIA
BUILDING-Rough-Frame 2/21/2023 Partial Approval AMY COLIN
Green Building Rough 2/21/2023 Not Ready for Inspection AMY COLIN
PLUMBING-Rough 2/21/2023 Partial Approval AMY COLIN
Floor/Roof Diaphrgm/Shear Wall 3/8/2023 Partial Approval AMY COLIN
Insulation 3/8/2023 Partial Approval AMY COLIN
BUILDING-Rough-Frame 4/7/2023 Partial Approval AMY COLIN
Green Building Rough 4/7/2023 Not Ready for Inspection AMY COLIN
ELECTRICAL-Rough 5/22/2023 Corrections Issued AMY COLIN
HVAC-Rough 5/22/2023 Partial Approval AMY COLIN
PLUMBING-Rough 5/22/2023 Corrections Issued AMY COLIN
Gas Test 6/7/2023 Partial Approval AMY COLIN
Insulation 6/7/2023 Approved AMY COLIN
Interior/Exterior Lathing 6/7/2023 Partial Approval AMY COLIN
Rough-Elec/Plmb/HVAC 6/7/2023 Approved AMY COLIN
Drywall Nailing 6/13/2023 Approved AMY COLIN
Gas Test 6/13/2023 Approved AMY COLIN
Green Building Rough 6/13/2023 Approved AMY COLIN
BUILDING-Rough-Frame 2/29/2024 Approved ALIZAH MAYAGOITIA
Final 2/29/2024 Corrections Issued ALIZAH MAYAGOITIA
Green Building Final 2/29/2024 Approved ALIZAH MAYAGOITIA
SGSOV-Seismic Gas S/O Valve 2/29/2024 SGSOV Not Ready ALIZAH MAYAGOITIA
Smoke Detectors 2/29/2024 Approved ALIZAH MAYAGOITIA
SGSOV-Seismic Gas S/O Valve 3/5/2024 SGSOV Approved ALIZAH MAYAGOITIA
Final 4/3/2024 OK to Issue CofO ALIZAH MAYAGOITIA