1408 N ANGELUS AVE 90026

Certificate Information: 1408 N ANGELUS AVE 90026

Application / Permit
21014-10000-03275
Plan Check / Job No.
B21LA12088
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
REMODEL OF (E) SINGLE FAMILY DWELLING, CHANGE EXISTING BASEMENT LEVEL FROM STORAGE TO HABITABLE SPACE
Permit Issued
Issued on 11/20/2021
Issuing Office
Current Status
CofO Issued on 8/13/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/28/2021 APPLICANT
Assigned to Plan Check Engineer 8/5/2021 LAMAR DAVIS
Corrections Issued 8/18/2021 LAMAR DAVIS
Quality Review Completed 8/24/2021 WING SUEN
Plan Check Approved 10/15/2021 LAMAR DAVIS
Issued 11/20/2021 APPLICANT
Building Plans Picked Up 12/10/2021 APPLICANT
CofO in Progress 8/7/2023 THOMAS LOGRASSO
Permit Finaled 8/13/2023 DEROLD HAUFF
CofO Issued 8/13/2023 DEROLD HAUFF
Permit Finaled 8/13/2023 DEROLD HAUFF

Permit Application Clearance Information

ZA Case Cleared 9/16/2021 KENTON TRINH
Sewer availability Cleared 9/18/2021 CECILIO NAVARRO
Eng Process Fee Ord 176,300 Cleared 9/20/2021 CECILIO NAVARRO
Tenant Habitability Plan Cleared 9/21/2021 PHILLIP MUNGUIA

Contact Information

Architect Unruh,, Antony M; Lic. No.: C26012 2311 HYPERION AVENUE      LOS ANGELES, CA 90027
Contractor Owner-Builder       ,

Inspector Information

HAMIK HARTOUNIAN, (213) 202-3275 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 2/7/2022 Partial Approval THOMAS LOGRASSO
ELECTRICAL-Rough 3/24/2022 Corrections Issued THOMAS LOGRASSO
HVAC-Rough 3/24/2022 Corrections Issued THOMAS LOGRASSO
PLUMBING-Rough 3/24/2022 Partial Approval THOMAS LOGRASSO
ELECTRICAL-Rough 5/5/2022 Approved RUBEN SALAS
Gas Test 5/5/2022 Approved RUBEN SALAS
HVAC-Rough 5/5/2022 Approved RUBEN SALAS
PLUMBING-Rough 5/5/2022 Approved RUBEN SALAS
Special/Order Compliance 5/5/2022 Corrections Issued RUBEN SALAS
Insulation 5/12/2022 Approved AMY COLIN
Drywall Nailing 5/31/2022 Corrections Issued THOMAS LOGRASSO
Interior/Exterior Lathing 5/31/2022 Approved THOMAS LOGRASSO
BUILDING-Rough-Frame 2/15/2023 Approved THOMAS LOGRASSO
Drywall Nailing 2/15/2023 Approved THOMAS LOGRASSO
Final 2/15/2023 Corrections Issued THOMAS LOGRASSO
Footing/Foundation/Slab 2/15/2023 Approved THOMAS LOGRASSO
Green Building Final 2/15/2023 Not Ready for Inspection THOMAS LOGRASSO
Green Building Rough 2/15/2023 Approved THOMAS LOGRASSO
SGSOV-Seismic Gas S/O Valve 2/15/2023 SGSOV Approved THOMAS LOGRASSO
Smoke Detectors 2/15/2023 Approved THOMAS LOGRASSO
ELECTRICAL-Final 8/4/2023 Approved THOMAS LOGRASSO
Final 8/4/2023 OK to Issue CofO THOMAS LOGRASSO
Green Building Final 8/4/2023 Approved THOMAS LOGRASSO
HVAC-Final 8/4/2023 Approved THOMAS LOGRASSO
PLUMBING-Final 8/4/2023 Approved THOMAS LOGRASSO