Pre-Inspection
|
5/7/2024
|
Partial Inspection
|
ARAM AVEDISIAN
|
|
Pre-Inspection
|
6/28/2024
|
Partial Inspection
|
ARAM AVEDISIAN
|
|
Deputy Drilled-In Anchors
|
9/6/2024
|
Conditional Approval
|
JESUS RODRIGUEZ
|
|
Footing/Foundation/Slab
|
9/20/2024
|
Partial Approval
|
JESUS RODRIGUEZ
|
|
Deputy Reinf. Concrete
|
9/23/2024
|
Conditional Approval
|
JESUS RODRIGUEZ
|
|
Footing/Foundation/Slab
|
9/27/2024
|
Not Ready for Inspection
|
CARLOS MATAMOROS
|
|
Excavation/Setback/Form/Re-Bar
|
10/1/2024
|
Corrections Issued
|
JESUS RODRIGUEZ
|
|
Excavation/Setback/Form/Re-Bar
|
10/21/2024
|
Partial Approval
|
JESUS RODRIGUEZ
|
|
Excavation/Setback/Form/Re-Bar
|
11/1/2024
|
Partial Approval
|
JESUS RODRIGUEZ
|
|
Footing/Foundation/Slab
|
11/1/2024
|
Partial Approval
|
JESUS RODRIGUEZ
|
|
Deputy Reinf. Concrete
|
11/8/2024
|
Conditional Approval
|
JESUS RODRIGUEZ
|
|
HVAC-Rough
|
12/19/2024
|
Partial Approval
|
JESUS RODRIGUEZ
|
|
Underground Mechanical
|
12/19/2024
|
Partial Approval
|
JESUS RODRIGUEZ
|
|
Insulation
|
2/26/2025
|
Approved
|
JESUS RODRIGUEZ
|
|
Excavation/Setback/Form/Re-Bar
|
4/1/2025
|
Not Ready for Inspection
|
HERBERT GIRON
|
|
Deputy Drilled-In Anchors
|
4/3/2025
|
Conditional Approval
|
HERBERT GIRON
|
|
Floor/Roof Diaphrgm/Shear Wall
|
4/3/2025
|
Partial Approval
|
HERBERT GIRON
|
|
Footing/Foundation/Slab
|
4/17/2025
|
Corrections Issued
|
HERBERT GIRON
|
|
Footing/Foundation/Slab
|
4/21/2025
|
Partial Approval
|
KEVIN SARGSYAN
|
|
Deputy Reinf. Concrete
|
4/22/2025
|
Conditional Approval
|
HERBERT GIRON
|
|
PLUMBING-Rough
|
4/30/2025
|
Corrections Issued
|
HERBERT GIRON
|
|
Footing/Foundation/Slab
|
5/6/2025
|
Not Ready for Inspection
|
HERBERT GIRON
|
|
Reinforced Concrete Frame
|
5/6/2025
|
Not Ready for Inspection
|
HERBERT GIRON
|
|
Reinforced Concrete Frame
|
5/23/2025
|
Partial Approval
|
ARAM AVEDISIAN
|
|
Reinforced Concrete Frame
|
6/2/2025
|
Partial Approval
|
HERBERT GIRON
|
|
Footing/Foundation/Slab
|
6/13/2025
|
Partial Approval
|
HERBERT GIRON
|
|
Floor/Roof Diaphrgm/Shear Wall
|
7/15/2025
|
Approved
|
HERBERT GIRON
|
|
Footing/Foundation/Slab
|
7/23/2025
|
Approved
|
HERBERT GIRON
|
|
PLUMBING-Rough
|
7/23/2025
|
Partial Approval
|
HERBERT GIRON
|
|
Floor/Roof Diaphrgm/Shear Wall
|
8/29/2025
|
Partial Approval
|
HERBERT GIRON
|
|
Special/Order Compliance
|
10/28/2025
|
Corrections Issued
|
HERBERT GIRON
|
|
Wood Frame
|
10/28/2025
|
Partial Approval
|
HERBERT GIRON
|
|
Floor/Roof Diaphrgm/Shear Wall
|
10/31/2025
|
Conditional Approval
|
HERBERT GIRON
|
|
Deputy Drilled-In Anchors
|
11/7/2025
|
Conditional Approval
|
HERBERT GIRON
|
|
Reinforced Concrete Frame
|
11/12/2025
|
Approved
|
HERBERT GIRON
|
|
Deputy Reinf. Concrete
|
11/13/2025
|
Approved
|
HERBERT GIRON
|
|
Deputy Wood Construction
|
12/18/2025
|
Conditional Approval
|
HERBERT GIRON
|
|
Floor/Roof Diaphrgm/Shear Wall
|
12/22/2025
|
Partial Approval
|
KEVIN SARGSYAN
|
|
ELECTRICAL-Rough
|
12/23/2025
|
Partial Inspection
|
KEVIN SARGSYAN
|
|
PLUMBING-Rough
|
1/15/2026
|
Partial Approval
|
HERBERT GIRON
|
|
Deputy Drilled-In Anchors
|
1/28/2026
|
Conditional Approval
|
JUAN VALENZUELA
|
|
Footing/Foundation/Slab
|
1/30/2026
|
Approved
|
KEVIN SARGSYAN
|
|
ELECTRICAL-Rough
|
3/2/2026
|
Corrections Issued
|
HERBERT GIRON
|
|
Interior/Exterior Lathing
|
3/3/2026
|
Corrections Issued
|
HERBERT GIRON
|
|
ELECTRICAL-Rough
|
3/4/2026
|
Not Ready for Inspection
|
HERBERT GIRON
|
|
HVAC-Rough
|
3/4/2026
|
Not Ready for Inspection
|
HERBERT GIRON
|
|
PLUMBING-Rough
|
3/5/2026
|
Partial Approval
|
HERBERT GIRON
|
|
ELECTRICAL-Rough
|
3/6/2026
|
Approved
|
HERBERT GIRON
|
|
Shower Pan
|
3/6/2026
|
Approved
|
HERBERT GIRON
|
|
HVAC-Rough
|
3/11/2026
|
Corrections Issued
|
HERBERT GIRON
|
|
ELECTRICAL-Rough
|
3/18/2026
|
Approved
|
HERBERT GIRON
|
|
HVAC-Rough
|
3/18/2026
|
Approved
|
HERBERT GIRON
|
|
PLUMBING-Rough
|
3/18/2026
|
Approved
|
HERBERT GIRON
|
|
Floor/Roof Diaphrgm/Shear Wall
|
3/24/2026
|
Corrections Issued
|
HERBERT GIRON
|
|
Interior/Exterior Lathing
|
3/24/2026
|
Partial Approval
|
HERBERT GIRON
|
|
Floor/Roof Diaphrgm/Shear Wall
|
3/25/2026
|
Partial Approval
|
HERBERT GIRON
|
|
Floor/Roof Diaphrgm/Shear Wall
|
4/1/2026
|
Corrections Issued
|
HERBERT GIRON
|
|
Interior/Exterior Lathing
|
4/1/2026
|
Partial Approval
|
HERBERT GIRON
|
|
BUILDING-Rough-Frame
|
4/7/2026
|
Approved
|
HERBERT GIRON
|
|
Floor/Roof Diaphrgm/Shear Wall
|
4/7/2026
|
Approved
|
HERBERT GIRON
|
|
Green Building Rough
|
4/7/2026
|
Approved
|
HERBERT GIRON
|
|
Insulation
|
4/13/2026
|
Corrections Issued
|
KEVIN SARGSYAN
|
|
Insulation
|
4/17/2026
|
Approved
|
KEVIN SARGSYAN
|
|
Drywall Nailing
|
4/27/2026
|
Approved
|
DANIEL VERA
|
|
Final
|
4/27/2026
|
Corrections Issued
|
DANIEL VERA
|
|
Drywall Nailing
|
4/29/2026
|
Partial Inspection
|
HERBERT GIRON
|