5650 W BRUSHTON ST 90008
Certificate Information: 5650 W BRUSHTON ST 90008
- Application / Permit
- 21014-10000-03211
- Plan Check / Job No.
- B21LA11818
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- PROPOSED ADDITION'S TO EXISTING SFD/GARAGE, ADDITION TO CREATE NEW ENTRY, OFFICE, FAMILY ROOM, AND LAUNDRY ROOM. SCOPE WILL ALSO INCLUDE COMPLETE INTERIOR REMODEL, KITCHEN/BATHROOM REMODEL.
- Permit Issued
- Issued on 5/16/2022
- Issuing Office
- Current Status
- CofO Issued on 7/23/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 6/29/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 8/5/2021 | MICHAEL LOPEZ |
| Corrections Issued | 8/12/2021 | MICHAEL LOPEZ |
| Quality Review Completed | 8/18/2021 | KEN GILL |
| Applicant returned to address corrections | 11/18/2021 | MICHAEL LOPEZ |
| Plan Check Approved | 11/18/2021 | MICHAEL LOPEZ |
| Issued | 5/16/2022 | APPLICANT |
| CofO in Progress | 7/18/2023 | ANTHONY EGSON |
| Permit Finaled | 7/23/2023 | DEROLD HAUFF |
| Permit Finaled | 7/23/2023 | DEROLD HAUFF |
| CofO Issued | 7/23/2023 | DEROLD HAUFF |
Permit Application Clearance Information
| Grading Pre-Inspection | Cleared | 9/27/2021 | ROBERT HUGHES |
| Roof/Waste drainage to street | Cleared | 10/1/2021 | JEANIE LAM |
| Eng Process Fee Ord 176,300 | Cleared | 10/5/2021 | JEANIE LAM |
Contact Information
| Contractor | Castillo'S Building Inc; Lic. No.: 1027270-B | 28441 HIGHRIDGE RD STE 420 ROLLING HILLS ESTATES, CA 90274 |
| Engineer | Garcia,, Ricardo Ray; Lic. No.: C66957 | 27702 QUINCY ST CASTAIC, CA 91384 |
Inspector Information
| LUIS CASTRO, (213) 202-3436 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 7/29/2022 | Approved | ANTHONY EGSON |
| Excavation/Setback/Form/Re-Bar | 8/8/2022 | Approved | ANTHONY EGSON |
| Footing/Foundation/Slab | 8/8/2022 | Approved | ANTHONY EGSON |
| METHANE-Barrier | 8/8/2022 | Approved | ANTHONY EGSON |
| METHANE-Subgrade | 8/8/2022 | Approved | ANTHONY EGSON |
| BUILDING-Rough-Frame | 8/18/2022 | Partial Inspection | ANTHONY EGSON |
| Green Building Rough | 8/18/2022 | Not Ready for Inspection | ANTHONY EGSON |
| METHANE-Rough | 8/18/2022 | Approved | ANTHONY EGSON |
| Floor/Roof Diaphrgm/Shear Wall | 8/19/2022 | Approved | ANTHONY EGSON |
| Floor/Roof Diaphrgm/Shear Wall | 8/25/2022 | Not Ready for Inspection | ANTHONY EGSON |
| Insulation | 8/25/2022 | Partial Approval | ANTHONY EGSON |
| Floor/Roof Diaphrgm/Shear Wall | 8/26/2022 | Partial Approval | ANTHONY EGSON |
| ELECTRICAL-Rough | 11/21/2022 | Approved | ANTHONY EGSON |
| HVAC-Rough | 11/21/2022 | Approved | ANTHONY EGSON |
| PLUMBING-Rough | 11/21/2022 | Approved | ANTHONY EGSON |
| BUILDING-Rough-Frame | 11/29/2022 | No Access for Inspection | ANTHONY EGSON |
| Green Building Rough | 11/29/2022 | No Access for Inspection | ANTHONY EGSON |
| BUILDING-Rough-Frame | 12/2/2022 | Approved | ANTHONY EGSON |
| Floor/Roof Diaphrgm/Shear Wall | 12/2/2022 | Approved | ANTHONY EGSON |
| Green Building Rough | 12/2/2022 | Approved | ANTHONY EGSON |
| Interior/Exterior Lathing | 12/21/2022 | Not Ready for Inspection | ANTHONY EGSON |
| Shower Pan | 12/21/2022 | Approved | ANTHONY EGSON |
| Interior/Exterior Lathing | 12/27/2022 | Approved | ANTHONY EGSON |
| Insulation | 1/3/2023 | Approved | ANTHONY EGSON |
| Interior/Exterior Lathing | 1/6/2023 | Corrections Issued | ANTHONY EGSON |
| Drywall Nailing | 1/9/2023 | Approved | ANTHONY EGSON |
| Interior/Exterior Lathing | 1/9/2023 | Approved | ANTHONY EGSON |
| Pre-Inspection | 1/18/2023 | Partial Inspection | ANTHONY EGSON |
| HVAC-Rough | 2/27/2023 | Approved | ANTHONY EGSON |
| Gas Test | 3/28/2023 | Approved | ANTHONY EGSON |
| Final | 4/28/2023 | Corrections Issued | ANTHONY EGSON |
| Green Building Final | 4/28/2023 | Corrections Issued | ANTHONY EGSON |
| SGSOV-Seismic Gas S/O Valve | 4/28/2023 | SGSOV Approved | ANTHONY EGSON |
| Smoke Detectors | 4/28/2023 | Approved | ANTHONY EGSON |
| ELECTRICAL-Final | 5/10/2023 | Approved | ANTHONY EGSON |
| Final | 5/10/2023 | Corrections Issued | ANTHONY EGSON |
| Green Building Final | 5/10/2023 | Corrections Issued | ANTHONY EGSON |
| HVAC-Final | 5/10/2023 | Approved | ANTHONY EGSON |
| PLUMBING-Final | 5/10/2023 | Approved | ANTHONY EGSON |
| Service/Power Release | 5/10/2023 | Not Ready for Inspection | ANTHONY EGSON |
| Final | 6/28/2023 | Partial Approval | ANTHONY EGSON |
| Green Building Final | 6/28/2023 | Approved | ANTHONY EGSON |
| Service/Power Release | 6/28/2023 | Approved | ANTHONY EGSON |
| Final | 7/18/2023 | OK to Issue CofO | ANTHONY EGSON |