1235 1/2 N MARINE AVE 90744
Certificate Information: 1235 1/2 N MARINE AVE 90744
- Application / Permit
- 21014-10000-03203
- Plan Check / Job No.
- B21LA11801
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (2) Duplex
- Work Description
- ePlan ADU conversion. Converting existing 484 sq. ft. garage into Attached ADU per GCS 65852.2(e)(1)(A). All work per WFPP
- Permit Issued
- Issued on 3/1/2022
- Issuing Office
- Current Status
- CofO Issued on 8/20/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 6/24/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 6/28/2021 | DANIEL YIP |
| Corrections Issued | 6/28/2021 | ZAW HAN |
| Applicant returned to address corrections | 8/19/2021 | ZAW HAN |
| Applicant returned to address corrections | 12/17/2021 | DANIEL YIP |
| Plan Check Approved | 2/8/2022 | DANIEL YIP |
| Issued | 3/1/2022 | APPLICANT |
| CofO in Progress | 8/9/2022 | EUGENE CASSIDY |
| Permit Finaled | 8/20/2022 | DEROLD HAUFF |
| Permit Finaled | 8/20/2022 | DEROLD HAUFF |
| CofO Issued | 8/20/2022 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 7/29/2021 | CHINH DINH |
| Eng Process Fee Ord 176,300 | Cleared | 7/29/2021 | CHINH DINH |
| Roof/Waste drainage to street | Cleared | 7/29/2021 | CHINH DINH |
| Sewer availability | Cleared | 7/29/2021 | CHINH DINH |
| Tenant Habitability Plan | Cleared | 12/14/2021 | RICHARD BRINSON |
| Clean Up Green Up | Cleared | 1/5/2022 | LOUIS ORTEGA |
| ZA Case | Cleared | 1/5/2022 | LOUIS ORTEGA |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| EUGENE CASSIDY, (310) 548-2508 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 5/5/2022 | Partial Approval | EUGENE CASSIDY |
| Pre-Inspection | 5/5/2022 | Approved | EUGENE CASSIDY |
| Footing/Foundation/Slab | 5/11/2022 | Partial Approval | EUGENE CASSIDY |
| ELECTRICAL-Rough | 5/17/2022 | Approved | EUGENE CASSIDY |
| Interior/Exterior Lathing | 5/17/2022 | Partial Approval | EUGENE CASSIDY |
| Insulation | 5/20/2022 | Corrections Issued | EUGENE CASSIDY |
| Drywall Nailing | 6/2/2022 | Approved | EUGENE CASSIDY |
| Interior/Exterior Lathing | 6/2/2022 | Approved | EUGENE CASSIDY |
| BUILDING-Rough-Frame | 7/25/2022 | Not Ready for Inspection | EUGENE CASSIDY |
| Final | 7/25/2022 | Corrections Issued | EUGENE CASSIDY |
| Green Building Final | 7/25/2022 | Not Ready for Inspection | EUGENE CASSIDY |
| Green Building Rough | 7/25/2022 | Approved | EUGENE CASSIDY |
| METHANE-Final | 7/25/2022 | Not Ready for Inspection | EUGENE CASSIDY |
| METHANE-Rough | 7/25/2022 | Approved | EUGENE CASSIDY |
| SGSOV-Seismic Gas S/O Valve | 7/25/2022 | SGSOV Not Ready | EUGENE CASSIDY |
| Smoke Detectors | 7/25/2022 | Not Ready for Inspection | EUGENE CASSIDY |
| BUILDING-Rough-Frame | 8/1/2022 | Approved | EUGENE CASSIDY |
| Final | 8/1/2022 | Corrections Issued | EUGENE CASSIDY |
| Green Building Final | 8/1/2022 | Approved | EUGENE CASSIDY |
| METHANE-Final | 8/1/2022 | Approved | EUGENE CASSIDY |
| METHANE-Rough | 8/1/2022 | Approved | EUGENE CASSIDY |
| SGSOV-Seismic Gas S/O Valve | 8/1/2022 | SGSOV Approved | EUGENE CASSIDY |
| Smoke Detectors | 8/1/2022 | Approved | EUGENE CASSIDY |
| ELECTRICAL-Final | 8/8/2022 | Approved | EUGENE CASSIDY |
| Final | 8/8/2022 | OK to Issue CofO | EUGENE CASSIDY |
| HVAC-Final | 8/8/2022 | Approved | EUGENE CASSIDY |
| PLUMBING-Final | 8/8/2022 | Approved | EUGENE CASSIDY |