2912 S BENTLEY AVE 90064
Certificate Information: 2912 S BENTLEY AVE 90064
- Application / Permit
- 21014-10000-03171
- Plan Check / Job No.
- B21LA11704
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- ADDITION TO DETACHED GARAGE TO CONVERT INTO ADU PER LAMC 12.22 A.33(c) AND (d)
- Permit Issued
- Issued on 9/20/2022
- Issuing Office
- Metro
- Current Status
- CofO Issued on 9/5/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 6/22/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 6/30/2021 | RICARDO RAMIREZ |
| Corrections Issued | 7/6/2021 | RICARDO RAMIREZ |
| Building Plans Picked Up | 7/7/2021 | APPLICANT |
| Applicant returned to address corrections | 5/31/2022 | FERNANDO FLORES |
| Plan Check Approved | 9/20/2022 | DANIEL SANJUAN |
| Issued | 9/20/2022 | APPLICANT |
| CofO in Progress | 9/2/2025 | EVAN COOPER |
| CofO in Progress | 9/2/2025 | EVAN COOPER |
| CofO in Progress | 9/2/2025 | EVAN COOPER |
| Permit Finaled | 9/5/2025 | RICHARD STEINBACH |
| CofO Issued | 9/5/2025 | RICHARD STEINBACH |
| Permit Finaled | 9/5/2025 | RICHARD STEINBACH |
Permit Application Clearance Information
| Address approval | Cleared | 9/14/2021 | CATHERINE ADROVER |
| Construction within easement | Cleared | 12/2/2021 | RIDWAN HARDY |
| Hydrant and Access approval | Cleared | 1/27/2022 | KURT CORRAL |
| Eng Process Fee Ord 176,300 | Cleared | 2/3/2022 | DINAH GARIN |
| Sewer availability | Cleared | 2/4/2022 | DINAH GARIN |
| Grading Pre-Inspection | Cleared | 2/7/2022 | PATRICK MISCHLICH |
| Low Impact Development | Cleared | 5/6/2022 | JULIAN SUNG |
| Roof/Waste drainage to street | Cleared | 5/24/2022 | DINAH GARIN |
| GPI Written Notices | Cleared | 9/20/2022 | RICARDO RAMIREZ |
Contact Information
| Contractor | Sr Maintenance & Management Services Inc; Lic. No.: 959989-B | 9525 STEWART & GRAY ROAD DOWNEY, CA 90241 |
| Engineer | Morales,, Carlos A; Lic. No.: C69972 | 38100 SAN MATEO AVE PALMDALE, CA 93551 |
Inspector Information
| KIRK SANDERS, (310) 914-3896 | Office Hours: 7:00-8:00 AM MON-FRI |
| ARAM AVEDISIAN, (310) 914-3896 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 11/4/2022 | Conditional Approval | JOHNNY MIRANDA |
| Footing/Foundation/Slab | 11/8/2022 | Partial Approval | EVAN COOPER |
| Pre-Inspection | 11/8/2022 | Approved | EVAN COOPER |
| Reinforced Concrete Frame | 11/8/2022 | Partial Approval | EVAN COOPER |
| Deputy Drilled-In Anchors | 11/21/2022 | Conditional Approval | JOHNNY MIRANDA |
| Footing/Foundation/Slab | 11/28/2022 | Corrections Issued | ASHLEY THOMPSON |
| PLUMBING-Rough | 12/27/2022 | Partial Approval | JOHNNY MIRANDA |
| Footing/Foundation/Slab | 2/2/2023 | Approved | JOHNNY MIRANDA |
| Floor/Roof Diaphrgm/Shear Wall | 5/9/2023 | Partial Approval | JOHNNY MIRANDA |
| Green Building Rough | 5/9/2023 | Not Ready for Inspection | JOHNNY MIRANDA |
| MERV13>=Rough | 5/9/2023 | Not Ready for Inspection | JOHNNY MIRANDA |
| BUILDING-Rough-Frame | 5/22/2023 | Not Ready for Inspection | JOHNNY MIRANDA |
| Green Building Rough | 5/22/2023 | Not Ready for Inspection | JOHNNY MIRANDA |
| HVAC-Rough | 5/22/2023 | Not Ready for Inspection | JOHNNY MIRANDA |
| MERV13>=Rough | 5/22/2023 | Not Ready for Inspection | JOHNNY MIRANDA |
| PLUMBING-Rough | 5/22/2023 | Approved | JOHNNY MIRANDA |
| Rough-Elec/Plmb/HVAC | 5/22/2023 | Not Ready for Inspection | JOHNNY MIRANDA |
| Sewer | 5/22/2023 | Approved | JOHNNY MIRANDA |
| Underground Mechanical | 5/22/2023 | Approved | JOHNNY MIRANDA |
| HVAC-Rough | 6/29/2023 | Corrections Issued | DAVID FEILER |
| Interior/Exterior Lathing | 6/29/2023 | Corrections Issued | DAVID FEILER |
| ELECTRICAL-Rough | 7/21/2023 | Approved | JEREMY TODD |
| HVAC-Rough | 7/21/2023 | Approved | JEREMY TODD |
| Interior/Exterior Lathing | 7/21/2023 | Approved | JEREMY TODD |
| BUILDING-Rough-Frame | 10/24/2023 | Approved | JESUS PINEDA |
| Green Building Rough | 10/24/2023 | Approved | JESUS PINEDA |
| MERV13>=Rough | 10/24/2023 | Approved | JESUS PINEDA |
| Insulation | 10/25/2023 | Corrections Issued | JESUS PINEDA |
| Drywall Nailing | 10/30/2023 | Approved | JESUS PINEDA |
| Insulation | 10/30/2023 | Approved | JESUS PINEDA |
| Special/Order Compliance | 4/18/2025 | Not Ready for Inspection | ARAM AVEDISIAN |
| Final | 4/21/2025 | Not Ready for Inspection | MEL KHACHATOURIAN |
| Green Building Final | 4/21/2025 | Not Ready for Inspection | MEL KHACHATOURIAN |
| MERV13>=Final | 4/21/2025 | Not Ready for Inspection | MEL KHACHATOURIAN |
| SGSOV-Seismic Gas S/O Valve | 4/21/2025 | SGSOV Not Ready | MEL KHACHATOURIAN |
| Smoke Detectors | 4/21/2025 | Not Ready for Inspection | MEL KHACHATOURIAN |
| ELECTRICAL-Final | 4/22/2025 | Not Ready for Inspection | MEL KHACHATOURIAN |
| PLUMBING-Final | 4/22/2025 | Not Ready for Inspection | MEL KHACHATOURIAN |
| ELECTRICAL-Rough | 4/24/2025 | No Access for Inspection | ARAM AVEDISIAN |
| ELECTRICAL-Final | 5/1/2025 | Corrections Issued | ARAM AVEDISIAN |
| PLUMBING-Final | 5/1/2025 | Not Ready for Inspection | ARAM AVEDISIAN |
| ELECTRICAL-Final | 5/12/2025 | Approved | ARAM AVEDISIAN |
| Final | 5/12/2025 | Corrections Issued | ARAM AVEDISIAN |
| Green Building Final | 5/12/2025 | Approved | ARAM AVEDISIAN |
| HVAC-Final | 5/12/2025 | Not Ready for Inspection | ARAM AVEDISIAN |
| MERV13>=Final | 5/12/2025 | Not Ready for Inspection | ARAM AVEDISIAN |
| PLUMBING-Final | 5/12/2025 | Not Ready for Inspection | ARAM AVEDISIAN |
| SGSOV-Seismic Gas S/O Valve | 5/12/2025 | SGSOV Not Ready | ARAM AVEDISIAN |
| Smoke Detectors | 5/12/2025 | Approved | ARAM AVEDISIAN |
| Final | 6/6/2025 | Corrections Issued | WILBER ROSALES |
| HVAC-Final | 6/6/2025 | Corrections Issued | WILBER ROSALES |
| MERV13>=Final | 6/6/2025 | Approved | WILBER ROSALES |
| PLUMBING-Final | 6/6/2025 | Approved | WILBER ROSALES |
| SGSOV-Seismic Gas S/O Valve | 6/6/2025 | SGSOV Approved | WILBER ROSALES |
| Service/Power Release | 6/6/2025 | Not Ready for Inspection | WILBER ROSALES |
| HVAC-Final | 7/11/2025 | Corrections Issued | ARAM AVEDISIAN |
| Final | 9/2/2025 | OK to Issue CofO | EVAN COOPER |
| HVAC-Final | 9/2/2025 | Approved | EVAN COOPER |
| Service/Power Release | 9/2/2025 | Approved | EVAN COOPER |