1937 S CAMDEN AVE 90025
Certificate Information: 1937 S CAMDEN AVE 90025
- Application / Permit
- 21014-10000-03166
- Plan Check / Job No.
- B21LA11701
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- GROUND FLOOR ADDITION (72 SF) AT REAR OF (E) SFD, SECOND FLOOR ADDITION (922 SF), AND REMODEL.
- Permit Issued
- Issued on 11/17/2021
- Issuing Office
- Current Status
- CofO Issued on 1/22/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 6/22/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 7/29/2021 | VIVIAN LAO |
| Corrections Issued | 8/5/2021 | VIVIAN LAO |
| Quality Review Completed | 8/12/2021 | MICHAEL PEREZ |
| Applicant returned to address corrections | 10/18/2021 | VIVIAN LAO |
| Applicant returned to address corrections | 10/22/2021 | VIVIAN LAO |
| Plan Check Approved | 11/17/2021 | VIVIAN LAO |
| Issued | 11/17/2021 | APPLICANT |
| Building Plans Picked Up | 11/19/2021 | APPLICANT |
| CofO in Progress | 1/19/2024 | KENNETH NAGLE |
| Permit Finaled | 1/22/2024 | DANIEL ORRANTE |
| CofO Issued | 1/22/2024 | DANIEL ORRANTE |
| Permit Finaled | 1/22/2024 | DANIEL ORRANTE |
Permit Application Clearance Information
| Sewer availability | Cleared | 8/17/2021 | DINAH GARIN |
| Eng Process Fee Ord 176,300 | Cleared | 8/18/2021 | DINAH GARIN |
| Low Impact Development | Cleared | 10/13/2021 | TA ANH |
| Roof/Waste drainage to street | Cleared | 10/15/2021 | DINAH GARIN |
| GPI Written Notices | Cleared | 10/26/2021 | VIVIAN LAO |
| Grading Pre-Inspection | Cleared | 10/26/2021 | VIVIAN LAO |
Contact Information
| Contractor | Jno Construction And Design Inc; Lic. No.: 1051923-B | 750 N SAN VICENTE STE 800 WEST RED WEST HOLLYWOOD, CA 90069 |
Inspector Information
| ANTHONY EGSON, (310) 914-3893 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 1/19/2022 | Corrections Issued | OGANES TARAKHCHYAN |
| Footing/Foundation/Slab | 1/24/2022 | Partial Inspection | KENNETH NAGLE |
| Footing/Foundation/Slab | 2/3/2022 | Corrections Issued | OGANES TARAKHCHYAN |
| Underground Mechanical | 2/15/2022 | Partial Approval | OGANES TARAKHCHYAN |
| Wood Frame | 2/15/2022 | Partial Approval | OGANES TARAKHCHYAN |
| Floor/Roof Diaphrgm/Shear Wall | 2/22/2022 | Partial Approval | OGANES TARAKHCHYAN |
| Floor/Roof Diaphrgm/Shear Wall | 2/28/2022 | Partial Approval | OGANES TARAKHCHYAN |
| Floor/Roof Diaphrgm/Shear Wall | 3/15/2022 | Corrections Issued | OGANES TARAKHCHYAN |
| Floor/Roof Diaphrgm/Shear Wall | 4/7/2022 | Partial Approval | OGANES TARAKHCHYAN |
| Floor/Roof Diaphrgm/Shear Wall | 4/13/2022 | Approved | OGANES TARAKHCHYAN |
| PLUMBING-Rough | 5/9/2022 | Partial Approval | OGANES TARAKHCHYAN |
| HVAC-Rough | 6/16/2022 | Not Ready for Inspection | CARLOS MATAMOROS |
| ELECTRICAL-Rough | 8/2/2022 | Corrections Issued | GERMAN RODRIGUEZ MENDOZA |
| HVAC-Rough | 8/2/2022 | Not Ready for Inspection | GERMAN RODRIGUEZ MENDOZA |
| HVAC-Rough | 8/5/2022 | Not Ready for Inspection | ANDREW NAVE |
| ELECTRICAL-Rough | 8/8/2022 | Approved | JOHN KIDWELL |
| HVAC-Rough | 8/8/2022 | Approved | JOHN KIDWELL |
| PLUMBING-Rough | 8/19/2022 | Approved | JOHN KIDWELL |
| BUILDING-Rough-Frame | 9/12/2022 | Partial Approval | JOHN KIDWELL |
| Green Building Rough | 9/12/2022 | Partial Approval | JOHN KIDWELL |
| Insulation | 10/12/2022 | Not Ready for Inspection | STEPHANIE SWANSON |
| Interior/Exterior Lathing | 10/12/2022 | Partial Approval | STEPHANIE SWANSON |
| Shower Pan | 10/12/2022 | Not Ready for Inspection | STEPHANIE SWANSON |
| BUILDING-Rough-Frame | 10/17/2022 | Corrections Issued | STEPHANIE SWANSON |
| Insulation | 10/17/2022 | Corrections Issued | STEPHANIE SWANSON |
| Shower Pan | 10/17/2022 | Not Ready for Inspection | STEPHANIE SWANSON |
| BUILDING-Rough-Frame | 10/20/2022 | Approved | ASHLEY THOMPSON |
| Green Building Rough | 10/20/2022 | Approved | ASHLEY THOMPSON |
| Insulation | 10/20/2022 | Approved | ASHLEY THOMPSON |
| Shower Pan | 10/20/2022 | Partial Approval | ASHLEY THOMPSON |
| Drywall Nailing | 10/31/2022 | Approved | ASHLEY THOMPSON |
| Interior/Exterior Lathing | 10/31/2022 | Approved | ASHLEY THOMPSON |
| Shower Pan | 10/31/2022 | Approved | ASHLEY THOMPSON |
| ELECTRICAL-Final | 3/24/2023 | Not Ready for Inspection | CLAYTON GRAHAM |
| HVAC-Final | 3/24/2023 | Not Ready for Inspection | CLAYTON GRAHAM |
| Pre-Inspection | 3/24/2023 | Partial Inspection | CLAYTON GRAHAM |
| ELECTRICAL-Final | 3/31/2023 | Corrections Issued | CLAYTON GRAHAM |
| ELECTRICAL-Final | 4/4/2023 | Approved | CLAYTON GRAHAM |
| HVAC-Final | 4/4/2023 | Not Ready for Inspection | CLAYTON GRAHAM |
| PLUMBING-Final | 4/4/2023 | Not Ready for Inspection | CLAYTON GRAHAM |
| Service/Power Release | 4/5/2023 | Approved | RICHARD STEINBACH |
| Final | 8/2/2023 | Partial Approval | MEL KHACHATOURIAN |
| Footing/Foundation/Slab | 8/2/2023 | Approved | MEL KHACHATOURIAN |
| Green Building Final | 8/2/2023 | Approved | MEL KHACHATOURIAN |
| SGSOV-Seismic Gas S/O Valve | 8/2/2023 | SGSOV Approved | MEL KHACHATOURIAN |
| Smoke Detectors | 8/2/2023 | Approved | MEL KHACHATOURIAN |
| Final | 9/7/2023 | Partial Approval | MEL KHACHATOURIAN |
| Final | 1/19/2024 | OK to Issue CofO | KENNETH NAGLE |