3306 1/2 E BESWICK ST 90023
Certificate Information: 3306 1/2 E BESWICK ST 90023
- Application / Permit
- 21014-10000-03165
- Plan Check / Job No.
- B21LA11700
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT EXISTING GARAGE TO ACCESSORY DWELLING UNIT WITH ADDITION PER LAMC 12.22 A.33 (c)-(d)
- Permit Issued
- Issued on 2/10/2023
- Issuing Office
- Metro
- Current Status
- CofO Issued on 3/5/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 6/28/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 7/7/2021 | SINA KHOSRAVI |
| Corrections Issued | 7/8/2021 | SINA KHOSRAVI |
| Building Plans Picked Up | 7/15/2021 | APPLICANT |
| Applicant returned to address corrections | 1/10/2023 | VICTOR CHEN |
| Plan Check Approved | 1/30/2023 | SAMUEL GONZALEZ |
| Issued | 2/10/2023 | APPLICANT |
| CofO in Progress | 3/4/2024 | FREDDIE RIVERA |
| Permit Finaled | 3/5/2024 | DEROLD HAUFF |
| CofO Issued | 3/5/2024 | DEROLD HAUFF |
| Permit Finaled | 3/5/2024 | DEROLD HAUFF |
Permit Application Clearance Information
| Construction near power lines | Cleared | 3/4/2022 | TINA MIRANDA |
| Low Impact Development | Cleared | 10/5/2022 | LUIS LUVANO |
| Address approval | Cleared | 10/27/2022 | CINDY QI |
| Roof/Waste drainage to street | Cleared | 10/31/2022 | CINDY QI |
| Grading Pre-Inspection | Cleared | 11/30/2022 | KIRK LINKLATER |
| Eng Process Fee Ord 176,300 | Cleared | 1/10/2023 | CINDY QI |
| Sewer availability | Cleared | 1/10/2023 | CINDY QI |
Contact Information
| Contractor | S J Construction; Lic. No.: 1031127-B | 1313 BLUFF RD MONTEBELLO, CA 90640 |
| Engineer | Lu,, Yi; Lic. No.: S5678 | P O BOX 2754 PALOS VERDES PENINSULA, CA 90274 |
Inspector Information
| FREDDIE RIVERA, (213) 202-3437 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 3/8/2023 | Conditional Approval | FREDDIE RIVERA |
| Footing/Foundation/Slab | 3/9/2023 | Approved | FREDDIE RIVERA |
| BUILDING-Rough-Frame | 4/11/2023 | Corrections Issued | FREDDIE RIVERA |
| Insulation | 4/11/2023 | Approved | FREDDIE RIVERA |
| PLUMBING-Rough | 4/11/2023 | Partial Approval | FREDDIE RIVERA |
| BUILDING-Rough-Frame | 6/23/2023 | Partial Inspection | FREDDIE RIVERA |
| ELECTRICAL-Rough | 6/23/2023 | Approved | FREDDIE RIVERA |
| Floor/Roof Diaphrgm/Shear Wall | 6/23/2023 | Approved | FREDDIE RIVERA |
| Green Building Rough | 6/23/2023 | Order to Comply Issued | FREDDIE RIVERA |
| MERV13>=Rough | 6/23/2023 | Approved | FREDDIE RIVERA |
| PLUMBING-Rough | 6/23/2023 | Approved | FREDDIE RIVERA |
| Sewer | 6/23/2023 | Approved | FREDDIE RIVERA |
| BUILDING-Rough-Frame | 6/28/2023 | Approved | FREDDIE RIVERA |
| Floor/Roof Diaphrgm/Shear Wall | 6/28/2023 | Approved | FREDDIE RIVERA |
| Green Building Rough | 6/28/2023 | Approved | FREDDIE RIVERA |
| Insulation | 7/5/2023 | Approved | JOSEPH MCGARRY |
| Interior/Exterior Lathing | 7/5/2023 | Partial Approval | JOSEPH MCGARRY |
| Interior/Exterior Lathing | 7/11/2023 | Approved | FREDDIE RIVERA |
| ELECTRICAL-Rough | 8/29/2023 | Partial Inspection | FREDDIE RIVERA |
| Final | 10/20/2023 | Corrections Issued | FREDDIE RIVERA |
| Green Building Final | 10/20/2023 | Corrections Issued | FREDDIE RIVERA |
| MERV13>=Final | 10/20/2023 | Partial Inspection | FREDDIE RIVERA |
| SGSOV-Seismic Gas S/O Valve | 10/20/2023 | SGSOV Not Ready | FREDDIE RIVERA |
| Smoke Detectors | 10/20/2023 | Approved | FREDDIE RIVERA |
| Final | 10/27/2023 | Conditional Approval | FREDDIE RIVERA |
| Green Building Final | 10/27/2023 | Approved | FREDDIE RIVERA |
| MERV13>=Final | 10/27/2023 | Approved | FREDDIE RIVERA |
| SGSOV-Seismic Gas S/O Valve | 10/27/2023 | SGSOV Approved | FREDDIE RIVERA |
| Final | 3/1/2024 | Corrections Issued | FREDDIE RIVERA |
| Final | 3/4/2024 | OK to Issue CofO | FREDDIE RIVERA |