3463 E BESWICK ST 90023
Certificate Information: 3463 E BESWICK ST 90023
- Application / Permit
- 21014-10000-03154
- Plan Check / Job No.
- B21LA11639
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- eplan Convert (E) garage and storage to an A.D.U. and add second story to said A.D.U.
- Permit Issued
- Issued on 1/20/2022
- Issuing Office
- Current Status
- CofO Issued on 1/14/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 6/21/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 7/22/2021 | ARSALAN SHABESTARI |
| Corrections Issued | 7/30/2021 | ARSALAN SHABESTARI |
| Quality Review Completed | 8/10/2021 | MICHAEL PEREZ |
| Plan Check Approved | 1/16/2022 | ARSALAN SHABESTARI |
| Issued | 1/20/2022 | APPLICANT |
| CofO in Progress | 1/10/2023 | FREDDIE RIVERA |
| Permit Finaled | 1/14/2023 | DEROLD HAUFF |
| CofO Issued | 1/14/2023 | DEROLD HAUFF |
| Permit Finaled | 1/14/2023 | DEROLD HAUFF |
Permit Application Clearance Information
| Low Impact Development | Cleared | 9/28/2021 | JORGE MEJIA LEMUS |
| Address approval | Cleared | 12/8/2021 | TREVOR QUAN |
| Roof/Waste drainage to street | Cleared | 12/8/2021 | TREVOR QUAN |
| Eng Process Fee Ord 176,300 | Cleared | 12/9/2021 | TREVOR QUAN |
| Sewer availability | Cleared | 12/9/2021 | TREVOR QUAN |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Maalouf,, Sami; Lic. No.: NA53210 | , |
Inspector Information
| FREDDIE RIVERA, (213) 202-3437 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 3/15/2022 | Partial Inspection | FREDDIE RIVERA |
| Deputy Drilled-In Anchors | 3/23/2022 | Partial Approval | SCOTT FINNILA |
| Footing/Foundation/Slab | 3/23/2022 | Conditional Approval | SCOTT FINNILA |
| Footing/Foundation/Slab | 4/1/2022 | Approved | FREDDIE RIVERA |
| Floor/Roof Diaphrgm/Shear Wall | 4/14/2022 | Partial Approval | FREDDIE RIVERA |
| Floor/Roof Diaphrgm/Shear Wall | 5/2/2022 | Corrections Issued | FREDDIE RIVERA |
| ELECTRICAL-Rough | 6/2/2022 | Approved | FREDDIE RIVERA |
| HVAC-Rough | 6/2/2022 | Approved | FREDDIE RIVERA |
| PLUMBING-Rough | 6/10/2022 | Approved | FREDDIE RIVERA |
| Wood Frame | 6/20/2022 | Approved | FREDDIE RIVERA |
| Insulation | 7/7/2022 | Approved | RYAN SALAZAR |
| Interior/Exterior Lathing | 7/7/2022 | Approved | RYAN SALAZAR |
| Drywall Nailing | 7/11/2022 | Approved | FREDDIE RIVERA |
| Gas Test | 8/1/2022 | Not Ready for Inspection | FREDDIE RIVERA |
| SGSOV-Seismic Gas S/O Valve | 8/1/2022 | SGSOV Not Ready | FREDDIE RIVERA |
| Gas Test | 8/2/2022 | Corrections Issued | MICHAEL LEWIS |
| Gas Test | 8/5/2022 | Partial Approval | FREDDIE RIVERA |
| Gas Test | 8/9/2022 | Approved | FREDDIE RIVERA |
| PLUMBING-Rough | 8/16/2022 | Corrections Issued | FREDDIE RIVERA |
| PLUMBING-Rough | 8/19/2022 | Approved | FREDDIE RIVERA |
| PLUMBING-Rough | 11/7/2022 | Approved | FREDDIE RIVERA |
| BUILDING-Rough-Frame | 11/29/2022 | Conditional Approval | FREDDIE RIVERA |
| Final | 11/29/2022 | Partial Inspection | FREDDIE RIVERA |
| MERV13>=Final | 11/29/2022 | Partial Inspection | FREDDIE RIVERA |
| MERV13>=Rough | 11/29/2022 | Partial Inspection | FREDDIE RIVERA |
| SGSOV-Seismic Gas S/O Valve | 11/29/2022 | SGSOV Not Ready | FREDDIE RIVERA |
| Smoke Detectors | 11/29/2022 | Approved | FREDDIE RIVERA |
| BUILDING-Rough-Frame | 12/20/2022 | Approved | ALIZAH MAYAGOITIA |
| Final | 12/20/2022 | Corrections Issued | ALIZAH MAYAGOITIA |
| MERV13>=Final | 12/20/2022 | Approved | ALIZAH MAYAGOITIA |
| MERV13>=Rough | 12/20/2022 | Approved | ALIZAH MAYAGOITIA |
| SGSOV-Seismic Gas S/O Valve | 12/20/2022 | SGSOV Approved | ALIZAH MAYAGOITIA |
| HVAC-Final | 1/5/2023 | Partial Inspection | FREDDIE RIVERA |
| Final | 1/10/2023 | OK to Issue CofO | FREDDIE RIVERA |
| Service/Power Release | 1/12/2023 | Approved | FREDDIE RIVERA |