3463 E BESWICK ST 90023

Certificate Information: 3463 E BESWICK ST 90023

Application / Permit
21014-10000-03154
Plan Check / Job No.
B21LA11639
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
eplan Convert (E) garage and storage to an A.D.U. and add second story to said A.D.U.
Permit Issued
Issued on 1/20/2022
Issuing Office
Current Status
CofO Issued on 1/14/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/21/2021 APPLICANT
Assigned to Plan Check Engineer 7/22/2021 ARSALAN SHABESTARI
Corrections Issued 7/30/2021 ARSALAN SHABESTARI
Quality Review Completed 8/10/2021 MICHAEL PEREZ
Plan Check Approved 1/16/2022 ARSALAN SHABESTARI
Issued 1/20/2022 APPLICANT
CofO in Progress 1/10/2023 FREDDIE RIVERA
Permit Finaled 1/14/2023 DEROLD HAUFF
CofO Issued 1/14/2023 DEROLD HAUFF
Permit Finaled 1/14/2023 DEROLD HAUFF

Permit Application Clearance Information

Low Impact Development Cleared 9/28/2021 JORGE MEJIA LEMUS
Address approval Cleared 12/8/2021 TREVOR QUAN
Roof/Waste drainage to street Cleared 12/8/2021 TREVOR QUAN
Eng Process Fee Ord 176,300 Cleared 12/9/2021 TREVOR QUAN
Sewer availability Cleared 12/9/2021 TREVOR QUAN

Contact Information

Contractor Owner-Builder       ,
Engineer Maalouf,, Sami; Lic. No.: NA53210       ,

Inspector Information

FREDDIE RIVERA, (213) 202-3437 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 3/15/2022 Partial Inspection FREDDIE RIVERA
Deputy Drilled-In Anchors 3/23/2022 Partial Approval SCOTT FINNILA
Footing/Foundation/Slab 3/23/2022 Conditional Approval SCOTT FINNILA
Footing/Foundation/Slab 4/1/2022 Approved FREDDIE RIVERA
Floor/Roof Diaphrgm/Shear Wall 4/14/2022 Partial Approval FREDDIE RIVERA
Floor/Roof Diaphrgm/Shear Wall 5/2/2022 Corrections Issued FREDDIE RIVERA
ELECTRICAL-Rough 6/2/2022 Approved FREDDIE RIVERA
HVAC-Rough 6/2/2022 Approved FREDDIE RIVERA
PLUMBING-Rough 6/10/2022 Approved FREDDIE RIVERA
Wood Frame 6/20/2022 Approved FREDDIE RIVERA
Insulation 7/7/2022 Approved RYAN SALAZAR
Interior/Exterior Lathing 7/7/2022 Approved RYAN SALAZAR
Drywall Nailing 7/11/2022 Approved FREDDIE RIVERA
Gas Test 8/1/2022 Not Ready for Inspection FREDDIE RIVERA
SGSOV-Seismic Gas S/O Valve 8/1/2022 SGSOV Not Ready FREDDIE RIVERA
Gas Test 8/2/2022 Corrections Issued MICHAEL LEWIS
Gas Test 8/5/2022 Partial Approval FREDDIE RIVERA
Gas Test 8/9/2022 Approved FREDDIE RIVERA
PLUMBING-Rough 8/16/2022 Corrections Issued FREDDIE RIVERA
PLUMBING-Rough 8/19/2022 Approved FREDDIE RIVERA
PLUMBING-Rough 11/7/2022 Approved FREDDIE RIVERA
BUILDING-Rough-Frame 11/29/2022 Conditional Approval FREDDIE RIVERA
Final 11/29/2022 Partial Inspection FREDDIE RIVERA
MERV13>=Final 11/29/2022 Partial Inspection FREDDIE RIVERA
MERV13>=Rough 11/29/2022 Partial Inspection FREDDIE RIVERA
SGSOV-Seismic Gas S/O Valve 11/29/2022 SGSOV Not Ready FREDDIE RIVERA
Smoke Detectors 11/29/2022 Approved FREDDIE RIVERA
BUILDING-Rough-Frame 12/20/2022 Approved ALIZAH MAYAGOITIA
Final 12/20/2022 Corrections Issued ALIZAH MAYAGOITIA
MERV13>=Final 12/20/2022 Approved ALIZAH MAYAGOITIA
MERV13>=Rough 12/20/2022 Approved ALIZAH MAYAGOITIA
SGSOV-Seismic Gas S/O Valve 12/20/2022 SGSOV Approved ALIZAH MAYAGOITIA
HVAC-Final 1/5/2023 Partial Inspection FREDDIE RIVERA
Final 1/10/2023 OK to Issue CofO FREDDIE RIVERA
Service/Power Release 1/12/2023 Approved FREDDIE RIVERA