3721 S NORTON AVE 90018

Certificate Information: 3721 S NORTON AVE 90018

Application / Permit
21014-10000-03142
Plan Check / Job No.
B21LA11615
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
ADDITION TO (E) SFD FOR NEW DINNING AREA WITH NEW TRELLIS ADDITION.
Permit Issued
Issued on 10/7/2021
Issuing Office
Current Status
CofO Issued on 7/15/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/22/2021 APPLICANT
Assigned to Plan Check Engineer 6/30/2021 FARSHAD ALIMOHAMADI
Corrections Issued 7/1/2021 FARSHAD ALIMOHAMADI
Applicant returned to address corrections 8/11/2021 FARSHAD ALIMOHAMADI
Plan Check Approved 9/7/2021 JOSEPH RAFOLS
Issued 10/7/2021 APPLICANT
Building Plans Picked Up 10/8/2021 APPLICANT
CofO in Progress 7/8/2022 ANTHONY EGSON
CofO Issued 7/15/2022 DEROLD HAUFF
Permit Finaled 7/15/2022 DEROLD HAUFF

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 8/2/2021 RENZ SORIANO
Roof/Waste drainage to street Cleared 8/2/2021 RENZ SORIANO

Contact Information

Contractor Owner-Builder       ,
Engineer Kazemi,, Milad; Lic. No.: C92143 21126 MERRIDY STREET      CHATSWORTH, CA 91311

Inspector Information

LUIS CASTRO, (213) 202-3436 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 11/3/2021 Corrections Issued ANTHONY EGSON
Footing/Foundation/Slab 11/23/2021 Not Ready for Inspection ANTHONY EGSON
Footing/Foundation/Slab 12/3/2021 Partial Approval JUSTIN HAWLEY
Insulation 12/16/2021 Partial Approval JOAQUIN GREENOUGH
Floor/Roof Diaphrgm/Shear Wall 12/21/2021 Partial Approval ADAM ESCOTO
BUILDING-Rough-Frame 1/7/2022 Not Ready for Inspection ANTHONY EGSON
Floor/Roof Diaphrgm/Shear Wall 1/7/2022 Approved ANTHONY EGSON
Green Building Rough 1/7/2022 Not Ready for Inspection ANTHONY EGSON
BUILDING-Rough-Frame 2/11/2022 Approved HORACE FULTZ
ELECTRICAL-Rough 2/11/2022 Approved HORACE FULTZ
Green Building Rough 2/11/2022 Approved HORACE FULTZ
Insulation 2/11/2022 Approved HORACE FULTZ
Interior/Exterior Lathing 2/11/2022 Partial Approval HORACE FULTZ
PLUMBING-Rough 2/11/2022 Approved HORACE FULTZ
Drywall Nailing 2/23/2022 Approved ANTHONY EGSON
ELECTRICAL-Final 3/29/2022 Corrections Issued ANTHONY EGSON
Final 3/29/2022 Corrections Issued ANTHONY EGSON
Footing/Foundation/Slab 3/29/2022 Approved ANTHONY EGSON
Green Building Final 3/29/2022 Corrections Issued ANTHONY EGSON
PLUMBING-Final 3/29/2022 Corrections Issued ANTHONY EGSON
SGSOV-Seismic Gas S/O Valve 3/29/2022 SGSOV Approved ANTHONY EGSON
Smoke Detectors 3/29/2022 Approved ANTHONY EGSON
Final 6/6/2022 Conditional Approval ANTHONY EGSON
Green Building Final 6/6/2022 Approved ANTHONY EGSON