112 S CRESCENT HEIGHTS BLVD 90048

Certificate Information: 112 S CRESCENT HEIGHTS BLVD 90048

Application / Permit
21014-10000-03140
Plan Check / Job No.
B21LA11592
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
NEW (15'-6" X 34'-2") ADDITION TO THE REAR OF EXISTING SINGLE FAMILY DWELLING
Permit Issued
Issued on 5/11/2022
Issuing Office
Current Status
CofO Issued on 7/8/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/21/2021 APPLICANT
Assigned to Plan Check Engineer 6/28/2021 FARSHAD ALIMOHAMADI
Corrections Issued 6/29/2021 FARSHAD ALIMOHAMADI
Applicant returned to address corrections 1/5/2022 ZAW HAN
Applicant returned to address corrections 3/31/2022 SINA KHOSRAVI
Applicant returned to address corrections 4/21/2022 TSE MING HUANG
Building Plans Picked Up 5/4/2022 APPLICANT
Plan Check Approved 5/11/2022 CRISTINA SALAZAR
Issued 5/11/2022 APPLICANT
CofO in Progress 6/28/2023 JEREMY TODD
Permit Finaled 7/8/2023 DANIEL ORRANTE
CofO Issued 7/8/2023 DANIEL ORRANTE
Permit Finaled 7/8/2023 DANIEL ORRANTE

Permit Application Clearance Information

Address approval Cleared 7/14/2021 JEANIE LAM
Eng Process Fee Ord 176,300 Cleared 7/14/2021 JEANIE LAM
Sewer availability Cleared 7/15/2021 JEANIE LAM
Low Impact Development Cleared 3/15/2022 TA ANH
Roof/Waste drainage to street Cleared 3/31/2022 AMAAN MALIK

Contact Information

Architect Adams,, Lauren Amanda; Lic. No.: C30146 8695 WASHINGTON BLVD SUITE 205      CULVER CITY, CA 90232
Contractor Letter Four Inc; Lic. No.: 1028949-B 12822 WASHINGTN BLVD      LOS ANGELES, CA 90066
Engineer Kazemi,, Milad; Lic. No.: C92143 21126 MERRIDY STREET      CHATSWORTH, CA 91311

Inspector Information

WILBER ROSALES, (310) 914-3892 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 6/20/2022 Corrections Issued DAVID FEILER
METHANE-Barrier 6/20/2022 Approved DAVID FEILER
METHANE-Subgrade 6/20/2022 Approved DAVID FEILER
Footing/Foundation/Slab 6/29/2022 Approved EVAN COOPER
Deputy Wood Construction 7/8/2022 No Access for Inspection MICHAEL PELHAM
Wood Frame 7/11/2022 Partial Approval EVAN COOPER
PLUMBING-Rough 7/26/2022 Partial Approval GERMAN RODRIGUEZ MENDOZA
Floor/Roof Diaphrgm/Shear Wall 9/16/2022 Partial Approval ANDREW NAVE
ELECTRICAL-Rough 10/12/2022 Approved EVAN COOPER
PLUMBING-Rough 10/12/2022 Approved EVAN COOPER
HVAC-Rough 10/21/2022 Approved EVAN COOPER
BUILDING-Rough-Frame 11/15/2022 Not Ready for Inspection GERMAN RODRIGUEZ MENDOZA
Green Building Rough 11/15/2022 Not Ready for Inspection GERMAN RODRIGUEZ MENDOZA
METHANE-Rough 11/15/2022 Approved GERMAN RODRIGUEZ MENDOZA
Floor/Roof Diaphrgm/Shear Wall 12/14/2022 Partial Approval JEREMY TODD
Interior/Exterior Lathing 1/26/2023 Approved JEREMY TODD
BUILDING-Rough-Frame 1/31/2023 Approved JEREMY TODD
Green Building Rough 1/31/2023 Approved JEREMY TODD
Insulation 1/31/2023 Approved JEREMY TODD
Interior/Exterior Lathing 1/31/2023 Approved JEREMY TODD
Shower Pan 1/31/2023 Approved JEREMY TODD
Drywall Nailing 2/6/2023 Approved JEREMY TODD
Gas Test 3/31/2023 Approved JEREMY TODD
PLUMBING-Final 3/31/2023 Approved JEREMY TODD
SGSOV-Seismic Gas S/O Valve 3/31/2023 SGSOV Approved JEREMY TODD
ELECTRICAL-Final 5/10/2023 Corrections Issued JEREMY TODD
Final 5/10/2023 Not Ready for Inspection JEREMY TODD
Green Building Final 5/10/2023 Approved JEREMY TODD
HVAC-Final 5/10/2023 Approved JEREMY TODD
Smoke Detectors 5/10/2023 Approved JEREMY TODD
ELECTRICAL-Final 5/16/2023 Approved JEREMY TODD
Final 5/16/2023 Corrections Issued JEREMY TODD
Final 6/27/2023 OK to Issue CofO JEREMY TODD
Service/Power Release 6/27/2023 Approved JEREMY TODD