112 S CRESCENT HEIGHTS BLVD 90048
Certificate Information: 112 S CRESCENT HEIGHTS BLVD 90048
- Application / Permit
- 21014-10000-03140
- Plan Check / Job No.
- B21LA11592
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- NEW (15'-6" X 34'-2") ADDITION TO THE REAR OF EXISTING SINGLE FAMILY DWELLING
- Permit Issued
- Issued on 5/11/2022
- Issuing Office
- Current Status
- CofO Issued on 7/8/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 6/21/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 6/28/2021 | FARSHAD ALIMOHAMADI |
| Corrections Issued | 6/29/2021 | FARSHAD ALIMOHAMADI |
| Applicant returned to address corrections | 1/5/2022 | ZAW HAN |
| Applicant returned to address corrections | 3/31/2022 | SINA KHOSRAVI |
| Applicant returned to address corrections | 4/21/2022 | TSE MING HUANG |
| Building Plans Picked Up | 5/4/2022 | APPLICANT |
| Plan Check Approved | 5/11/2022 | CRISTINA SALAZAR |
| Issued | 5/11/2022 | APPLICANT |
| CofO in Progress | 6/28/2023 | JEREMY TODD |
| Permit Finaled | 7/8/2023 | DANIEL ORRANTE |
| CofO Issued | 7/8/2023 | DANIEL ORRANTE |
| Permit Finaled | 7/8/2023 | DANIEL ORRANTE |
Permit Application Clearance Information
| Address approval | Cleared | 7/14/2021 | JEANIE LAM |
| Eng Process Fee Ord 176,300 | Cleared | 7/14/2021 | JEANIE LAM |
| Sewer availability | Cleared | 7/15/2021 | JEANIE LAM |
| Low Impact Development | Cleared | 3/15/2022 | TA ANH |
| Roof/Waste drainage to street | Cleared | 3/31/2022 | AMAAN MALIK |
Contact Information
| Architect | Adams,, Lauren Amanda; Lic. No.: C30146 | 8695 WASHINGTON BLVD SUITE 205 CULVER CITY, CA 90232 |
| Contractor | Letter Four Inc; Lic. No.: 1028949-B | 12822 WASHINGTN BLVD LOS ANGELES, CA 90066 |
| Engineer | Kazemi,, Milad; Lic. No.: C92143 | 21126 MERRIDY STREET CHATSWORTH, CA 91311 |
Inspector Information
| WILBER ROSALES, (310) 914-3892 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 6/20/2022 | Corrections Issued | DAVID FEILER |
| METHANE-Barrier | 6/20/2022 | Approved | DAVID FEILER |
| METHANE-Subgrade | 6/20/2022 | Approved | DAVID FEILER |
| Footing/Foundation/Slab | 6/29/2022 | Approved | EVAN COOPER |
| Deputy Wood Construction | 7/8/2022 | No Access for Inspection | MICHAEL PELHAM |
| Wood Frame | 7/11/2022 | Partial Approval | EVAN COOPER |
| PLUMBING-Rough | 7/26/2022 | Partial Approval | GERMAN RODRIGUEZ MENDOZA |
| Floor/Roof Diaphrgm/Shear Wall | 9/16/2022 | Partial Approval | ANDREW NAVE |
| ELECTRICAL-Rough | 10/12/2022 | Approved | EVAN COOPER |
| PLUMBING-Rough | 10/12/2022 | Approved | EVAN COOPER |
| HVAC-Rough | 10/21/2022 | Approved | EVAN COOPER |
| BUILDING-Rough-Frame | 11/15/2022 | Not Ready for Inspection | GERMAN RODRIGUEZ MENDOZA |
| Green Building Rough | 11/15/2022 | Not Ready for Inspection | GERMAN RODRIGUEZ MENDOZA |
| METHANE-Rough | 11/15/2022 | Approved | GERMAN RODRIGUEZ MENDOZA |
| Floor/Roof Diaphrgm/Shear Wall | 12/14/2022 | Partial Approval | JEREMY TODD |
| Interior/Exterior Lathing | 1/26/2023 | Approved | JEREMY TODD |
| BUILDING-Rough-Frame | 1/31/2023 | Approved | JEREMY TODD |
| Green Building Rough | 1/31/2023 | Approved | JEREMY TODD |
| Insulation | 1/31/2023 | Approved | JEREMY TODD |
| Interior/Exterior Lathing | 1/31/2023 | Approved | JEREMY TODD |
| Shower Pan | 1/31/2023 | Approved | JEREMY TODD |
| Drywall Nailing | 2/6/2023 | Approved | JEREMY TODD |
| Gas Test | 3/31/2023 | Approved | JEREMY TODD |
| PLUMBING-Final | 3/31/2023 | Approved | JEREMY TODD |
| SGSOV-Seismic Gas S/O Valve | 3/31/2023 | SGSOV Approved | JEREMY TODD |
| ELECTRICAL-Final | 5/10/2023 | Corrections Issued | JEREMY TODD |
| Final | 5/10/2023 | Not Ready for Inspection | JEREMY TODD |
| Green Building Final | 5/10/2023 | Approved | JEREMY TODD |
| HVAC-Final | 5/10/2023 | Approved | JEREMY TODD |
| Smoke Detectors | 5/10/2023 | Approved | JEREMY TODD |
| ELECTRICAL-Final | 5/16/2023 | Approved | JEREMY TODD |
| Final | 5/16/2023 | Corrections Issued | JEREMY TODD |
| Final | 6/27/2023 | OK to Issue CofO | JEREMY TODD |
| Service/Power Release | 6/27/2023 | Approved | JEREMY TODD |