213 S LARCHMONT BLVD 90004

Certificate Information: 213 S LARCHMONT BLVD 90004

Application / Permit
21014-10000-03109
Plan Check / Job No.
B21LA11520
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT A PORTION OF EXISTING GARAGE TO ACCESSORY DWELLING UNIT & SMALL ADDITION AT 1ST FLOOR. ADDITION OF RECREATION ROOM AT 2ND FLOOR.
Permit Issued
Issued on 10/21/2021
Issuing Office
Current Status
CofO Issued on 8/6/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/18/2021 APPLICANT
Assigned to Plan Check Engineer 7/22/2021 PRANITA SHAH
Corrections Issued 8/9/2021 PRANITA SHAH
Quality Review Completed 8/16/2021 MICHAEL PEREZ
Plan Check Approved 10/18/2021 PRANITA SHAH
Issued 10/21/2021 APPLICANT
CofO in Progress 7/21/2023 LILIANA PORTILLO
Permit Finaled 8/6/2023 DEROLD HAUFF
CofO Issued 8/6/2023 DEROLD HAUFF
Permit Finaled 8/6/2023 DEROLD HAUFF

Permit Application Clearance Information

HPOZ Cleared 8/26/2021 LAMBERT GIESSINGER
Address approval Cleared 9/1/2021 WALLIE JONG
Roof/Waste drainage to street Cleared 9/1/2021 WALLIE JONG
Eng Process Fee Ord 176,300 Cleared 9/2/2021 WALLIE JONG
Sewer availability Cleared 9/2/2021 WALLIE JONG

Contact Information

Architect Cooke,, Barrett H; Lic. No.: C37365 5239 WINDERMERE AVE      LOS ANGELES, CA 90041
Contractor Owner-Builder       ,
Engineer Rhee,, Kyle; Lic. No.: C78215 2753 WAVERLY DR 403      LOS ANGELES, CA 90039

Inspector Information

RONNIE MINDANAO, (213) 202-3252 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 1/19/2022 Partial Approval ARTHUR SARGSYAN
Footing/Foundation/Slab 2/2/2022 Approved ARTHUR SARGSYAN
METHANE-Barrier 2/2/2022 Approved ARTHUR SARGSYAN
METHANE-Subgrade 2/2/2022 Approved ARTHUR SARGSYAN
Deputy Wood Construction 5/2/2022 Approved ARTHUR SARGSYAN
BUILDING-Rough-Frame 5/23/2022 Not Ready for Inspection ADAM ESCOTO
Floor/Roof Diaphrgm/Shear Wall 5/23/2022 Approved ADAM ESCOTO
HVAC-Rough 5/23/2022 Not Ready for Inspection ADAM ESCOTO
METHANE-Rough 5/23/2022 Approved ADAM ESCOTO
PLUMBING-Rough 5/23/2022 Corrections Issued ADAM ESCOTO
BUILDING-Rough-Frame 6/7/2022 Conditional Approval ADAM ESCOTO
Floor/Roof Diaphrgm/Shear Wall 6/7/2022 Approved ADAM ESCOTO
Interior/Exterior Lathing 6/7/2022 Not Ready for Inspection ADAM ESCOTO
PLUMBING-Rough 6/7/2022 Partial Approval ADAM ESCOTO
Insulation 6/13/2022 Corrections Issued ADAM ESCOTO
Interior/Exterior Lathing 6/13/2022 Approved ADAM ESCOTO
PLUMBING-Rough 6/13/2022 Approved ADAM ESCOTO
Drywall Nailing 6/22/2022 Partial Inspection JOSEPH MCGARRY
Interior/Exterior Lathing 8/15/2022 Approved ALIZAH MAYAGOITIA
Shower Pan 8/15/2022 Approved ALIZAH MAYAGOITIA
BUILDING-Rough-Frame 10/21/2022 Approved MICHAEL LEWIS
Final 10/21/2022 Corrections Issued MICHAEL LEWIS
SGSOV-Seismic Gas S/O Valve 10/21/2022 SGSOV Not Required MICHAEL LEWIS
Smoke Detectors 10/21/2022 Corrections Issued MICHAEL LEWIS
Final 7/11/2023 Corrections Issued LILIANA PORTILLO
Smoke Detectors 7/11/2023 Corrections Issued LILIANA PORTILLO
ELECTRICAL-Final 7/20/2023 Approved LILIANA PORTILLO
Final 7/20/2023 OK to Issue CofO LILIANA PORTILLO
HVAC-Final 7/20/2023 Approved LILIANA PORTILLO
PLUMBING-Final 7/20/2023 Approved LILIANA PORTILLO
Smoke Detectors 7/20/2023 Approved LILIANA PORTILLO