5159 N DAHLIA DR 90041

Certificate Information: 5159 N DAHLIA DR 90041

Application / Permit
21014-10000-03108
Plan Check / Job No.
B21LA11518
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT GARAGE TO ADU WITH GROUND FLOOR ADDITION (1-STORY) TO CREATE DETACHED ADU PER ORDINANCE
Permit Issued
Issued on 1/18/2022
Issuing Office
Current Status
CofO Issued on 9/12/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/18/2021 APPLICANT
Assigned to Plan Check Engineer 7/22/2021 CARLOS MONTES
Corrections Issued 7/25/2021 CARLOS MONTES
Quality Review Completed 7/25/2021 PRANITA SHAH
Plan Check Approved 10/13/2021 CARLOS MONTES
Issued 1/18/2022 APPLICANT
CofO in Progress 8/20/2024 CRAIG VAUGHAN
Permit Finaled 9/12/2024 RUBEN SALAS
CofO Issued 9/12/2024 RUBEN SALAS
Permit Finaled 9/12/2024 RUBEN SALAS

Permit Application Clearance Information

Grading Pre-Inspection Cleared 8/4/2021 BARTON HOLMES
Address approval Cleared 8/11/2021 RENZ SORIANO
Eng Process Fee Ord 176,300 Cleared 8/11/2021 RENZ SORIANO
Roof/Waste drainage to street Cleared 8/11/2021 RENZ SORIANO
Sewer availability Cleared 8/11/2021 RENZ SORIANO

Contact Information

Architect Cooke,, Barrett H; Lic. No.: C37365 5239 WINDERMERE AVE      LOS ANGELES, CA 90041
Contractor Oko Builders Inc; Lic. No.: 1063539-B 369 S DOHENY DR SUITE 116      BEVERLY HILLS, CA 90211
Engineer Rhee,, Kyle; Lic. No.: C78215 2753 WAVERLY DR 403      LOS ANGELES, CA 90039

Inspector Information

RONNIE MEDINA, (213) 469-5852 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 3/7/2022 Partial Approval CRAIG VAUGHAN
Sewer 3/7/2022 Not Ready for Inspection CRAIG VAUGHAN
Footing/Foundation/Slab 3/9/2022 Not Ready for Inspection CRAIG VAUGHAN
Excavation/Setback/Form/Re-Bar 3/11/2022 Approved CRAIG VAUGHAN
Wood Frame 3/24/2022 Partial Approval CRAIG VAUGHAN
ELECTRICAL-Rough 6/9/2022 Approved CRAIG VAUGHAN
HVAC-Rough 6/9/2022 Approved CRAIG VAUGHAN
PLUMBING-Rough 6/9/2022 Not Ready for Inspection CRAIG VAUGHAN
Wood Frame 6/9/2022 Partial Approval CRAIG VAUGHAN
PLUMBING-Rough 6/14/2022 Approved CRAIG VAUGHAN
Wood Frame 6/14/2022 Approved CRAIG VAUGHAN
Insulation 6/17/2022 Approved CRAIG VAUGHAN
Interior/Exterior Lathing 6/24/2022 Partial Approval CRAIG VAUGHAN
Shower Pan 6/24/2022 Approved CRAIG VAUGHAN
Deputy Wood Construction 6/27/2022 Conditional Approval CRAIG VAUGHAN
Interior/Exterior Lathing 6/27/2022 Partial Approval CRAIG VAUGHAN
Drywall Nailing 7/7/2022 Approved CHARLES BOGHOSKHAN
Underground Mechanical 8/5/2022 No Access for Inspection HAMIK HARTOUNIAN
BUILDING-Rough-Frame 2/27/2023 Approved CRAIG VAUGHAN
Final 2/27/2023 Corrections Issued CRAIG VAUGHAN
Footing/Foundation/Slab 2/27/2023 Approved CRAIG VAUGHAN
Green Building Final 2/27/2023 Approved CRAIG VAUGHAN
Green Building Rough 2/27/2023 Approved CRAIG VAUGHAN
SGSOV-Seismic Gas S/O Valve 2/27/2023 SGSOV Approved CRAIG VAUGHAN
Smoke Detectors 2/27/2023 Approved CRAIG VAUGHAN
Final 2/7/2024 Partial Approval ROY SPAULDING
Final 5/16/2024 Conditional Approval CRAIG VAUGHAN
Final 8/19/2024 OK to Issue CofO CRAIG VAUGHAN