3649 S 5TH AVE 90018

Certificate Information: 3649 S 5TH AVE 90018

Application / Permit
21014-10000-03072
Plan Check / Job No.
B21LA11437
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
ePlan Garage conversion to ADU and addition of a story that includes a mezzanine and a bathroom.
Permit Issued
Issued on 6/30/2022
Issuing Office
Current Status
CofO Issued on 6/14/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/16/2021 APPLICANT
Assigned to Plan Check Engineer 7/22/2021 ARSALAN SHABESTARI
Corrections Issued 7/29/2021 ARSALAN SHABESTARI
Quality Review Completed 8/6/2021 MICHAEL PEREZ
Applicant returned to address corrections 1/14/2022 ARSALAN SHABESTARI
Plan Check Approved 5/25/2022 ARSALAN SHABESTARI
Issued 6/30/2022 APPLICANT
CofO in Progress 6/11/2024 JUSTIN HAWLEY
Permit Finaled 6/14/2024 DEROLD HAUFF
CofO Issued 6/14/2024 DEROLD HAUFF
Permit Finaled 6/14/2024 DEROLD HAUFF

Permit Application Clearance Information

HPOZ Cleared 8/2/2021 MAX LODER
Historic monument Cleared 8/2/2021 MAX LODER
Miscellaneous Cleared 8/2/2021 MAX LODER
Miscellaneous Cleared 8/2/2021 MAX LODER
Miscellaneous Cleared 8/2/2021 MAX LODER
Address approval Cleared 8/4/2021 CELINA MORENO
Roof/Waste drainage to street Cleared 8/4/2021 CELINA MORENO
Eng Process Fee Ord 176,300 Cleared 8/9/2021 CELINA MORENO
Sewer availability Cleared 8/9/2021 CELINA MORENO
Hydrant and Access approval Cleared 9/19/2021 JOHN CONNEALLY
Construction near power lines Cleared 12/30/2021 RIDWAN HARDY

Contact Information

Contractor 1 Oak Remodeling; Lic. No.: 1015424-B 6320 VAN NUYS BLVD STE 305      VAN NUYS, CA 91401

Inspector Information

JUSTIN HAWLEY, (213) 202-3432 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 7/21/2022 Corrections Issued STUART CHAPMAN
ELECTRICAL-Rough 5/26/2023 Approved CALEB MEISTER
PLUMBING-Rough 5/26/2023 Corrections Issued CALEB MEISTER
PLUMBING-Rough 6/5/2023 Not Ready for Inspection CALEB MEISTER
Sewer 6/5/2023 Approved CALEB MEISTER
Interior/Exterior Lathing 8/8/2023 Approved CALEB MEISTER
Insulation 8/18/2023 Approved CALEB MEISTER
BUILDING-Rough-Frame 9/27/2023 Approved CALEB MEISTER
Drywall Nailing 9/27/2023 Approved CALEB MEISTER
HVAC-Rough 9/27/2023 Approved CALEB MEISTER
Interior/Exterior Lathing 9/27/2023 Not Ready for Inspection CALEB MEISTER
PLUMBING-Rough 9/27/2023 Approved CALEB MEISTER
Shower Pan 10/19/2023 Approved CALEB MEISTER
Interior/Exterior Lathing 10/27/2023 Approved CALEB MEISTER
Final 5/16/2024 Corrections Issued JUSTIN HAWLEY
Footing/Foundation/Slab 5/16/2024 Approved JUSTIN HAWLEY
SGSOV-Seismic Gas S/O Valve 5/16/2024 SGSOV Not Required JUSTIN HAWLEY
Smoke Detectors 5/16/2024 Not Ready for Inspection JUSTIN HAWLEY
Final 5/28/2024 No Access for Inspection JUSTIN HAWLEY
Smoke Detectors 5/28/2024 No Access for Inspection JUSTIN HAWLEY
Final 5/31/2024 Corrections Issued RICHARD DOCKUS
Smoke Detectors 5/31/2024 Approved RICHARD DOCKUS
ELECTRICAL-Final 6/11/2024 Approved JUSTIN HAWLEY
Final 6/11/2024 OK to Issue CofO JUSTIN HAWLEY
HVAC-Final 6/11/2024 Approved JUSTIN HAWLEY
PLUMBING-Final 6/11/2024 Approved JUSTIN HAWLEY