3642 S BARRY AVE 90066

Certificate Information: 3642 S BARRY AVE 90066

Application / Permit
21014-10000-03059
Plan Check / Job No.
B21LA11399
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERSION AND ADDITION OF GARAGE INTO TWO STORY ADU PER ORDINANCE AND LAMC 12.22 A33(c)&(d).ALL WORK PER ENGINEER DESIGN.
Permit Issued
Issued on 2/11/2022
Issuing Office
Current Status
CofO Issued on 2/16/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/18/2021 APPLICANT
Assigned to Plan Check Engineer 7/8/2021 ZAW HAN
Corrections Issued 7/14/2021 ZAW HAN
Quality Review Completed 7/26/2021 WING SUEN
Applicant returned to address corrections 1/21/2022 ZAW HAN
Plan Check Approved 1/24/2022 ZAW HAN
Plan Check Approved 2/10/2022 ZAW HAN
Issued 2/11/2022 APPLICANT
Building Plans Picked Up 2/11/2022 APPLICANT
CofO in Progress 2/16/2023 DAVID FEILER
Permit Finaled 2/16/2023 DANIEL ORRANTE
CofO Issued 2/16/2023 DANIEL ORRANTE
Permit Finaled 2/16/2023 DANIEL ORRANTE

Permit Application Clearance Information

GPI Written Notices Cleared 9/6/2021 AL GAMBLE
Grading Pre-Inspection Cleared 9/6/2021 AL GAMBLE
Address approval Cleared 9/21/2021 RAYMOND MUGAMBWA
Eng Process Fee Ord 176,300 Cleared 9/21/2021 RAYMOND MUGAMBWA
CPC Cleared 10/1/2021 LAUREN PADICK
CPC Cleared 10/1/2021 LAUREN PADICK
Roof/Waste drainage to street Cleared 10/1/2021 RAYMOND MUGAMBWA
Specific Plan Cleared 10/4/2021 FREDDY GARCIA
Miscellaneous Cleared 10/6/2021 RAYMOND MUGAMBWA
Sewer availability Cleared 10/6/2021 RAYMOND MUGAMBWA

Contact Information

Contractor Owner-Builder       ,
Engineer Lee,, Sang Youck; Lic. No.: S3821 3531 BROOKHILL ST      GLENDALE, CA 91214
Engineer Price,, Mark E; Lic. No.: L7764 18700 WELLHAVEN STREET      CANYON COUNTRY, CA 91351

Inspector Information

KIRK SANDERS, (310) 914-3896 Office Hours: 7:00-8:00 AM MON-FRI
ARAM AVEDISIAN, (310) 914-3896 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 2/23/2022 Not Ready for Inspection JOHNNY MIRANDA
Pre-Inspection 2/23/2022 Approved JOHNNY MIRANDA
PLUMBING-Rough 2/25/2022 Partial Approval JOHNNY MIRANDA
ELECTRICAL-Rough 3/1/2022 Not Ready for Inspection JOHNNY MIRANDA
PLUMBING-Rough 3/1/2022 Partial Approval JOHNNY MIRANDA
Footing/Foundation/Slab 3/3/2022 Corrections Issued JOHNNY MIRANDA
Underground Mechanical 3/3/2022 Partial Approval JOHNNY MIRANDA
PLUMBING-Rough 3/10/2022 Partial Approval JOHNNY MIRANDA
Footing/Foundation/Slab 3/16/2022 Not Ready for Inspection JOHNNY MIRANDA
Footing/Foundation/Slab 3/18/2022 Approved JOHNNY MIRANDA
Masonry Wall/Backfill 3/18/2022 Partial Approval JOHNNY MIRANDA
Masonry Wall/Backfill 3/23/2022 Partial Approval JOHNNY MIRANDA
Masonry Wall/Backfill 3/25/2022 Partial Approval JOHNNY MIRANDA
Floor/Roof Diaphrgm/Shear Wall 4/11/2022 Partial Approval JOHNNY MIRANDA
Floor/Roof Diaphrgm/Shear Wall 4/19/2022 Corrections Issued EVAN COOPER
PLUMBING-Rough 4/22/2022 Not Ready for Inspection JOHNNY MIRANDA
PLUMBING-Rough 4/26/2022 Approved JOHNNY MIRANDA
Floor/Roof Diaphrgm/Shear Wall 4/28/2022 Partial Approval JOHNNY MIRANDA
ELECTRICAL-Rough 5/11/2022 Not Ready for Inspection OGANES TARAKHCHYAN
ELECTRICAL-Rough 5/17/2022 Corrections Issued JOHNNY MIRANDA
Interior/Exterior Lathing 5/17/2022 Partial Approval JOHNNY MIRANDA
HVAC-Rough 5/20/2022 Approved JOHNNY MIRANDA
Insulation 5/24/2022 Approved JOHNNY MIRANDA
Drywall Nailing 5/31/2022 Corrections Issued STEPHANIE SWANSON
ELECTRICAL-Rough 5/31/2022 Corrections Issued STEPHANIE SWANSON
Green Building Rough 5/31/2022 Conditional Approval STEPHANIE SWANSON
Special/Order Compliance 6/2/2022 Partial Inspection KENNETH NAGLE
BUILDING-Rough-Frame 6/3/2022 Approved JOHNNY MIRANDA
Drywall Nailing 6/3/2022 Approved JOHNNY MIRANDA
ELECTRICAL-Rough 6/3/2022 Approved JOHNNY MIRANDA
Green Building Rough 6/3/2022 Approved JOHNNY MIRANDA
Service/Power Release 6/16/2022 Approved JOHNNY MIRANDA
Interior/Exterior Lathing 6/22/2022 Approved JOHNNY MIRANDA
Shower Pan 6/22/2022 Approved JOHNNY MIRANDA
Gas Test 7/6/2022 Approved JOHNNY MIRANDA
Masonry Wall/Backfill 7/26/2022 Partial Approval JOHNNY MIRANDA
Masonry Wall/Backfill 7/29/2022 Partial Approval JOHNNY MIRANDA
Masonry Wall/Backfill 8/2/2022 Approved JOHN KIDWELL
Service/Power Release 8/19/2022 Approved JOHNNY MIRANDA
Gas Test 9/6/2022 Approved JOHNNY MIRANDA
ELECTRICAL-Final 9/12/2022 Corrections Issued DAVID FEILER
Final 9/12/2022 Corrections Issued DAVID FEILER
Footing/Foundation/Slab 9/12/2022 Approved DAVID FEILER
Green Building Final 9/12/2022 Not Ready for Inspection DAVID FEILER
HVAC-Final 9/12/2022 Corrections Issued DAVID FEILER
PLUMBING-Final 9/12/2022 Corrections Issued DAVID FEILER
SGSOV-Seismic Gas S/O Valve 9/12/2022 SGSOV Approved DAVID FEILER
Smoke Detectors 9/12/2022 Approved DAVID FEILER
Green Building Final 9/22/2022 Corrections Issued JOHN KIDWELL
Final 9/29/2022 Corrections Issued JOHNNY MIRANDA
Green Building Final 9/29/2022 Not Ready for Inspection JOHNNY MIRANDA
Final 11/21/2022 Corrections Issued JOHNNY MIRANDA
Green Building Final 11/21/2022 Approved JOHNNY MIRANDA
Final 2/16/2023 OK to Issue CofO DAVID FEILER